Subscribe options

Select your newsletters:

Please enter your email address:

@

News & Media

Latest ITER Newsline

  • FEC2020 | Seeking sponsors for 28th IAEA Fusion Energy Conference

    For only the third time since 1961, the International Atomic Energy Agency's Fusion Energy Conference will be taking place in France—hosted jointly by the Frenc [...]

    Read more

  • Nuclear safety | Under constant scrutiny

    Because one of the elements involved in the fusion reaction is the radioactive isotope tritium, and because the hydrogen fusion reaction itself generates a high [...]

    Read more

  • Power conversion | Alien structures and strange contraptions

    There are places in ITER that seem to belong to another world, places full of alien structures and strange contraptions. The feeling—a mixture of awe and puzzle [...]

    Read more

  • Tokamak Complex | A changing landscape

    For the past three years, the view from the top of the highest worksite crane has not changed much. Inside of the Tokamak Complex, 80 metres below, concrete gal [...]

    Read more

  • Ion cyclotron heating | How to pump 20 MW of power into 1 gram of plasma

    To power the ion cyclotron system, the ITER Organization and its partners are designing not only new antennas, which will be housed in the tokamak vessel, but a [...]

    Read more

Of Interest

See archived entries

Sector assembly tools

Commissioning with load completed

The final test operation for the twin sector sub-assembly tools—commissioning with load—was completed in the Assembly Hall on 26 November.

The 360-tonne megalith is lowered to the Assembly Hall floor. After six months hooked up first to one, then the other, of the sector sub-assembly tools (left), the test loads will be stored in laydown areas until called for use to commission the upending tool. (Click to view larger version...)
The 360-tonne megalith is lowered to the Assembly Hall floor. After six months hooked up first to one, then the other, of the sector sub-assembly tools (left), the test loads will be stored in laydown areas until called for use to commission the upending tool.
With the completion of commissioning, these giant tools are now cleared for operation in 2020, when the first 440-tonne vacuum vessel sectors will be delivered to ITER. The tools will suspend the sectors vertically in their centre while they are pre-assembled with toroidal field coils and thermal shield panels prior to transport to the assembly pit.

The final commissioning activity was carried out using test loads of steel and concrete. Not only were these loads representative of the weight of toroidal field coils (360 tonnes), they also reproduced the coils' general shape and centre of gravity. During full load testing—which was carried out between July and November on first one tool then the other—the loads were secured on the tools' lateral wings and rotated inward, demonstrating that they are working according to specified requirements.

Tool commissioning is an important activity, during which the all specified functional requirements are demonstrated. Also, for tools sourced outside of the European Union, it is the occasion to show compliance with EU regulations. (Click to view larger version...)
Tool commissioning is an important activity, during which the all specified functional requirements are demonstrated. Also, for tools sourced outside of the European Union, it is the occasion to show compliance with EU regulations.
With testing completed, the test loads have now been removed from the tools and transferred to a laydown area. They will be used again in the months to come—this time to test the upending tool, which is designed to raise ITER's largest components (vacuum vessel sectors and D-shaped toroidal field coils) to an upright position.



return to the latest published articles