Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Image of the week | Tokamak-sur-mer

    At the height of the heat wave, in late June, surface temperature on the ITER worksite climbed to the 50 °C range. To continue work—and protect workers—a series [...]

    Read more

  • Space propulsion | Have fusion, will travel

    The idea of propelling rockets and spaceships using the power of the atom is nothing new: the Manhattan Project in the mid-1940s as well as countless endeavours [...]

    Read more

  • Cold fusion | End of story?

    Thirty years ago, two electrochemists at the University of Utah, Martin Fleischmann and Stanley Pons, created a sensation when they claimed they had achieved fu [...]

    Read more

  • Magnet feeders | Wave of deliveries ahead

    Several batches of magnet feeder components will arrive from China in September containing elements that need to be received, inspected and readied for installa [...]

    Read more

  • Tokamak cooling system procurement | Global team for better efficiency

    A unique work-sharing arrangement is expediting the design and fabrication of ITER's tokamak cooling water system and building the knowledge base that will be c [...]

    Read more

Of Interest

See archived entries

Cryostat

Next phase for lower cylinder

At approximately 250 tonnes, the second tier of the ITER cryostat's lower cylinder represents only 15 percent of the cryostat's total weight. Still, in order to weld together its many segments, no less than 1.3 tonnes of filling metal will be required—another amazing figure that opens a window into the unique world of the super-massive ITER components ...

Working in pairs, one man on either side of the massive steel plates, welders will use approximately 1.3 tonnes of filling metal to finalize the welding of the second tier of the cryostat's lower cylinder. (Click to view larger version...)
Working in pairs, one man on either side of the massive steel plates, welders will use approximately 1.3 tonnes of filling metal to finalize the welding of the second tier of the cryostat's lower cylinder.
Following a traditional coconut ceremony, welding operations began on 21 February in the onsite Cryostat Workshop for the second level (tier two) of the lower cylinder.

Operating in tandem, one on either side of the cylinder's steel plates, welders will progressively fill the 5.2-metre-high, 50-millimetre-wide, trough-shaped seams between the segments using a technique called "butt welding." The total length of the welds for this part of the lower cylinder will add up to 160 metres.

Controlling distortions is always an issue when welding large high-tech components. "In the ITER cryostat, because of the number of openings, ports and penetrations and also because of the sheer mass of welds involved, welding is a considerable challenge", explains Vikas Dube, the responsible officer for manufacturing activities in the workshop.

Welding operations on the second tier of the lower cylinder should be complete by late March and the whole assembly (tiers one and two) is expected to be ready for factory acceptance testing in June.

 


return to the latest published articles