Enable Recite

Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Interview | Michel Huguet on the long chain of "fusion builders"

    Some thirty years ago, the ITER Project entered what is called the Engineering Design Activities, a phase which aimed at providing the engineering drawings and [...]

    Read more

  • Assembly | Long-term coil park

    Manufactured in China under a European contract, poloidal field coil #6 (PF6) was the first magnet to be installed in the assembly pit in late April 2021. Saili [...]

    Read more

  • On site | Safety comes first

    Whether they spend their day in an office at ITER or on one of the upper floors of the Tokamak Complex, driving a vehicle or manoeuvring a crane, every per [...]

    Read more

  • Visitors | EU Commissioner for Energy: "ITER is a unique project in frontier science"

    Kadri Simson, European Union Commissioner for Energy, spent Friday 17 September at ITER. In the course of her visit to key site installations and during the pre [...]

    Read more

  • Image of the week | 2nd vacuum vessel sector passes site tests

    On 27 August, the ITER community celebrated the safe arrival of vacuum vessel sector #1(7)—the second of four sectors expected from the Korean Domestic Agency. [...]

    Read more

Of Interest

See archived entries

Sub-assembly tools

One foot inside

The twin Korean giants already have a foot inside the Assembly Hall—literally.

The giant's foot is a 4.4-metre-long steel cylinder that weighs 11 tonnes. It belongs to one of the formidable handling machines that will be used to pre-assemble vacuum vessel sectors with toroidal field coils and thermal shield segments. (Click to view larger version...)
The giant's foot is a 4.4-metre-long steel cylinder that weighs 11 tonnes. It belongs to one of the formidable handling machines that will be used to pre-assemble vacuum vessel sectors with toroidal field coils and thermal shield segments.
The foot—or "bottom inboard column" in ITER parlance—is a 4.4-metre-long steel cylinder that weighs 11 tonnes. It is one of the four segments that, once stacked, will form the central column (and the rotation axis) of the first sector sub-assembly tool (SSAT-1)

Formidable handling machines, twin SSAT tools towering 22 metres above ground will be used to pre-assemble vacuum vessel sectors with toroidal field coils and thermal shield segments.

Preparation for the erection of the first tool began two months ago, with the installation of the base plates for the rail tracks. The rails were temporarily put into position a few days ago to check the interfaces with the plates and to make sure that the bolt holes in both components are perfectly aligned.

Beginning next week installation will begin in earnest and last approximately four months. In March 2018, operational tests, including a load test of 310 tonnes, will be performed on SSAT-1. By that time, the second tool (under fabrication now in Korea) will have been delivered and the first assembly activities initiated.



return to the latest published articles