Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Heating | A pinch of moondust in the ITER plasma

    One day in the distant future, fusion plants might be fuelled by helium 3—an isotope that is extremely scarce on Earth but reputed to be abundant on the Moon. B [...]

    Read more

  • Delivery | 2,000 km through canals, locks and tunnels

    When the thruway is closed, one takes the back roads. And when it's low-water season on the Rhine-Rhône canal, a barge leaving Switzerland for the Mediterranean [...]

    Read more

  • Monaco Fellows | A hand in shaping ITER

    For the sixth time, ITER is welcoming a group of five young researchers as part of the Monaco-ITER postdoctoral fellowship scheme. Working alongside experienced [...]

    Read more

  • On site | Drone survey on a perfect day

    There are days in winter when the skies over Provence are perfectly transparent. Snowy peaks 200 kilometres away appear close enough to be touched and farms, co [...]

    Read more

  • AAAS conference | ITER on the world science stage

    With more than 120,000 members globally, the American Association for the Advancement of Science (AAAS) is billed as the world's largest scientific society. The [...]

    Read more

Of Interest

See archived entries

The Seismic Pit basemat is now complete

An important milestone in the project's schedule: the pouring, on 22 December, of the twenty-first and last concrete slab of the Seismic Pit Basemat. (Click to view larger version...)
An important milestone in the project's schedule: the pouring, on 22 December, of the twenty-first and last concrete slab of the Seismic Pit Basemat.
There is no traditional ceremony attached to the completion of the foundations for a future home as there is one, called a Topping Out, to celebrate the laying of a roof.

Had there been one, ITER, F4E and their contractor GTM could have raised a glass to an important milestone in the project's schedule: the pouring, on 22 December, of the twenty-first and last concrete slab of the Seismic Pit basemat.

Work on this 1.5-metre-thick structure began before dawn on a warm August day six months ago. Since then, some 18,000 m³ of concrete have been poured over a dense array of steel rebar and stirrups—some 3,400 tonnes of metal in all.

In order to insure close-to-perfect homogeneity of the basemat, each slab had to be poured in one continuous operation lasting no more than an extended workday. Considering that the pumps could deliver an average of 100 m³ of concrete per hour, the 11,500 m² surface of basemat was broken down into 21 sections, each to be filled successively with 800 m³ of concrete.

In order to ensure ''close to perfect'' homogeneity, each slab had to be poured in one continuous operation lasting no more than an extended workday. (Click to view larger version...)
In order to ensure ''close to perfect'' homogeneity, each slab had to be poured in one continuous operation lasting no more than an extended workday.
This slab-by-slab technique also reduced the forces exerted by concrete "shrinkage" on the steel rebar.

The Seismic Pit basemat was designed to be extremely strong. It supports the anti-seismic pillars and bearings upon which the Tokamak Complex basemat will rest, and will ultimately bear the 360,000 tonnes of the Tokamak Complex.

A central area of the basemat—approximately 80 m²—was reinforced to bear the weight of the mammoth central column assembly tool that will operate during the machine assembly phase on the Tokamak Complex basemat. This extra strength was achieved through an increased density of stirrups.

Upon the now-finalized basemat, 159 seismic bearings (out of a total of 493) remain to be installed over the next two months. Twenty percent of the retaining walls have been completed and two parallel operations will commence this spring: a much smaller (5,500 m²) and relatively shallow excavation for the Assembly Building basemat and, prior to rebar reinforcement, horizontal wooden formwork and scaffolding for the next basemat that will be poured: the Tokamak Complex basemat.


return to the latest published articles