Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Vacuum components | Shake, rattle, and... qualify!

    A public-private testing partnership certified that ITER's vacuum components can withstand major seismic events. Making sure the ITER tokamak will be safe in th [...]

    Read more

  • Feeders | Delivering the essentials

    Like a circle of giant syringes all pointing inward, the feeders transport and deliver the essentials to the 10,000-tonne ITER magnet system—that is, electrical [...]

    Read more

  • Image of the week | It's FAB season

    It's FAB season at ITER. Like every year since 2008, the Financial Audit Board (FAB) will proceed with a meticulous audit of the project's finances, siftin [...]

    Read more

  • Disruption mitigation | Final design review is a major step forward

    The generations of physicists, engineers, technicians and other specialists who have worked in nuclear fusion share a common goal, dedication and responsibility [...]

    Read more

  • Image of the week | Like grasping a bowl of cereal

    Contrary to the vast majority of ITER machine components, the modules that form the central solenoid cannot be lifted by way of hooks and attachments. The 110-t [...]

    Read more

Of Interest

See archived entries

Tokamak Complex

A temporary roof for the bioshield

In August of last year, a circular platform—the "lid"—was installed deep inside of the ITER bioshield, effectively splitting the well-shaped work area into two. The 140-tonne steel structure was designed to protect the workers active in the basement levels while offering storage for the activities underway on the four above-ground levels.

It took three hours for the eight hydraulic jacks, positioned on platforms anchored to the bioshield wall, to pull the 140-tonne ''lid'' to the top of the massive concrete structure. (Click to view larger version...)
It took three hours for the eight hydraulic jacks, positioned on platforms anchored to the bioshield wall, to pull the 140-tonne ''lid'' to the top of the massive concrete structure.
Now, as teams are preparing for the pouring of the concrete crown and buttressing walls at the lowest level of the Tokamak assembly arena, it was time to hoist the lid some 20 metres to the very top.

The same technique that was used in September 2015 to lift the 800-tonne roof of the Assembly Hall was implemented last Friday 9 March to raise the structure centimetre by centimetre, carefully maintaining its perfectly horizontal position.

The ''lid'' will remain in its present position until April 2020 when it will be removed to allow components into the assembly pit. (Click to view larger version...)
The ''lid'' will remain in its present position until April 2020 when it will be removed to allow components into the assembly pit.
Eight hydraulic jacks—positioned on sturdy platforms distributed around the top of the bioshield—slowly pulled on cables that were attached to the lid in an operation lasting three hours.

The bioshield's new "roof" will remain in its present position until April 2020, when the lid will be removed in preparation for the first components to be delivered for installation by the overhead handling cranes.

Click here to read a related report on the European Domestic Agency website.


return to the latest published articles