At the far end of the workshop, work has begun on the assembly of the fabrication and transport frame for the lower cylinder. Once this is finalized, the first lower cylinder segments will be positioned on the frame and welded; a "second storey" will be added once the tier-two segments are delivered in September.
Both the base section and the lower cylinder should be finalized by the second quarter of 2018.
While the base section will remain inside the Cryostat Workshop, the lower cylinder will be stored in a dedicated area adjacent to the building. The 490-tonne component will be encased in an airtight cocoon with a regulated atmosphere.
The space freed in the Cryostat Workshop will then be devoted to the assembly and welding of the upper cylinder.
The elements of ITER's giant "thermos" will be installed according to the assembly sequences planned for the machine. The cryostat base section—at 1,250 tonnes—will be the single largest lift of the machine assembly phase.