Enable Recite

Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Cryoplant | First steps toward commissioning

    Every week since the beginning of November, a tube trailer filled with approximately 4,600 cubic metres (750 kg) of compressed gaseous helium delivers its load [...]

    Read more

  • Training | Seeking the next group of Monaco-ITER Fellows

    Recruitment opens for the next Monaco-ITER Postdoctoral Fellowship campaign on 17 January 2022. If your PhD was awarded after 1 January 2019—or you are about to [...]

    Read more

  • Contemporary art | Venet's "arcs" are as heavy as ITER coils

    A 'conceptual artist' among the most prominent on the art scene today, Bernar Venet is not impressed by massive towering steel structures like those in the ITER [...]

    Read more

  • Image of the week | Final activities on Europe's first sector

    The first vacuum vessel sector produced in Europe will arrive at ITER next year. Five of ITER's nine vacuum vessel sectors are the responsibility of Europe's AM [...]

    Read more

  • Vacuum vessel sector preparation | Lessons learned reduce work time by half

    In life as in the assembly of the ITER machine, 'lessons learned' are what makes progress possible. Gains in wisdom, time, skill, investment can be incremental; [...]

    Read more

Of Interest

See archived entries

Winding facility

Lots happening

Activity is underway in all areas of Europe's 257-metre-long winding facility, as the elements of poloidal field coil #5 (PF5) are advancing through the impregnation and stacking phases, and the winding tables have begun to turn again for PF2.
 

 (Click to view larger version...)
Winding: With a few adaptations, the equipment set up to wind the first production coil, PF5, can serve again to wind the double pancakes required for PF2, as both coils measure 17 metres in diameter. However the two coils are siblings, not twins. They differ in the number of turns, or spires, per double pancake (10 for PF2; 14 for PF5) and in the number of double pancakes per coil (6 for PF2; 8 for PF5). As a consequence, PF5 will be much heavier than PF2—350 tonnes vs 204 tonnes. In February, European contractors began winding the first double pancake for PF2.
 
 (Click to view larger version...)
Stacking: Following vacuum pressure impregnation (VPI) with epoxy resin—a process that imparts rigidity to the double pancake and ensures electrical insulation—the double pancakes are stacked to form the coil. For PF5, five out of a total of eight double pancakes have successfully completed VPI and are now stacked. The teams must then connect the pancakes to ensure the flow of cryogenic helium—both between the double layers of each pancake (an "intra pancake joint"), and between each double pancakes (an "inter pancake joint").
 
 (Click to view larger version...)
Dummy: Once all double pancakes are stacked and joined, another VPI resin-impregnation operation is performed on the entire assembly to create the "winding pack"—the very core of the coil. Just like for the earlier impregnation operation on individual double pancakes, the operation contributes both to electrical insulation and structural strength. The procedure will be tested on this short mockup section of a dummy PF5 winding pack.
 
 (Click to view larger version...)
Cold testing: At the end of the manufacturing process, the completed coil is placed into a toroidal vacuum chamber (or "cryostat") and cooled to cryogenic temperature in order to monitor thermal stresses and detect potential leaks in the helium piping. The large cryostat for PF5 and PF2 is already assembled (background); a smaller one is under construction in the foreground for PF6—the 10-metre-in-diameter coil that is being manufactured in China under a contract from Europe. PF6 is expected to be delivered to ITER in November.



return to the latest published articles