Within the vast, 2,300 square-metre facility, the equipment was assembled on time, including the winding line—one of the most important parts of the manufacturing process. The equipment for vacuum pressure impregnation (VPI) had undergone commissioning tests in the presence of ITER Organization representatives that showed that all parameters can meet technical requirements. A laser welding process for correction coil case closure was also selected.
The completion of all commissioning tests will ensure the start of Phase III in the correction coil production task: manufacturing process qualification.
Luo Delong congratulated all those responsible for the completion of the correction coil production line. Wang Min, vice director of the Project & Engineering Department at CN-DA; Li Hongwei, correction coil Technical Responsible Officer; and Li Jiangang, ASIPP director, also took part in the ceremony.