  • Cryoplant | Filled from floor to ceiling

    The ITER cryoplant used to be a vast echoey chamber with 5,400 m² of interior space divided into two areas; now, it is filled from floor to ceiling with industr [...]

    Read more

  • Cryostat | Adjusting, welding, testing ...

    The assembly of the ITER cryostat—the stainless steel "thermos" that insulates the ultra-cold superconducting magnets from the environment—is progress [...]

    Read more

  • Tokamak Building | Full steam ahead

    In this central arena of the construction site, construction teams are active three shifts a day—two full work shifts and a third, at night, dedicated to moving [...]

    Read more

  • Poloidal field coils | Turning tables and hot resin

    One of only two manufacturing facilities located on the ITER site, the Poloidal Field Coils Winding Facility was constructed by Europe to house the winding, imp [...]

    Read more

  • Assembly Hall | One giant standing

    Two identical handling tools in the Assembly Hall will play a critical role in preparing ITER's nine vacuum vessel sectors for their final journey: transport by [...]

    Read more

Of Interest

See archived entries

Handing over to industry

Jeremy Goff, Coil Power Supply Section

The participants to the meeting with the CEO of Dawonsys, Sun-Soon Park, Jong-Seok Oh from the Korean Domestic Agency, DDG Yong-Hwan Kim and Ivone Benfatto, head of the Electrical Engineering Division, together with the team from ITER, and industry. (Click to view larger version...)
The participants to the meeting with the CEO of Dawonsys, Sun-Soon Park, Jong-Seok Oh from the Korean Domestic Agency, DDG Yong-Hwan Kim and Ivone Benfatto, head of the Electrical Engineering Division, together with the team from ITER, and industry.
This week saw a great step forward in the evolution of the ITER coil power supplies and pulsed power distribution systems. The Procurement Arrangement with the Korean Domestic Agency for the AC/DC converters (signed in March this year) had led to the selection and award of a contract in August to a consortium led by Dawonsys Co. Ltd. who will design and build the converters, and Hyosung Co. Ltd. who will design and build the converter transformers.

Since the contract kick-off meeting in September, the consortium has performed an enormous amount of preliminary design work, fault analysis, simulations, and configuration checks; the full status report was made during a three-day meeting at Cadarache this week with the Coil Power Supply Section (Electrical Engineering Division, EED). They presented a 3D model showing the latest configuration based on the R&D result of a prototype converter unit.

The objectives of the face-to-face meeting were to ensure an efficient start of contract activities and follow up work to be performed by the ITER Organization, to identify any issues to be resolved and, of course, to begin the best working relationship between ITER and the Domestic Agency's industrial partners.