Enable Recite

Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Cryolines | Out through the door, in through the roof

    Cooling fluids for the machine's magnets, thermal shield and cryopumps will travel to the Tokamak Building through a set of large multi-process pipes (cryolines [...]

    Read more

  • Image of the week | Next in line

    Of six ring-shaped coils required for the ITER Tokamak, poloidal field coil #6 (PF6) is the heaviest (400 tonnes) and the second smallest, with a diameter of 10 [...]

    Read more

  • Assembly tools | Strong base for a very heavy task

    The first part of the in-pit assembly tool has been installed in the Tokamak pit. When complete, the tool will stand more than 20 metres high and branch out in [...]

    Read more

  • Diagnostics | A stowaway on board toroidal field coil #8

    Hidden inside the steel case of the most recent toroidal field coil delivered to ITER—TF8, from Japan—is a unique and critical diagnostic device. Named after th [...]

    Read more

  • Vacuum vessel sector | A 90° tilt in mid-air

    Ever since ITER entered the machine assembly phase, some ten months ago, we have been treated to a few spectacular lifting operations. In May 2020, we watched t [...]

    Read more

Of Interest

See archived entries

Assembly Hall

Another massive handling tool

Inside of the Assembly Hall, some of ITER's heaviest components will have to be raised ever so carefully from their horizontal delivery positions to vertical. This delicate operation is the job of the "upending tool"—a large, sturdy steel frame capable of handling 440-tonne vacuum vessel sectors and 360-tonne toroidal field coils with utmost precision.

The upending tool (right) was delivered to the Assembly Hall on 6 November and is now being assembled and precisely positioned on a set of base plates embedded in the floor in the far right corner. (Click to view larger version...)
The upending tool (right) was delivered to the Assembly Hall on 6 November and is now being assembled and precisely positioned on a set of base plates embedded in the floor in the far right corner.
Procured by Korea, the upending tool was delivered to ITER on 6 November. The 18-metre long, 14-metre wide frame came in two halves that are presently being assembled and positioned on dedicated base plates embedded into the building's floor.

Contrary to the twin pre-assembly tools (SSAT), the upending tool does not feature any mechanical, electrical or hydraulic machinery. It is basically a steel frame, but a highly sophisticated one. "The tool is huge," says Assembly Support Section Leader Hyung Yeol Yang. "Controlling the overall dimensions within tolerances of less than 2 millimetres was very challenging for ILJIN, the Korean manufacturer."

The tool is designed to handle two types of components that have nothing in common except their exceptional size and weight: 440 tonnes for a vacuum vessel sector, 360 tonnes for a toroidal field coil. Switching from one to the other will require a complete reconfiguration of the component's supports inside the frame.

The tilt operations, with the upending tool and its load suspended to the hooks of the overhead crane, will need to be repeated 27 times in order to deliver vacuum vessel sectors and toroidal field coils to the pre-assembly tools. The process will be a slow one: up to three weeks to finalize each operation.



return to the latest published articles