Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Director-General | Visits and an award in Washington

    Keeping the governments and policy makers of the ITER Members informed on the project's progress and challenges is an essential part of the Director-General's m [...]

    Read more

  • On-site coil winding | Big, round and red

    It's big, round and red and represents the latest addition to the collection of cranes operating on the ITER construction site. On Friday 8 November, two power [...]

    Read more

  • Milestones | Japan completes central solenoid conductor

    The Japanese Domestic Agency has successfully completed the procurement of 43 kilometres (700 tonnes) of niobium-tin cable-in-conduit superconductor for ITER's [...]

    Read more

  • Neutral beam test facility | Powerful ion source delivered

    OnSPIDER, one of twotestbeds at the ITER Neutral Beam Test Facility, the negative ion source for ITER's heating neutral beam system will be demonstrated at full [...]

    Read more

  • Image of the week | Santa's factory

    It may be the thin layer of snow, or the warm lights piercing the night, or just the feeling of the season ... but this aerial view of the ITER site is strongly [...]

    Read more

Of Interest

See archived articles

Building ITER

Halfway to First Plasma

ITER Communication

It's been a long road and we haven't reached our destination yet. But on its way to operation, ITER has just passed a significant milestone: according to the stringent metrics that measure project performance, 50 percent of the "total construction work scope through First Plasma" is now complete.

This view of ''Planet ITER'' shows a worksite teeming with activity. Close to 53% of construction activities on site and manufacturing activities in the ITER Members for components and systems needed for First Plasma have been completed. (Click to view larger version...)
This view of ''Planet ITER'' shows a worksite teeming with activity. Close to 53% of construction activities on site and manufacturing activities in the ITER Members for components and systems needed for First Plasma have been completed.
The performance metrics used in ITER assign a relative weight to every activity category within the project. Design, for instance, accounts for 24 percent; buildings construction and manufacturing for 48 percent; assembly and installation for 20 percent.

After having compounded the percentage of completion of each category, the metrics produce a figure for the totality of the work scope through the launch of operations ("First Plasma"). Design, which accounts for approximately one-fourth of the scope, is now close to 95 percent complete; manufacturing and building, which represents almost half of the total activities is close to 53 percent complete. Do a little math and the result is clear: in terms of activities that need to be completed, ITER is now halfway to its first operational event.

The passing of this milestone reflects "the collective contribution and commitment of ITER's seven Members," writes Director-General Bernard Bigot in a top-level communication to officials in the governments of the participating nations.

The reaction of the world media to the passing of this highly symbolic milestone was unprecedented: close to 600 publications, from a total of 41 countries, hailed the accomplishment. Global news agencies, newspapers and magazines (from the Guardian in the UK to Times of India), radio stations in the Czech Republic and Germany, and countless web sites in the United States, India, the United Arab Emirates, the Philippines or Australia ... all stressed the importance of what is at stake in ITER.

See a selection of articles here.

Read the Statement sent by the Director-General to all ITER Members (in English or in French).
 
Read the full press release in English or in French.
 