Lettres d'information

Choisissez ce que vous souhaitez recevoir :

Merci de renseigner votre adresse de messagerie électronique :

@

Votre adresse email ne sera utilisée que dans le cadre de campagnes d'information ITER Organization auxquelles vous êtes abonné. ITER Organization ne communiquera jamais votre adresse email et autres informations personnelles à quiconque ou dans le cadre d'informations commerciales.

Si vous changez d'avis, il vous est possible de vous désinscrire en cliquant sur le lien 'unsubscribe' visible dans vos emails provenant d'ITER Organization.

Pour plus d'information, veuillez consulter notre Politique de confidentialité.

Actu & Médias


Pour les actualités en français, voir la page Actus & Médias.

Divertor target qualification phase begins in Europe

Examples of how the small-scale mockups of the inner vertical target could look when completed. (Click to view larger version...)
Examples of how the small-scale mockups of the inner vertical target could look when completed.
The plasma-facing components of the ITER divertor will be exposed to a heat load that is ten times higher than that of a spacecraft re-entering Earth's atmosphere (10-20 MW per square metre). To ensure the performance and manufacturability of these critical components, qualification activities on the ITER divertor targets (inner vertical target, outer vertical target, and dome) have been underway for years.

The European Domestic Agency, responsible for procuring the divertor inner vertical target, has concluded multiple framework contracts for the fabrication of qualification prototypes. Work will be conducted in two phases: the pre-qualification phase, during which small-scale prototypes will be manufactured and tested in order to validate manufacturing technologies, and a second qualification phase (for those companies whose mockups pass the first phase) for the fabrication of full-scale inner vertical target prototypes.

Two French consortiums (ALCEN-ATMOSTAT and CNIM-TPI) and the German firm Research Instruments have joined the already approved contractor Ansaldo Nucleare (Italy) in a bid to pre-qualify as European Domestic Agency suppliers.

For the European Domestic Agency, contracting with different suppliers not only ensures competition, but also contributes toward mitigating technical risks through the development of different technologies. "We are working to find the right compromise," says Patrick Lorenzetto, project manager for Europe's in-vessel team. "We need enough companies for the pre-qualification stage in order to have enough competition when we then get to the qualification stage."

With the framework contract signatures now in place, the companies will have approximately 18 months for the manufacturing of the small-scale inner vertical target mockups.

Read the full story on the European Domestic Agency website.