Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Bookmark | "ITER: the Giant Fusion Reactor," second edition

    'Is ITER the 'star of science' whose creation has been made possible by humankind's sophisticated mastery of the laws of nature and the powers of technology? Or [...]

    Read more

  • Fusion world | ITER and ASDEX Upgrade in the monastic quiet

    The ASDEX Upgrade tokamak in Germany has been helping to establish the scientific basis for the optimization of the tokamak approach to fusion energy since 1991 [...]

    Read more

  • On site | There goes the long-standing crane

    In October 2014, close to ten years ago, five giant cranes were installed on and around the Tokamak Complex basemat slab. As work progressed to erect the Comple [...]

    Read more

  • Portfolio | Sector repair has started

    Built up against vacuum vessel sector #7, the scaffolding reaches almost 20 metres in height and masks the massive component. Streaks of blinding light, filtere [...]

    Read more

  • Fusion world | Public/private consortium is building the DTT tokamak

    The Divertor Test Tokamak in Italy is creating a new model for engagement with industry in fusion research. ITER helped to pave the way. The Divertor Test Tokam [...]

    Read more

Of Interest

See archived entries

Revisiting the master plan

Members of the newly established Task Force double-checking the design of the Tokamak Building basement. (Click to view larger version...)
Members of the newly established Task Force double-checking the design of the Tokamak Building basement.
When building a house, you will, at one stage, have to decide where to place the kitchen and the bathroom in order to allow the architect to make provision for the required installations such as pipes and electrical cables.

The same holds for an installation like ITER. The only difference between your house and the largest fusion research facility ever built is the fact that if you change your plans, this might have a more or less severe impact on your construction budget—and on the formerly good relationship you had with your architect—but change will be possible. In ITER it will not!

Leads the Building Integration Task Force: Ken Blacker (Click to view larger version...)
Leads the Building Integration Task Force: Ken Blacker
"We have made provision for about 1,600 penetrations in the walls of the Tokamak Building," explains Ken Blackler, Head of the Assembly and Operations Division. "And that is it. Drilling additional holes through two-metre-thick reinforced concrete walls at a later stage will not be an option." A Building Integration Task Force was created in April this year in order to make sure that all the systems to be installed in the Tokamak Building, and in the adjacent Diagnostic and Tritium buildings, are correctly defined in the overall master plan. This includes all the necessary pipes, ducts, structures, cable trays, penetrations and embedded plates.

Thirty-five people have been diverted from their usual jobs to form this Task Force, which demonstrates the seriousness of the exercise. "We have to freeze the design now in order to proceed with the construction with confidence,"explains Ken. "But before we do so, we are going through the buildings one final time, floor by floor, to see if everything has been included ... if nothing has been left out."

On Monday this week, the Task Force passed its first Design Integration Review for the lowest basement level of the buildings. At this meeting Responsible Officers presented the design status of each system in order to allow the review panel to assess the level of design and its integration into the building. All outstanding actions will now be completed before the data is transferred to the Architect Engineer at the end of this month in order to begin construction design in June.

This Design Integration Review process will now be repeated, one floor each month, and hopefully by December we will have reached the top floor.


return to the latest published articles