Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Central solenoid assembly | First sequences underway

    What does it take to assemble the magnet at the heart of ITER? Heavy lifting, unerring accuracy, and a human touch. The central solenoid will be assembled from [...]

    Read more

  • Assembly | The eyes of ITER

    Supervisors ensure compliance and completion as machine and plant assembly forges ahead. In Greek mythology, Argus was considered an ideal guardian because his [...]

    Read more

  • Component repairs | Removing, displacing and disassembling

    A good repair job starts with a cleared workbench, the right tools on hand and a strong vise. This axiom, true for odd jobs in a home workshop, is also true for [...]

    Read more

  • Assembly | Set of handling tools for in-vessel installation finalized

    Inside of a test facility that reproduces the volume and geometry of the ITER vacuum vessel environment, a team from CNIM Systèmes Industriels has dem [...]

    Read more

  • 360° image of the week | The assembly theatre

    Ever since it was invented almost two centuries ago, photography has tried to capture what the human eye actually sees. Despite huge progress achieved, it has n [...]

    Read more

Of Interest

See archived entries

The Seismic Pit basemat is now complete

An important milestone in the project's schedule: the pouring, on 22 December, of the twenty-first and last concrete slab of the Seismic Pit Basemat. (Click to view larger version...)
An important milestone in the project's schedule: the pouring, on 22 December, of the twenty-first and last concrete slab of the Seismic Pit Basemat.
There is no traditional ceremony attached to the completion of the foundations for a future home as there is one, called a Topping Out, to celebrate the laying of a roof.

Had there been one, ITER, F4E and their contractor GTM could have raised a glass to an important milestone in the project's schedule: the pouring, on 22 December, of the twenty-first and last concrete slab of the Seismic Pit basemat.

Work on this 1.5-metre-thick structure began before dawn on a warm August day six months ago. Since then, some 18,000 m³ of concrete have been poured over a dense array of steel rebar and stirrups—some 3,400 tonnes of metal in all.

In order to insure close-to-perfect homogeneity of the basemat, each slab had to be poured in one continuous operation lasting no more than an extended workday. Considering that the pumps could deliver an average of 100 m³ of concrete per hour, the 11,500 m² surface of basemat was broken down into 21 sections, each to be filled successively with 800 m³ of concrete.

In order to ensure ''close to perfect'' homogeneity, each slab had to be poured in one continuous operation lasting no more than an extended workday. (Click to view larger version...)
In order to ensure ''close to perfect'' homogeneity, each slab had to be poured in one continuous operation lasting no more than an extended workday.
This slab-by-slab technique also reduced the forces exerted by concrete "shrinkage" on the steel rebar.

The Seismic Pit basemat was designed to be extremely strong. It supports the anti-seismic pillars and bearings upon which the Tokamak Complex basemat will rest, and will ultimately bear the 360,000 tonnes of the Tokamak Complex.

A central area of the basemat—approximately 80 m²—was reinforced to bear the weight of the mammoth central column assembly tool that will operate during the machine assembly phase on the Tokamak Complex basemat. This extra strength was achieved through an increased density of stirrups.

Upon the now-finalized basemat, 159 seismic bearings (out of a total of 493) remain to be installed over the next two months. Twenty percent of the retaining walls have been completed and two parallel operations will commence this spring: a much smaller (5,500 m²) and relatively shallow excavation for the Assembly Building basemat and, prior to rebar reinforcement, horizontal wooden formwork and scaffolding for the next basemat that will be poured: the Tokamak Complex basemat.


return to the latest published articles