Central solenoid | Module #1 nears completion

Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Augmented reality | Assessing the future work environment

    As part of their collaboration within the Site Support Agreement*, ITER and its neighbour CEA are developing a novel approach to explore, analyze and assess the [...]

    Read more

  • Diagnostics and instrumentation | First welding on the vacuum vessel

    Beginning in 2035, ITER will open a window into "burning plasmas"—a state of matter that exists in the core of stars only. Observing, assessing and mo [...]

    Read more

  • Assembly | Machining workshop opens on site

    Construction of an on-site machining workshop began in December 2019 and was completed on schedule in September 2020.The new workshop will be operated by the D [...]

    Read more

  • Neutral Beam Test Facility | Power is ready for the prototype injector

    The European Domestic Agency has carried out successful site acceptance tests at the ITER Neutral Beam Test Facility on power supply equipment installed ov [...]

    Read more

  • In-vessel coils | First components arrive on site

    ITER has received the first shipments of mineral-insulated conductor for ITER's in-vessel coils. The first lengths are destined for winding and bending trials a [...]

    Read more

Of Interest

See archived entries

Central solenoid

Module #1 nears completion

US ITER and contractor General Atomics recently achieved a major milestone in the fabrication of the ITER central solenoid, completing vacuum pressure impregnation (VPI) on the first production module. The VPI process is the penultimate step of fabrication that turns almost 6 km of carefully wound superconducting conductor into a structurally strong, electrically insulated electromagnet.
The module fabrication team at the General Atomics Magnet Technology Center in Poway, California. Six stacked modules will form the 1,000-tonne central solenoid magnet. Photo: GA (Click to view larger version...)
The module fabrication team at the General Atomics Magnet Technology Center in Poway, California. Six stacked modules will form the 1,000-tonne central solenoid magnet. Photo: GA
"Completion of VPI is a critical step in the process and the team worked diligently and with great care to insure its success," said John Smith, project manager for General Atomics. "The first production unit now looks like a central solenoid module, and it won't be too much longer before it is complete and begins to function as one."

The central solenoid, often called the "heart of ITER," is essential for operation, serving to initiate plasma and generate the necessary current for plasma heating and sustainment. Six modules will be stacked to form the 1,000-tonne central solenoid, which will be the largest pulsed superconducting magnet in the world when it is complete. General Atomics is under contract to US ITER to fabricate the six modules plus one spare.

During vacuum pressure impregnation, the team evacuates a rigid mold encasing the coil and injects a three-part epoxy mixture to impregnate the insulation materials wrapped around each conductor turn, plus the ground insulation around the module itself. The epoxy provides both electrical insulation and structural support to the module. In a final fabrication step, piping is added and the assembly undergoes final testing.

Fabrication of the modules began in 2016 at the General Atomics Magnet Technologies Center in Poway, California. The manufacturing process takes approximately 22-24 months per module plus an additional 5-6 months of testing. Five modules are currently in various stages of production.

General Atomics has been a pioneer in fusion research and development for over 50 years and is also home to the DIII-D National Fusion Facility, funded by the Department of Energy through the Office of Fusion Energy Sciences.


return to the latest published articles