Enable Recite

Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Remembering Bernard Bigot, ITER Director-General 2015-2022

    On the ITER site, the machinery of construction was humming just like on any weekday. Workers were concentrating on their tasks, laying rebar for new buildings [...]

    Read more

  • Tokamak assembly | Preparing for the Big Lift

    The distance was short but the challenge daunting: on Thursday last week, the first section of the plasma chamber was lifted 50 centimetres above its suppor [...]

    Read more

  • Image of the week | 13th toroidal field coil arrives from Europe

    The toroidal field coil procurement effort has been one of the longest of the ITER program, initiated by Procurement Arrangements signed in 2007 and 2008. Manuf [...]

    Read more

  • Diagnostics | Final Procurement Arrangement signed

    ITER Diagnostics reached an important milestone in December 2021 when it concluded the last Procurement Arrangement of the diagnostics program. After signing a [...]

    Read more

  • On site | A quick visit to the Control Building

    Work is progressing on the ITER Control Building, ergonomically designed for the 60 to 80 operators, engineers and researchers who will call it home.  [...]

    Read more

Of Interest

See archived entries

Lower cylinder

Surveyed from every angle

Metrologists have performed the first "as-built" survey of a completed ITER component—the cryostat lower cylinder—before it was wrapped for outside storage.

ITER's Lionel Poncet (right) and Giacomo Calchi of the European Domestic Agency Fusion for Energy, F4E, perform a surface scan of a port opening inside the cryostat's lower cylinder. The ITER Organization and F4E enjoy an efficient resource-sharing collaboration in the area of metrology. (Click to view larger version...)
ITER's Lionel Poncet (right) and Giacomo Calchi of the European Domestic Agency Fusion for Energy, F4E, perform a surface scan of a port opening inside the cryostat's lower cylinder. The ITER Organization and F4E enjoy an efficient resource-sharing collaboration in the area of metrology.
At the completion of every major ITER component, metrological surveys will be performed to identify variations in the "as-built" dimensions with respect to design. The information is critical to the final assembly of the component in the machine and to the connection of interfacing components and systems.

Javier Fuentes leads the As-Built Data Management Working Group that manages the process. "We need to assess the impact of a component's actual dimensions on interfacing systems and decide on a case-by-case basis if the systems can be used as designed or whether they require adaptation."

All measurement tasks require a fixed reference base (or datum) from which measurements can be made and calculated. For large-volume metrology applications, the reference base typically takes the form of a 3D coordinate system that consists of a collection of target "nests" and/or instrument stations that have known geometry and uncertainty.

At the start of the as-built survey on the cryostat lower cylinder, which took place in March, metrology experts placed 53 fixed nests, also called "fiducials" or "target points," inside the structure and established the fixed points for laser tracker stations. The stations then served as a reference base for hand-held laser scanners. 

Equipped with calibrated cameras, the hand-held laser scanners can measure the exact distance to the scanned object and place it within the network of known coordinates. Operators used laser scanners to conduct not only spot measurements but also complete sweeps of large areas of the lower cylinder's surface.

Metrologists also collected information on "drifting"—or dimensional changes due to the thermal expansion or contraction of materials. Eight sensors were distributed on the inner shell of the lower cylinder to record temperature, and scanner measurements were automatically adjusted to compensate for deviations from the reference temperature of 20 °C.

Computer analysis of all this information makes it possible to establish the precise location of the scanned areas in three-dimensional space and thus establish exact "as-built" measurements. 

"It's the first time that we conducted this type of scanning survey," says metrology engineer Lionel Poncet. High-priority areas of the cryostat lower cylinder were charted first, including the interface areas for one neutral beam penetration, several cryopumps and a number of port openings.

Metrology Group Leader David Wilson assessed the results: "The survey met the requirements for measurement uncertainty which is in the range of 0.5 millimeters—a tiny value considering the size of the lower cylinder."

The outstanding measurements, including of the complete lower cylinder shell, will be performed before the component's installation in the Tokamak Building.

Click here to view a video of the cryostat lower cylinder being moved into storage.


return to the latest published articles