Subscribe options

Select your newsletters:

Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Component delivery| A jewel in a box

    Sailing under the flag of Germany, the Regine is a mighty ship, strengthened for heavy cargo and equipped on its portside with two 750-tonne on-board cranes. Ha [...]

    Read more

  • Education | Make your own tokamak with 3D printing!

    It's not Lego, but it is definitely 'hands-on.' To offer a tangible device to illustrate the workings of magnetic confinement fusion in a tokamak, the ITER Orga [...]

    Read more

  • Worksite | Europe's Fusion for Energy is building the ITER installation

    Anyone driving to ITER can take full measure of the enormity of the project a few kilometers before reaching the destination. Gigantic cranes can be seen from a [...]

    Read more

  • Disruption mitigation | Experts in plasma disruptions gather online

    On 20-23 July, 120 international experts participated in the 1st IAEA Technical Meeting on Plasma Disruptions and their Mitigation, jointly organized by the Int [...]

    Read more

  • Start of assembly | World dignitaries celebrate a collaborative achievement

    Due to the constraints imposed by the COVID-19 pandemic, the crowd in the ITER Assembly Hall was small. But thanks to live broadcasting and video feed, the audi [...]

    Read more

Of Interest

See archived entries

Sector assembly tools

Commissioning with load completed

The final test operation for the twin sector sub-assembly tools—commissioning with load—was completed in the Assembly Hall on 26 November.

The 360-tonne megalith is lowered to the Assembly Hall floor. After six months hooked up first to one, then the other, of the sector sub-assembly tools (left), the test loads will be stored in laydown areas until called for use to commission the upending tool. (Click to view larger version...)
The 360-tonne megalith is lowered to the Assembly Hall floor. After six months hooked up first to one, then the other, of the sector sub-assembly tools (left), the test loads will be stored in laydown areas until called for use to commission the upending tool.
With the completion of commissioning, these giant tools are now cleared for operation in 2020, when the first 440-tonne vacuum vessel sectors will be delivered to ITER. The tools will suspend the sectors vertically in their centre while they are pre-assembled with toroidal field coils and thermal shield panels prior to transport to the assembly pit.

The final commissioning activity was carried out using test loads of steel and concrete. Not only were these loads representative of the weight of toroidal field coils (360 tonnes), they also reproduced the coils' general shape and centre of gravity. During full load testing—which was carried out between July and November on first one tool then the other—the loads were secured on the tools' lateral wings and rotated inward, demonstrating that they are working according to specified requirements.

Tool commissioning is an important activity, during which the all specified functional requirements are demonstrated. Also, for tools sourced outside of the European Union, it is the occasion to show compliance with EU regulations. (Click to view larger version...)
Tool commissioning is an important activity, during which the all specified functional requirements are demonstrated. Also, for tools sourced outside of the European Union, it is the occasion to show compliance with EU regulations.
With testing completed, the test loads have now been removed from the tools and transferred to a laydown area. They will be used again in the months to come—this time to test the upending tool, which is designed to raise ITER's largest components (vacuum vessel sectors and D-shaped toroidal field coils) to an upright position.



return to the latest published articles