Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Worksite postcards | Under fog and autumn light

    Due to its proximity to the Durance River and to the narrow gully spanned by the Bridge of Mirabeau, the area around ITER often experiences a peculiar meteorolo [...]

    Read more

  • Assembly Hall | Another massive paint job

    By the end of December, the massive painting job in the Assembly Hall will be complete and the building's floor will be as white and pristine as the landscape i [...]

    Read more

  • ITER India | Testing a neutral beam for diagnostics

    Every 23 seconds during fusion operation, a probe beam will penetrate deep into the core of the ITER plasma to aid in the detection of helium ash—one of fusion' [...]

    Read more

  • Welded attachments | Follow the laser projections

    How do you position 150,000 welded attachments on to a vacuum vessel the size of a house, each one needing to be accurately placed to less than a 4 mm target? [...]

    Read more

  • Visit | Our neighbour the Nobel

    In 2018, the Nobel Prize in Physics was awarded to Gérard Mourou for his work on ultra-short, extremely high-intensity laser pulses—the so-called 'chirped pulse [...]

    Read more

Of Interest

See archived entries

MAC develops guidelines for additional direct investment

Sabina Griffith

Additional direct investments were the focus of the 10th meeting of the ITER Management Advisory Committee (MAC). (Click to view larger version...)
Additional direct investments were the focus of the 10th meeting of the ITER Management Advisory Committee (MAC).
At its 10th meeting held on 26-27 January 2011, the ITER Management Advisory Committee (MAC) looked at a detailed analysis of additional direct investments that had been performed by the ITER Organization and the seven Domestic Agencies in response to the request from the ITER Council at its seventh meeting in November (IC-7).
 
These additional investments are the items deemed essential for the operation of the ITER machine, but that are not presently part of the ITER Baseline.

The Baseline that describes the scope, schedule and cost for the construction phase of the ITER Project was approved by the extraordinary ITER Council in July last year.

The total value of the project's construction costs was capped at 4,700 kIUA*, including a contingency of 115.3 kIUA. It was agreed that any additional necessary resources were to be made available within this capped value.
 
Take a break, have a chat: ITER Director-General Osamu Motojima and members of the MAC taking the discussion off-line. (Click to view larger version...)
Take a break, have a chat: ITER Director-General Osamu Motojima and members of the MAC taking the discussion off-line.
During its meeting, the MAC developed guidelines that will be used to evaluate the allocation of responsibilities and credit values associated with additional direct investment based on the capped ceiling. Following these guidelines, future risks will now be accounted for.

MAC encouraged the ITER Organization to continue pursuing reduction in the overall cost of the ITER Project and efforts to accelerate its schedule.

* ITER Units of Account (IUAs) are the ITER "currency," a very unique feature of the ITER Project based on the principle of procurement sharing. Instead of contributing cash to the project, the Members will provide "in-kind" contributions; all of the components of the ITER facility will be built by the seven ITER Members and delivered to the ITER site in France. The IUA was devised in order to measure the value of in-kind contributions consistently over time, and neutralize market fluctuations.


return to the latest published articles