SPIDER's power supply and calorimeter signed off
17 Dec 2010
This week, the Procurement Arrangement for the 100 kV power supply of the SPIDER test facility and calorimeter was signed by Shishir Deshpande, the Head of the Indian Domestic Agency. ITER Director-General Osamu Motojima signed the contract on 10 December.
SPIDER is the source for Production of Ion of Deuterium Extracted Radio Frequency plasma. SPIDER—together with MITICA (Megavolt ITER injector & Concept Advance)—comprise the PRIMA facility that is also known as the neutral beam test facility. PRIMA will be located in Padua, Italy.
On the full size neutral beam test facility, components and subsystems for ITER's powerful neutral beams will be tested and developed. For example, it will test the ITER injector at full power and pulse length, thus establishing all the methods and procedures needed to fully commission the injectors on ITER, independently of ITER, using the built-in calorimeter.
The main objective of the SPIDER test bed is to optimize, as far as possible, the performance of the full ITER size ion source at full extracted current, at full pulse length with a source uniformity within ±10 percent and in hydrogen and deuterium operation.
The SPIDER power supply system shall provide the electric power to the SPIDER accelerator grids and shall supply the SPIDER ion source and the auxiliary components. A section of the SPIDER power supply system, called the -100 kV power supply, shall be capable of voltage regulation and of switch off in case of grid breakdown.