Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Without minimizing challenges, Council reaffirms commitment

    On 24 October 2007, the ITER Organization was officially established following the ratification by the seven ITER Members of the project's constitutive document [...]

    Read more

  • Heat waves

    Plasma is like a tenuous mist of particles—light atoms that have been dissociated into ions (the atom nucleus) and free-roaming electrons. In order to study pla [...]

    Read more

  • What a difference ten days make

    There was a time when progress in Tokamak Complex construction was easy to follow.Excavation in 2010; the creation of the ground support structure and seismic f [...]

    Read more

  • What's in the box?

    At ITER, even the opening of a box takes on a spectacular dimension. The operation requires a powerful crane, a full team of specialists and, as everything ITER [...]

    Read more

  • EU Commission has "positive appreciation" of ITER progress

    On 14 June, the European Commission issued a Communication presenting the revised schedule and budget estimates for European participation in ITER. Its object? [...]

    Read more

Of Interest

See archived articles

Spring is blooming, construction is booming

-Robert Arnoux

In a scene reminiscent of an Apollo Moon mission, geologists take measurements in the Tokamak excavation pit. (Click to view larger version...)
In a scene reminiscent of an Apollo Moon mission, geologists take measurements in the Tokamak excavation pit.
It is springtime on the ITER site. Green is sprouting along the embankments, and construction, in Tim Watson's own words, "is progressing reasonably well" both on the platform and just below, on the Headquarters Building worksite.

"Everything is going pretty much as planned," says the Head of the Buildings & Site Infrastructure (BSI) Directorate. Concrete structures in the basement level of the future ITER Headquarters are now nearing completion and work on the ground floor, where the social amenities such as a restaurant and bank counter will be located, is now well underway.

A "model office" should be set up in September 2011 to test the layout of furniture and office equipment. The ITER Headquarters will accommodate some 500 ITER staff in a set-up designed as "a good balance between very large open-plan offices and small single occupancy offices." Agence Iter France and the European Domestic Agency F4E are expected to hand the building over to the ITER Organization during the summer of 2012.

A ''fairly conventional construction, but a very big one,'' the Poloidal Field Coil Assembly Building has entered ''roof and cladding'' operations. (Click to view larger version...)
A ''fairly conventional construction, but a very big one,'' the Poloidal Field Coil Assembly Building has entered ''roof and cladding'' operations.
On top of the ITER platform, Tokamak excavation works (literally) reached rock bottom last month. By way of radar mapping and the boring of more than 500 holes, geological surveys provided a detailed map of the substratum. Some voids were detected, the largest being a few cubic meters in volume; these voids will now be filled with concrete.

The Tokamak excavation area is now being readied for the pouring of a thin layer of 'blinding concrete' that will create the clean and flat work surface upon which the 1.5-metre-thick "lower basemat" will be created. Concrete operations should begin a few weeks from now and last until the end of the year. Some 82,000 tonnes of concrete will go into the lower basemat alone.

A "fairly conventional construction, but a very big one," the Poloidal Field Coil Assembly Building has entered "roof and cladding" operations. Five out of the six poloidal field coils of the ITER Tokamak will be assembled here; operations could begin as early as 2012 and last until 2017.

What will happen to this 11,000 square metre building once coil winding operations are complete? "Everybody wants to use it," says Tim. "Nothing has been decided yet, but people always use a space if it's there... There are indeed lots of things you can do in a large open space with two cranes."

An artist's view of the 4,000 square metre ''switchyard'' through which power will be fed to ITER. © AIF (Click to view larger version...)
An artist's view of the 4,000 square metre ''switchyard'' through which power will be fed to ITER. © AIF
A new and quite large element, in the form of a 43-metre-high electricity pylon, will soon be added to the platform scenery. The pylon will be anchored between the "green" and "blue" buildings of the present contractors' area, and will support the last portion of the 400 kV lines destined to supply current to the ITER installation. In June, France's electricity carrier RTE (Réseau de Transport d'Électricité) will commence the construction of the large (40,000 square-metres) "switchyard" through which power will be fed to ITER.

What has been accomplished since last August is impressive. It was only nine months ago, after all, that bulldozers, scrapers and power shovels returned to the ITER platform.


return to the latest published articles