Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Cryoplant | Filled from floor to ceiling

    The ITER cryoplant used to be a vast echoey chamber with 5,400 m² of interior space divided into two areas; now, it is filled from floor to ceiling with industr [...]

    Read more

  • Cryostat | Adjusting, welding, testing ...

    The assembly of the ITER cryostat—the stainless steel "thermos" that insulates the ultra-cold superconducting magnets from the environment—is progress [...]

    Read more

  • Tokamak Building | Full steam ahead

    In this central arena of the construction site, construction teams are active three shifts a day—two full work shifts and a third, at night, dedicated to moving [...]

    Read more

  • Poloidal field coils | Turning tables and hot resin

    One of only two manufacturing facilities located on the ITER site, the Poloidal Field Coils Winding Facility was constructed by Europe to house the winding, imp [...]

    Read more

  • Assembly Hall | One giant standing

    Two identical handling tools in the Assembly Hall will play a critical role in preparing ITER's nine vacuum vessel sectors for their final journey: transport by [...]

    Read more

Of Interest

See archived entries

MAC develops guidelines for additional direct investment

Sabina Griffith

Additional direct investments were the focus of the 10th meeting of the ITER Management Advisory Committee (MAC). (Click to view larger version...)
Additional direct investments were the focus of the 10th meeting of the ITER Management Advisory Committee (MAC).
At its 10th meeting held on 26-27 January 2011, the ITER Management Advisory Committee (MAC) looked at a detailed analysis of additional direct investments that had been performed by the ITER Organization and the seven Domestic Agencies in response to the request from the ITER Council at its seventh meeting in November (IC-7).
 
These additional investments are the items deemed essential for the operation of the ITER machine, but that are not presently part of the ITER Baseline.

The Baseline that describes the scope, schedule and cost for the construction phase of the ITER Project was approved by the extraordinary ITER Council in July last year.

The total value of the project's construction costs was capped at 4,700 kIUA*, including a contingency of 115.3 kIUA. It was agreed that any additional necessary resources were to be made available within this capped value.
 
Take a break, have a chat: ITER Director-General Osamu Motojima and members of the MAC taking the discussion off-line. (Click to view larger version...)
Take a break, have a chat: ITER Director-General Osamu Motojima and members of the MAC taking the discussion off-line.
During its meeting, the MAC developed guidelines that will be used to evaluate the allocation of responsibilities and credit values associated with additional direct investment based on the capped ceiling. Following these guidelines, future risks will now be accounted for.

MAC encouraged the ITER Organization to continue pursuing reduction in the overall cost of the ITER Project and efforts to accelerate its schedule.

* ITER Units of Account (IUAs) are the ITER "currency," a very unique feature of the ITER Project based on the principle of procurement sharing. Instead of contributing cash to the project, the Members will provide "in-kind" contributions; all of the components of the ITER facility will be built by the seven ITER Members and delivered to the ITER site in France. The IUA was devised in order to measure the value of in-kind contributions consistently over time, and neutralize market fluctuations.


return to the latest published articles