Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • "Friendship Award"| China honours ITER Director-General

    Last week, ITER Director-General Bernard Bigot was one of 100 foreign experts from 31 countries to be awarded China's Government Friendship Award. The Governm [...]

    Read more

  • Disruption mitigation | First tests with JET's shattered pellet injector

    A shattered pellet injector—a device which pre-empts plasma disruptions by releasing a spray of frozen deuterium-neon pellets into a plasma—is now in testing on [...]

    Read more

  • Image of the week | 12 pillars and counting

    Two rows of pillars have now appeared at the top of the ITER Tokamak Building—12 out of 20 base pillars that will soon be topped by a second level of pillars, a [...]

    Read more

  • Blanket first wall | Qualification program concludes in Europe

    Directly facing the heat and high-energy neutrons produced during fusion is the first wall of the ITER blanket—440 beryllium-coated, detachable panels that will [...]

    Read more

  • Software | ITER's healthy reliance on open source

    A long-time user of open source, ITER does not stand alone—far from it. Virtually all Big Science projects in the world are big users of public domain software. [...]

    Read more

Of Interest

See archived entries

Assembly tools

Titan moves its little finger

A few days ago, one of the Titans in the Assembly Hall woke up and flexed its little finger. The movement was slow, almost imperceptible. Like in a living body, nerves and muscles (in the form of signal cables and hydraulic pumps) coordinated their action to lift and lower one of the upper alignment units at the top of the giant sector sub-assembly tool—one of the first steps in the mechanical tests program being performed on the spectacular, 20-metre high twin Titans.

No fewer than 20 hydraulic cylindrical rods actuated by hydraulic/pneumatic forces enable the giant tool to adjust the different elements of the pre-assembly with millimetric accuracy. The hydraulic fluid circulates between dozens of pumps throughout a 500-metre-long network of pipes. (Click to view larger version...)
No fewer than 20 hydraulic cylindrical rods actuated by hydraulic/pneumatic forces enable the giant tool to adjust the different elements of the pre-assembly with millimetric accuracy. The hydraulic fluid circulates between dozens of pumps throughout a 500-metre-long network of pipes.
The sector sub-assembly tools (SSAT) are the largest tools in the ITER assembly panoply. Their task is to pre-assemble a vacuum vessel sector with its thermal shield and two toroidal field coils. Opening and closing their arms, adjusting the position of their upper and lower alignment units, they will repeat sub-assembly operations nine times, once for each of the Tokamak's nine vacuum vessel sectors.

The pre-assemblies, weighing approximately 1,200 tonnes, will then be transferred to the assembly pit by way of a double overhead gantry crane to be integrated into the machine.

Before this can happen, however, two major milestones need to be accomplished: the completion of full mechanical and load tests on both SSATs, and the erection of a steel structure over of the Tokamak Building to "close over" the Tokamak Pit and allow the Assembly Hall crane bays to be extended.

Load tests are scheduled to begin in early June, and preparation work has already started for the extension of the crane bays.

Click here to view a video of the Titan's awakening.


return to the latest published articles