Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • ITER DNA | A "case" study...

    In December last year, and again this year in early May, pre-welding fitting tests demonstrated that steel components as tall as a four-storey building (and wei [...]

    Read more

  • First plasma| Temporary in-vessel protection

    The vacuum vessel, the operating theatre of the ITER machine, needs to be protected against possible damage from the hot plasma at any given time during its ope [...]

    Read more

  • Divertor cassettes | Successful prototypes open way to series

    Before embarking on the fabrication of the 54 complex steel structures that will form a ring at the bottom of the ITER machine—the divertor cassettes—the Europe [...]

    Read more

  • Images of the week | Titan tool 90 percent complete

    Towering 22 metres above ground and weighing approximately 800 tonnes, the twin sector sub-assembly tools (SSAT) are formidable handling machines that will be u [...]

    Read more

  • Video | How does the ITER cryoplant work?

    Cold is essential to ITER—10,000 tonnes of superconducting magnets, the thermal shield that surrounds the machine, the cryopumps that achieve the high vacuum in [...]

    Read more

Of Interest

See archived articles

Tokamak Building

The many mirrored room

It's a strange place—a room that could easily accommodate a three-storey building, a star-studded firmament (except these stars are all square), and tall sheets of stainless steel installed on the lower walls. In a few weeks, the floor will receive the same treatment and the place will soon shine like a mirror.

In case of a leak in the tanks, the steel lining will act as a ''drip pan'' to contain contaminated effluents within the room. (Click to view larger version...)
In case of a leak in the tanks, the steel lining will act as a ''drip pan'' to contain contaminated effluents within the room.
Welcome to the drain tank room: 40 metres long, 15 meters wide, and 11 metres high. Located in the lowest basement level (B2) of the Tokamak Complex, the room will accommodate seven large steel containers with volumes ranging from 100 to 210 cubic metres. These water storage tanks are required for normal operation, as well as for the recovery of water from the tokamak cooling water system or the vacuum vessel pressure suppression system in accidental situations.

Like in other areas of the Tokamak Complex, the constellations on the ceiling of this room are formed by the complex arrangement of embedded plates. There are dozens of them, deeply anchored in the reinforced concrete and precisely positioned in order to anchor piping and equipment.

The steel lining on the floor and lower walls is more unusual (1). It will ensure that, in the event of a leak in one of the tanks, contaminated effluents will remain contained within the room.

The 4-millimetre thick steel sheets need to be adjusted and welded with utmost precision in order to ensure leak tightness. (Click to view larger version...)
The 4-millimetre thick steel sheets need to be adjusted and welded with utmost precision in order to ensure leak tightness.
The workers from SEMA, the VFR contractor that is responsible for the installation of the lining, call it a "drip pan" because it acts like the tray one places under roasting meat to collect the drippings.

The lining on the walls is made of 4-millimetre-thick stainless steel sheets that measure 3 metres in height and 1.4 metres in width. Openings need to be cut into most of the sheets to allow access to the embedded plates, and all the sheets need to be adjusted and welded with utmost precision in order to ensure leak tightness. The same procedure will be used to line the 600 square metres of the floor.

Every weld will be checked individually using a number of techniques. One is both sophisticated and simple—a vacuum box containing soapy water that is applied along the weld lengths. In the case of an air leak, bubbles will form.

SEMA began installing the lining in October and the whole "drip pan" should be completed in May.

(1) Cells in the Tritium Building will also be lined with stainless steel.