Sub-assembly tools | One foot inside

Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Cryodistribution | Blowing cold and hot

    If the cryodistribution system were a railroad, the cryogenic termination cold box would be its main switch. A massive structure packed with pipes, valves, elec [...]

    Read more

  • Pre-assembly activities | Captured from on high

    With assembly tools standing 22 metres tall, massive bridge cranes straddling the width of the building, and alien-shaped components placed at regular intervals [...]

    Read more

  • 27th ITER Council | Assembly moves ahead

    The Twenty-Seventh Meeting of the ITER Council took place by videoconference on 18 and 19 November 2020, chaired by LUO Delong from China. Representat [...]

    Read more

  • Fusion world | Translating JET into ITER

    With an inner wall made of beryllium and tungsten, the European tokamak JET is the only tokamak in the world to share the same material environment as ITER. Whe [...]

    Read more

  • Worksite | Major progress you don't see from the air

    There was a time when aerial pictures of the ITER worksite taken at six-month intervals showed spectacular change. Buildings and structures sprouted from previo [...]

    Read more

Of Interest

See archived entries

Sub-assembly tools

One foot inside

The twin Korean giants already have a foot inside the Assembly Hall—literally.

The giant's foot is a 4.4-metre-long steel cylinder that weighs 11 tonnes. It belongs to one of the formidable handling machines that will be used to pre-assemble vacuum vessel sectors with toroidal field coils and thermal shield segments. (Click to view larger version...)
The giant's foot is a 4.4-metre-long steel cylinder that weighs 11 tonnes. It belongs to one of the formidable handling machines that will be used to pre-assemble vacuum vessel sectors with toroidal field coils and thermal shield segments.
The foot—or "bottom inboard column" in ITER parlance—is a 4.4-metre-long steel cylinder that weighs 11 tonnes. It is one of the four segments that, once stacked, will form the central column (and the rotation axis) of the first sector sub-assembly tool (SSAT-1)

Formidable handling machines, twin SSAT tools towering 22 metres above ground will be used to pre-assemble vacuum vessel sectors with toroidal field coils and thermal shield segments.

Preparation for the erection of the first tool began two months ago, with the installation of the base plates for the rail tracks. The rails were temporarily put into position a few days ago to check the interfaces with the plates and to make sure that the bolt holes in both components are perfectly aligned.

Beginning next week installation will begin in earnest and last approximately four months. In March 2018, operational tests, including a load test of 310 tonnes, will be performed on SSAT-1. By that time, the second tool (under fabrication now in Korea) will have been delivered and the first assembly activities initiated.



return to the latest published articles