Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Neighbours | In goes the antenna

    Just a short distance from the ITER site, the Institute for Magnetic Fusion Research (IRFM) is modifying the Tore Supra plasma facility which, once transformed, [...]

    Read more

  • Remote handling | Off-site test facility for design evaluation

    Through a technical collaboration established between the ITER Organization and the UK Atomic Energy Authority (UKAEA) in 2017, the UKAEA's centre for Remote Ap [...]

    Read more

  • Poloidal field coils | A tailor-made ring

    They work like tailors, carefully taking measurements and cutting immaculate fabric with large pairs of scissors. But they're not making a white three-piece sui [...]

    Read more

  • Fusion world | Record results at KSTAR

    Experiments in the Korean tokamakKSTAR in 2017 achieved record-length periods of ELM suppression by the application of three-dimensional magnetic fields with in [...]

    Read more

  • JT-60 SA| Cryostat ready for Europe-Japan tokamak

    The cryostat vessel body of the JT-60SA tokamakhas been successfully manufactured and pre-assembled at a factory in Spain, and will soon be transferred to the J [...]

    Read more

Of Interest

See archived articles

The Seismic Pit basemat is now complete

An important milestone in the project's schedule: the pouring, on 22 December, of the twenty-first and last concrete slab of the Seismic Pit Basemat. (Click to view larger version...)
An important milestone in the project's schedule: the pouring, on 22 December, of the twenty-first and last concrete slab of the Seismic Pit Basemat.
There is no traditional ceremony attached to the completion of the foundations for a future home as there is one, called a Topping Out, to celebrate the laying of a roof.

Had there been one, ITER, F4E and their contractor GTM could have raised a glass to an important milestone in the project's schedule: the pouring, on 22 December, of the twenty-first and last concrete slab of the Seismic Pit basemat.

Work on this 1.5-metre-thick structure began before dawn on a warm August day six months ago. Since then, some 18,000 m³ of concrete have been poured over a dense array of steel rebar and stirrups—some 3,400 tonnes of metal in all.

In order to insure close-to-perfect homogeneity of the basemat, each slab had to be poured in one continuous operation lasting no more than an extended workday. Considering that the pumps could deliver an average of 100 m³ of concrete per hour, the 11,500 m² surface of basemat was broken down into 21 sections, each to be filled successively with 800 m³ of concrete.

In order to ensure ''close to perfect'' homogeneity, each slab had to be poured in one continuous operation lasting no more than an extended workday. (Click to view larger version...)
In order to ensure ''close to perfect'' homogeneity, each slab had to be poured in one continuous operation lasting no more than an extended workday.
This slab-by-slab technique also reduced the forces exerted by concrete "shrinkage" on the steel rebar.

The Seismic Pit basemat was designed to be extremely strong. It supports the anti-seismic pillars and bearings upon which the Tokamak Complex basemat will rest, and will ultimately bear the 360,000 tonnes of the Tokamak Complex.

A central area of the basemat—approximately 80 m²—was reinforced to bear the weight of the mammoth central column assembly tool that will operate during the machine assembly phase on the Tokamak Complex basemat. This extra strength was achieved through an increased density of stirrups.

Upon the now-finalized basemat, 159 seismic bearings (out of a total of 493) remain to be installed over the next two months. Twenty percent of the retaining walls have been completed and two parallel operations will commence this spring: a much smaller (5,500 m²) and relatively shallow excavation for the Assembly Building basemat and, prior to rebar reinforcement, horizontal wooden formwork and scaffolding for the next basemat that will be poured: the Tokamak Complex basemat.


return to the latest published articles