Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Image of the week | Tokamak-sur-mer

    At the height of the heat wave, in late June, surface temperature on the ITER worksite climbed to the 50 °C range. To continue work—and protect workers—a series [...]

    Read more

  • Space propulsion | Have fusion, will travel

    The idea of propelling rockets and spaceships using the power of the atom is nothing new: the Manhattan Project in the mid-1940s as well as countless endeavours [...]

    Read more

  • Cold fusion | End of story?

    Thirty years ago, two electrochemists at the University of Utah, Martin Fleischmann and Stanley Pons, created a sensation when they claimed they had achieved fu [...]

    Read more

  • Magnet feeders | Wave of deliveries ahead

    Several batches of magnet feeder components will arrive from China in September containing elements that need to be received, inspected and readied for installa [...]

    Read more

  • Tokamak cooling system procurement | Global team for better efficiency

    A unique work-sharing arrangement is expediting the design and fabrication of ITER's tokamak cooling water system and building the knowledge base that will be c [...]

    Read more

Of Interest

See archived entries

On site

A runway for the cryostat

Kirsten Haupt

A section of runway-worthy tarmac has been completed at ITER. But no plane will ever land here.

Workers of the French company Colas finalize the surfacing by spreading concrete grout. The work was carried out under the responsibility of Fusion for Energy (F4E), the European Domestic Agency, and supervised by Engage, F4E's architect-engineer contractor. (Click to view larger version...)
Workers of the French company Colas finalize the surfacing by spreading concrete grout. The work was carried out under the responsibility of Fusion for Energy (F4E), the European Domestic Agency, and supervised by Engage, F4E's architect-engineer contractor.
On three consecutive evenings last summer, work proceeded into the night to finalize the surfacing on a 5,000 m² area near the Cryostat Workshop. The road works were carried out to prepare for the relocation of a completed section of the ITER cryostat—the 490-tonne lower cylinder—from the workshop to a dedicated storage area on the platform.

The combined weight of the cryostat section and its transport vehicle calls for airfield-grade paving materials. While regular roads have a load-bearing capacity of 5 tonnes per cubic metre, the surface in front of the Cryostat Workshop needs to withstand higher pressures of up to 20 tonnes per cubic metre. And like on airfields, the new pavement also has a higher resistance for turning loads.

In front of the 30-metre doors of the Cryostat Workshop, the surface has been reinforced to prepare for the removal of the first completed section—the 490-tonne lower cylinder. (Click to view larger version...)
In front of the 30-metre doors of the Cryostat Workshop, the surface has been reinforced to prepare for the removal of the first completed section—the 490-tonne lower cylinder.
A combination of specially designed materials ensures that the road surfacing—while only 15 centimetres thick—has the required properties. The compacted 11-centimetre-thick base layer consists of Optibase, an asphalt of a particular formulation developed for heavy-load roads. This has been topped with a thin layer of highly permeable asphalt. In a final step, workers spread a reinforcing concrete grout across the entire asphalt surface, allowing it to seep into all the cracks and open spaces. 

The surface in front of the Cryostat Workshop is now ready for the relocation of the lower cylinder to the nearby storage area, making space for the upper cylinder that will be assembled next.

It is only the first area on the platform that has been upgraded to airfield-like tarmac. Other roads on the platform will follow suit in receiving this treatment once the work on the underground service networks in those areas has been completed. This will include the stretch of road near the Cleaning Building as well as the roads leading to the Poloidal Field Coils Winding Facility and around the cryoplant.


return to the latest published articles