Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Technology | The many wonders of ITER diagnostics

    The eyes and ears of virtually all plant functions, ITER diagnostic sensors and accompanying systems will play an essential role at ITER. They will keep the rea [...]

    Read more

  • Outreach | Industry really can be "extraordinaire"

    'Great things are done by a series of small things brought together.' This quote, attributed to the Dutch painter Vincent Van Gogh, could have been the perfect [...]

    Read more

  • Tokamak Building | Civil works completed

    The olive tree that stood for a few days at the top of the Tokamak Building marked the completion of a five-year effort by Europe and its main contractor VFR to [...]

    Read more

  • Assembly Hall | Another massive handling tool

    Inside of the Assembly Hall, some of ITER's heaviest components will have to be raised ever so carefully from their horizontal delivery positions to vertical. T [...]

    Read more

  • Image of the week | Time to celebrate

    It is traditional, in the world of construction, to celebrate the completion of a house or building by placing a leafy branch on its roof or topmost beam. The p [...]

    Read more

Of Interest

See archived entries

Scrutinizing AC/DC converter design

Hao Tan, ITER Power Electronic Engineer

Almost 40 participants from Korea and China, including review panel experts, participated in the Preliminary Engineering Design Review for ITER's AC/DC magnet power converters. (Click to view larger version...)
Almost 40 participants from Korea and China, including review panel experts, participated in the Preliminary Engineering Design Review for ITER's AC/DC magnet power converters.
The Preliminary Engineering Design Review for ITER's AC/DC magnet power converters took place from 7-11 May at ITER Headquarters.
 
The Procurement Arrangement for AC/DC converters was signed by the Korean Domestic Agency on 14 March 2011. It includes the design, fabrication, delivery, assembly, and installation of the convertors; site acceptance testing and integration of the power converter units for the toroidal field coils, the central solenoid, vertical stabilization circuit 1, and correction coils; a master control system; and a dummy load for system testing and maintenance.

Since the signature, the Korean Domestic Agency has appointed its suppliers: an industry consortium comprising Dawonsys and Hyosung.

This prototype converter unit, fabricated by DAWONSYS in June 2011, is ready to undergo testing. (Click to view larger version...)
This prototype converter unit, fabricated by DAWONSYS in June 2011, is ready to undergo testing.
Following 10 months of work headed by Korean Domestic Agency (including prototype R&D) the design review—a key milestone of Procurement Arrangement execution—was concluded on time in accordance with the Strategic Management Plan. Almost 40 participants from Korea and China, including review panel experts, scrutinized and analyzed the preliminary design of the AC/DC power converters and their transformers, together with the instrumentation and control (I&C) and interlock systems.

The review assessed the proposed solution as generally meeting the design input requirements and as meeting the project requirements. It identified some issues requiring further work, but no showstoppers were found.
 
The meeting was a further example of very successful collaboration between the ITER Organization, the Korean Domestic Agency and industry.