Lettres d'information

Choisissez ce que vous souhaitez recevoir :

Merci de renseigner votre adresse de messagerie électronique :

@

Votre adresse email ne sera utilisée que dans le cadre de campagnes d'information ITER Organization auxquelles vous êtes abonné. ITER Organization ne communiquera jamais votre adresse email et autres informations personnelles à quiconque ou dans le cadre d'informations commerciales.

Si vous changez d'avis, il vous est possible de vous désinscrire en cliquant sur le lien 'unsubscribe' visible dans vos emails provenant d'ITER Organization.

Pour plus d'information, veuillez consulter notre Politique de confidentialité.

Actu & Médias


Pour les actualités en français, voir la page Actus & Médias.
Cryostat

Next phase for lower cylinder

At approximately 250 tonnes, the second tier of the ITER cryostat's lower cylinder represents only 15 percent of the cryostat's total weight. Still, in order to weld together its many segments, no less than 1.3 tonnes of filling metal will be required—another amazing figure that opens a window into the unique world of the super-massive ITER components ...

Working in pairs, one man on either side of the massive steel plates, welders will use approximately 1.3 tonnes of filling metal to finalize the welding of the second tier of the cryostat's lower cylinder. (Click to view larger version...)
Working in pairs, one man on either side of the massive steel plates, welders will use approximately 1.3 tonnes of filling metal to finalize the welding of the second tier of the cryostat's lower cylinder.
Following a traditional coconut ceremony, welding operations began on 21 February in the onsite Cryostat Workshop for the second level (tier two) of the lower cylinder.

Operating in tandem, one on either side of the cylinder's steel plates, welders will progressively fill the 5.2-metre-high, 50-millimetre-wide, trough-shaped seams between the segments using a technique called "butt welding." The total length of the welds for this part of the lower cylinder will add up to 160 metres.

Controlling distortions is always an issue when welding large high-tech components. "In the ITER cryostat, because of the number of openings, ports and penetrations and also because of the sheer mass of welds involved, welding is a considerable challenge", explains Vikas Dube, the responsible officer for manufacturing activities in the workshop.

Welding operations on the second tier of the lower cylinder should be complete by late March and the whole assembly (tiers one and two) is expected to be ready for factory acceptance testing in June.

 