Image of the week | Crane gallery framed out

Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Augmented reality | Assessing the future work environment

    As part of their collaboration within the Site Support Agreement*, ITER and its neighbour CEA are developing a novel approach to explore, analyze and assess the [...]

    Read more

  • Diagnostics and instrumentation | First welding on the vacuum vessel

    Beginning in 2035, ITER will open a window into "burning plasmas"—a state of matter that exists in the core of stars only. Observing, assessing and mo [...]

    Read more

  • Assembly | Machining workshop opens on site

    Construction of an on-site machining workshop began in December 2019 and was completed on schedule in September 2020.The new workshop will be operated by the D [...]

    Read more

  • Neutral Beam Test Facility | Power is ready for the prototype injector

    The European Domestic Agency has carried out successful site acceptance tests at the ITER Neutral Beam Test Facility on power supply equipment installed ov [...]

    Read more

  • In-vessel coils | First components arrive on site

    ITER has received the first shipments of mineral-insulated conductor for ITER's in-vessel coils. The first lengths are destined for winding and bending trials a [...]

    Read more

Of Interest

See archived entries

Image of the week

Crane gallery framed out

It took only nine days to install the structural modules that top the frame of the crane gallery. As one year ends and another begins, the construction teams will turn to cladding.

 (Click to view larger version...)
In planning the five consecutive lift operations, the European contractors* in charge of the operation had to work around wind and rain, as well as other construction activities in the immediate vicinity. Two massive crawler cranes were required, with booms extending over 100 metres and lift capacities of 600 and 650 tonnes respectively.

The complete roof structure—20 tall pillars and roof modules included—weighs approximately 2,000 tonnes. Once covered over with steel and metal cladding, the crane hall will look exactly like the Assembly Hall. Once the temporary wall between the two buildings is removed, the overhead cranes will travel back and forth through undivided space, as they deliver machine components to the Tokamak pit. Activity is underway now to create the necessary connections between the different segments of rail.

*The lifting and berthing operation was performed under the responsibility of the European Domestic Agency Fusion for Energy. It was coordinated by architect-engineer Engage and implemented by contractors VFR (overall responsibility and coordination), Martifer (manufacturing and installation of the steel structure) and Vernazza (lifting operations).


return to the latest published articles