Subscribe options

Select your newsletters:

Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Technology | ITER-like disruption mitigation at KSTAR

    Two weeks ago at the Korean tokamak KSTAR, the technology chosen for disruption mitigation at ITER—shattered pellet injection—was tested for the first time in a [...]

    Read more

  • Cooling system | From river to droplets and mist

    A subterranean river runs through the ITER installation. Rushing through 60 kilometres of piping, passing through dozens of pumps, filters and heat exchangers a [...]

    Read more

  • Image of the week | How quickly it goes!

    There are many challenges in communicating ITER and one is to keep pace (from a visual point of view) with the progress of the Tokamak Building. Since this pi [...]

    Read more

  • FEC2020 | Seeking sponsors for 28th IAEA Fusion Energy Conference

    For only the third time since 1961, the International Atomic Energy Agency's Fusion Energy Conference will be taking place in France—hosted jointly by the Frenc [...]

    Read more

  • Nuclear safety | Under constant scrutiny

    Because one of the elements involved in the fusion reaction is the radioactive isotope tritium, and because the hydrogen fusion reaction itself generates a high [...]

    Read more

Of Interest

See archived entries

Tokamak Complex

A temporary roof for the bioshield

In August of last year, a circular platform—the "lid"—was installed deep inside of the ITER bioshield, effectively splitting the well-shaped work area into two. The 140-tonne steel structure was designed to protect the workers active in the basement levels while offering storage for the activities underway on the four above-ground levels.

It took three hours for the eight hydraulic jacks, positioned on platforms anchored to the bioshield wall, to pull the 140-tonne ''lid'' to the top of the massive concrete structure. (Click to view larger version...)
It took three hours for the eight hydraulic jacks, positioned on platforms anchored to the bioshield wall, to pull the 140-tonne ''lid'' to the top of the massive concrete structure.
Now, as teams are preparing for the pouring of the concrete crown and buttressing walls at the lowest level of the Tokamak assembly arena, it was time to hoist the lid some 20 metres to the very top.

The same technique that was used in September 2015 to lift the 800-tonne roof of the Assembly Hall was implemented last Friday 9 March to raise the structure centimetre by centimetre, carefully maintaining its perfectly horizontal position.

The ''lid'' will remain in its present position until April 2020 when it will be removed to allow components into the assembly pit. (Click to view larger version...)
The ''lid'' will remain in its present position until April 2020 when it will be removed to allow components into the assembly pit.
Eight hydraulic jacks—positioned on sturdy platforms distributed around the top of the bioshield—slowly pulled on cables that were attached to the lid in an operation lasting three hours.

The bioshield's new "roof" will remain in its present position until April 2020, when the lid will be removed in preparation for the first components to be delivered for installation by the overhead handling cranes.

Click here to read a related report on the European Domestic Agency website.


return to the latest published articles