Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Fusion world | A helium campaign kicks off at JET

    After achieving record-breaking results on the Joint European Torus during 2021 experiments with the high-performance fuel mix of deuterium and tritium, EUROfus [...]

    Read more

  • Coil winding table | Seven years of faithful service

    In November 2015, workers from the European contractor Sea Alp Engineering, an Italian company based in Turin, began installing a large circular structure at th [...]

    Read more

  • Image of the week | Down under

    It has been close to five months since the first vacuum vessel module was installed in the Tokamak pit. The view from above is by now familiar: a huge D-sha [...]

    Read more

  • On site | An annual reminder about safety

    ITER's Safety and Quality Department knows: you can never repeat an important message often enough. The second annual ITER Safety Day took place on 15 Septe [...]

    Read more

  • Top management | ITER Council appoints new Director-General

    Convening in an extraordinary session in Paris, the ITER Council has appointed Pietro Barabaschi as the next Director-General of the ITER Organization. Mr Barab [...]

    Read more

Of Interest

See archived entries

Configuration control

Masters of change hold 500th meeting

The ITER Configuration Control Board held its 500th meeting earlier this month. "CCB," as it is known at ITER, is at the centre of managing any changes to the technical configuration of the structures, systems and components of the ITER machine and plant.

With millions of components and an international governance structure based on in-kind contributions, ITER is one of the most complex projects in the world. Without the structured and highly controlled configuration of the tokamak machine and plant, it would be impossible to manage the project's complexity. (Click to view larger version...)
With millions of components and an international governance structure based on in-kind contributions, ITER is one of the most complex projects in the world. Without the structured and highly controlled configuration of the tokamak machine and plant, it would be impossible to manage the project's complexity.
Configuration management describes the processes, activities, tools and methods that are used to manage the full lifecycle of a project. Through systems engineering processes all functional characteristics are documented, consistency is maintained, and the project's deliverables are protected from unauthorized change.

With robust configuration management, project decisions related to design, development, operation and maintenance can be made on the basis of technical data that is not only consistent, but also controlled and validated.

Exactly 14 years ago, in January 2008, the ITER Configuration Control Board gathered for the first time under the leadership of Eisuke Tada, current Deputy of the Director-General who was at that time Head of Project Office.

Before that date, all design changes were brought before a Technical Management Board. The creation of a new board for configuration control was a sign of the importance top management placed on creating an integrated approach to handling project change requests and the recognition that, as the project moved forward, proper configuration management was integral to controlling cost, schedule and procurement. The idea was launched by Stefano Chiocchio, Design Integration & Configuration Control Section Leader at that time, who clearly saw the need for it. Every partner had proposals for detailed design changes to simplify, improve, or reduce costs, but very seldom were such proposals "stand-alone," with no implications for other equipment.

Today the CCB is celebrating its 500th meeting. It has been a long journey marked by many challenges and one overriding preoccupation—the constant search for the most efficient methodology.

"Since we introduced a Product Lifecycle Management (PLM) tool to manage ITER configuration in 2015, the system is more challenging for users, who have had to upload all engineering data and rigorously determine their applicability and level of technical control. But it gives us the guarantee that all project change requests are properly implemented throughout the project," says Benoit Salamon, Configuration Management Division Head since December 2021. "There is no space for omission: if a document is listed as 'impacted' by a certain approved change request, the request is blocked for closure until the new revision appears. These highly interlinked and automatized checks ensure high-quality engineering processes."

The effort to populate the PLM tool with data is still a work in progress. More than 100,000 documents have been uploaded (beginning with those relating to First Plasma components and systems) and another few hundreds of thousands are expected by the deuterium-tritium phase. We still need to interlink the configuration management tool with other ITER databases or improve these connections. But we can already see the fruit of the enormous effort of the past years.

"The work accomplished so far is incredibly valuable and now we are taking it one step further, examining all missing items in the technical baseline and preparing a list of 'known unknowns,'" says Alain Becoulet, Head of the Engineering Domain and CCB Chair since 2020. "We are finalizing a Project Change Request Forecast Roadmap—a list of changes that we know we still have to introduce for the proper operation of the machine."

The Configuration Control Board today is not only about project change requests; it has expanded to have oversight over other baseline-related issues, risks, and the resolution of some delivered-component non-conformities involving Domestic Agencies. We now have CCB meetings at three levels, from systems-level discussions right up to the level of the Director-General.

What remains unchanged is the participation in discussions. The CCB remains a forum that involves the ITER Organization and the Domestic Agencies. Each person who has a direct interest in the system or component under discussion can connect and participate remotely in the deliberations (since COVID-19, there have been no in-person gatherings).

Harry Bailey, configuration manager from the United States ITER Domestic Agency, speaks for all Domestic Agencies when he says, "We are all strongly involved in the discussions at CCB, and also keep a vigilant eye on what we are doing and how. If we believe we can help, we initiate discussion on possible improvements. As ITER evolves as a project, critical issues and concerns evolve as well. Our mission is to ensure that CCB fulfils its role as 'configuration guardian.'"