Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Without minimizing challenges, Council reaffirms commitment

    On 24 October 2007, the ITER Organization was officially established following the ratification by the seven ITER Members of the project's constitutive document [...]

    Read more

  • Heat waves

    Plasma is like a tenuous mist of particles—light atoms that have been dissociated into ions (the atom nucleus) and free-roaming electrons. In order to study pla [...]

    Read more

  • What a difference ten days make

    There was a time when progress in Tokamak Complex construction was easy to follow.Excavation in 2010; the creation of the ground support structure and seismic f [...]

    Read more

  • What's in the box?

    At ITER, even the opening of a box takes on a spectacular dimension. The operation requires a powerful crane, a full team of specialists and, as everything ITER [...]

    Read more

  • EU Commission has "positive appreciation" of ITER progress

    On 14 June, the European Commission issued a Communication presenting the revised schedule and budget estimates for European participation in ITER. Its object? [...]

    Read more

Of Interest

See archived articles

Bringing ITER components to Cadarache

-Krista Dulon

DAHER's Laurence Prudhomme and Barry Paul are on site to pilot the initial ''fact-finding'' phase. (Click to view larger version...)
DAHER's Laurence Prudhomme and Barry Paul are on site to pilot the initial ''fact-finding'' phase.
Planning has begun for the complex logistics task of bringing ITER components from factories on three continents to the ITER site in Cadarache. Following the selection of the European company DAHER as Logistics Service Provider (LSP) in February, a two-person DAHER team is now on site to pilot the initial planning phase of the LSP contract.

Laurence Prudhomme, operations manager, and Barry Paul, planning manager, are working closely with the ITER Organization and the Domestic Agencies to collect the many thousands of pieces of information that will allow the DAHER "control room" to plan for—and closely follow—the delivery of ITER components according to the ITER Project's overall schedule.

"The first phase of our mission is fact finding," explains Laurence. "We need to gather detailed information on manufacturing schedules and on the specificities of each load to be transported. We need to look into ship availability, pairing the needs of each load (i.e., heavy lift) with the capacity of each vessel."

Working backwards from the dates the components need to be on site, DAHER will plan all the steps in the transport process—from arranging the specific point of contact where it will take over responsibility for each load, to final delivery. As LSP provider, DAHER is in charge of insurance, customs clearance, interim storage before delivery, handling and unloading on site. During the eighteen months of the planning phase, DAHER will be initiating import customs procedures with the French authorities, and—via its agencies and local partners—export procedures at each manufacturing location.

Self-propelled transporters like this one, which can be piloted from cabins at both ends, will be used to transport ITER loads along the Itinerary beginning in 2014. Courtesy DAHER. (Click to view larger version...)
Self-propelled transporters like this one, which can be piloted from cabins at both ends, will be used to transport ITER loads along the Itinerary beginning in 2014. Courtesy DAHER.
DAHER IT engineers are currently adapting the company's logistics and industrial flow management tool, DAgeSCOPETM to fit the specificities of the ITER contract. Progressively "filled in" during the planning phase and the future implementation phase, this centralized database will be a powerful tool for optimizing shipments and for orchestrating deliveries according to the progress of ITER assembly.

"Once we have a more detailed schedule of all loads to transport, we'll focus on consolidating shipments wherever possible," says Laurence. "Imagine that we have two loads ready for shipment in Korea and two others nearly ready in Japan. We'll try to organize the shipment of all four loads in the same vessel by coordinating with the different parties."

As part of the initial fact-finding mission, Planning Manager Barry Paul is making a visit to all ITER Domestic Agencies to initiate discussions and conclude individual agreements within the framework of the LSP contract.

The team has one year to prepare for an important deliverable, according to Laurence: "By mid-2013, we will have all the elements we need to provide a comprehensive Transport and Logistics Global Plan (TLGP) to the ITER Organization, containing all the organizational and scheduling details for bringing each ITER component to Cadarache at the requested date." 