  • Making remote handling less remote

    Over a wet and windy three-day period on the ITER site in November, around 90 representatives of the ITER Organization, the Domestic Agencies of Europe and Japa [...]

    Read more

  • The framework for sharing ITER intellectual property

    In signing the ITER Agreement in 2006, the seven ITER Members were agreeing not only to share in the costs of constructing and operating the ITER facility, but [...]

    Read more

  • Wendelstein achieves ultra-precise magnetic topology

    A recent article in the online journal Nature Communications confirms that the complex topology of the magnetic field of Wendelstein 7-X—the world's largest ste [...]

    Read more

  • The Matrix, rigid and fluid

    A fast-growing array of structures and buildings has been emerging across the ITER worksite platform under the control and supervision of the European Domestic [...]

    Read more

  • By road, river and sea

    They travelled by road from the Air Liquide factory near Grenoble, sailed down the Rhône River from Lyon and entered the Mediterranean to the east of Fos-sur-Me [...]

    Read more

Of Interest

See archived articles

First concrete poured

-Taiger Murphy, Civil Engineering Technician

The columns for the Poloidal Field Coil Fabrication Building are rising out the ground in the foreground, while the Tokamak pit is taking shape in the background. (Click to view larger version...)
The columns for the Poloidal Field Coil Fabrication Building are rising out the ground in the foreground, while the Tokamak pit is taking shape in the background.
Work on the future Headquarters building is also progressing. (Click to view larger version...)
Work on the future Headquarters building is also progressing.
This week, construction activities on the ITER site included work in five major areas:
  • Tokamak Complex Excavation and Support Structure:
    There is ongoing rock blasting and excavation is continuing in the area of the future Tokamak Complex.
  • Poloidal Field Coil Fabrication Building:
    The first major concrete slab pour has taken place at the east end of the building. In tandem, continuing activities are progressing westwards along the building, including work on the column footing installation, concrete column reinforcement and cast-in-place concrete placement is continuing for the above-ground structure of the PF Coil Fabrication Building.
  • Permanent Iter Headquarters ('Annex Buildings'):
    Preparations for the beginning of foundation work are continuing for the future permanent ITER Headquarters Buildings. Ground preparation concrete is being poured.
  • Site Infrastructure:
    Permanent buried cable for communications installation continues between the Technical Building B07 and the Contractor's Area No. 1.