  • ITER DNA | A "case" study...

    In December last year, and again this year in early May, pre-welding fitting tests demonstrated that steel components as tall as a four-storey building (and wei [...]

    Read more

  • First plasma| Temporary in-vessel protection

    The vacuum vessel, the operating theatre of the ITER machine, needs to be protected against possible damage from the hot plasma at any given time during its ope [...]

    Read more

  • Divertor cassettes | Successful prototypes open way to series

    Before embarking on the fabrication of the 54 complex steel structures that will form a ring at the bottom of the ITER machine—the divertor cassettes—the Europe [...]

    Read more

  • Images of the week | Titan tool 90 percent complete

    Towering 22 metres above ground and weighing approximately 800 tonnes, the twin sector sub-assembly tools (SSAT) are formidable handling machines that will be u [...]

    Read more

  • Video | How does the ITER cryoplant work?

    Cold is essential to ITER—10,000 tonnes of superconducting magnets, the thermal shield that surrounds the machine, the cryopumps that achieve the high vacuum in [...]

    Read more

Of Interest

See archived articles

First concrete poured

Taiger Murphy, Civil Engineering Technician

The columns for the Poloidal Field Coil Winding Facility are rising out the ground in the foreground, while the Tokamak Pit is taking shape in the background. (Click to view larger version...)
The columns for the Poloidal Field Coil Winding Facility are rising out the ground in the foreground, while the Tokamak Pit is taking shape in the background.
Work on the future Headquarters building is also progressing. (Click to view larger version...)
Work on the future Headquarters building is also progressing.
This week, construction activities on the ITER site included work in five major areas:
  • Tokamak Complex excavation and support structure:
    There is ongoing rock blasting and excavation is continuing in the area of the future Tokamak Complex.
  • Poloidal field coil fabrication building:
    The first major concrete slab pour has taken place at the east end of the building. In tandem, continuing activities are progressing westwards along the building, including work on the column footing installation, concrete column reinforcement and cast-in-place concrete placement is continuing for the above-ground structure of the Poloidal Field Coils Winding Facility
  • Permanent ITER Headquarters ('Annex Buildings'):
    Preparations for the beginning of foundation work are continuing for the future permanent ITER Headquarters. Ground preparation concrete is being poured.
  • Site infrastructure:
    Permanent buried cable for communications installation continues between the Technical Building B07 and the Contractors Area No. 1.