Subscribe options

Select your newsletters:

Please enter your email address:

@

News & Media

Latest ITER Newsline

  • FEC2020 | Seeking sponsors for 28th IAEA Fusion Energy Conference

    For only the third time since 1961, the International Atomic Energy Agency's Fusion Energy Conference will be taking place in France—hosted jointly by the Frenc [...]

    Read more

  • Nuclear safety | Under constant scrutiny

    Because one of the elements involved in the fusion reaction is the radioactive isotope tritium, and because the hydrogen fusion reaction itself generates a high [...]

    Read more

  • Power conversion | Alien structures and strange contraptions

    There are places in ITER that seem to belong to another world, places full of alien structures and strange contraptions. The feeling—a mixture of awe and puzzle [...]

    Read more

  • Tokamak Complex | A changing landscape

    For the past three years, the view from the top of the highest worksite crane has not changed much. Inside of the Tokamak Complex, 80 metres below, concrete gal [...]

    Read more

  • Ion cyclotron heating | How to pump 20 MW of power into 1 gram of plasma

    To power the ion cyclotron system, the ITER Organization and its partners are designing not only new antennas, which will be housed in the tokamak vessel, but a [...]

    Read more

Of Interest

See archived entries

Cryostat

It's happening in the workshop

On a cold night in December 2015, a three-trailer convoy passed through the village of Saint-Paul-lez-Durance, adding its pulsating blue and orange lights to the Christmas illuminations. The convoy carried three 50-tonne steel pieces shaped like so many slices of pie—the first elements of the cryostat base to be assembled on site in the Cryostat Workshop.

Resembling a soup dish, or an upside down hat, the cryostat base is the heaviest single component of the ITER machine. It is also the first major lift of the ITER assembly phase. By March 2020, the completion of the Tokamak Building roof and the extension of the assembly crane rails will permit this component to be installed in the Tokamak Pit. (Click to view larger version...)
Resembling a soup dish, or an upside down hat, the cryostat base is the heaviest single component of the ITER machine. It is also the first major lift of the ITER assembly phase. By March 2020, the completion of the Tokamak Building roof and the extension of the assembly crane rails will permit this component to be installed in the Tokamak Pit.
Two-and-a-half years later, "physical work" on the 1,250-tonne subcomponent is now finalized. Taking over from the Indian Domestic Agency, which is responsible for the procurement of the cryostat, the ITER Organization will soon proceed with "pre-assembly work" prior to installing the component in the Tokamak Pit in May 2020.

Pre-assembly work will consist of welding handling and support systems to the base structure, attaching 18 bellows under the component's skirt to connect the machine to the cooling water system, and installing a monorail and small trolley to handle the clamps, shins and other elements needed to interface with the building.

Work has begun in the workshop on the cryostat upper cylinder. Several of the first-tier segments have already been unwrapped and installed on the assembly platform. (Click to view larger version...)
Work has begun in the workshop on the cryostat upper cylinder. Several of the first-tier segments have already been unwrapped and installed on the assembly platform.
With the base completed and the lower cylinder safely encased in its protective cocoon, activity in the Cryostat Workshop is now focused on the upper cylinder. In less than two weeks, three out of six tier-one segments have been positioned on their assembly frame. Due largely to the lessons learned in the assembly and welding of the lower cylinder, work is progressing at an exceptionally fast pace.

See the gallery below for more details.
 
 


return to the latest published articles