Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Crane operator | A cabin in the sky

    There are times, at dusk, when the ITER construction platform resembles an airport, with roads and buildings illuminated by yellow and white lights. From their [...]

    Read more

  • Assembly | A colossal task made manageable

    For the execution of work during the next project phase—machine and plant assembly up to First Plasma—the ITER Organization has chosen a contractual approach th [...]

    Read more

  • Neutral Beam Test Facility | A new agreement for a new era

    The ITER Organization and the Italian consortium Consorzio RFX* have signed a new agreement governing the construction and operation of the ITER Neutral Beam Te [...]

    Read more

  • Load tests | Heavyweight champion

    The Assembly Hall, with its two giant tools towering 20 metres above ground, is one of the most spectacular locations on the ITER site. When a dummy load weighi [...]

    Read more

  • Fusion's new pioneers | How to go fast enough to make a difference

    Last month in New York, the Stellar Energy Foundation and the Fusion Industry Association co-hosted an invitation-only workshop: 'Roadmap to the Fusion Energy E [...]

    Read more

Of Interest

See archived entries

Assembly tools

Titan moves its little finger

A few days ago, one of the Titans in the Assembly Hall woke up and flexed its little finger. The movement was slow, almost imperceptible. Like in a living body, nerves and muscles (in the form of signal cables and hydraulic pumps) coordinated their action to lift and lower one of the upper alignment units at the top of the giant sector sub-assembly tool—one of the first steps in the mechanical tests program being performed on the spectacular, 20-metre high twin Titans.

No fewer than 20 hydraulic cylindrical rods actuated by hydraulic/pneumatic forces enable the giant tool to adjust the different elements of the pre-assembly with millimetric accuracy. The hydraulic fluid circulates between dozens of pumps throughout a 500-metre-long network of pipes. (Click to view larger version...)
No fewer than 20 hydraulic cylindrical rods actuated by hydraulic/pneumatic forces enable the giant tool to adjust the different elements of the pre-assembly with millimetric accuracy. The hydraulic fluid circulates between dozens of pumps throughout a 500-metre-long network of pipes.
The sector sub-assembly tools (SSAT) are the largest tools in the ITER assembly panoply. Their task is to pre-assemble a vacuum vessel sector with its thermal shield and two toroidal field coils. Opening and closing their arms, adjusting the position of their upper and lower alignment units, they will repeat sub-assembly operations nine times, once for each of the Tokamak's nine vacuum vessel sectors.

The pre-assemblies, weighing approximately 1,200 tonnes, will then be transferred to the assembly pit by way of a double overhead gantry crane to be integrated into the machine.

Before this can happen, however, two major milestones need to be accomplished: the completion of full mechanical and load tests on both SSATs, and the erection of a steel structure over of the Tokamak Building to "close over" the Tokamak Pit and allow the Assembly Hall crane bays to be extended.

Load tests are scheduled to begin in early June, and preparation work has already started for the extension of the crane bays.

Click here to view a video of the Titan's awakening.


return to the latest published articles