  • Cryoplant | Filled from floor to ceiling

    The ITER cryoplant used to be a vast echoey chamber with 5,400 m² of interior space divided into two areas; now, it is filled from floor to ceiling with industr [...]

    Read more

  • Cryostat | Adjusting, welding, testing ...

    The assembly of the ITER cryostat—the stainless steel "thermos" that insulates the ultra-cold superconducting magnets from the environment—is progress [...]

    Read more

  • Tokamak Building | Full steam ahead

    In this central arena of the construction site, construction teams are active three shifts a day—two full work shifts and a third, at night, dedicated to moving [...]

    Read more

  • Poloidal field coils | Turning tables and hot resin

    One of only two manufacturing facilities located on the ITER site, the Poloidal Field Coils Winding Facility was constructed by Europe to house the winding, imp [...]

    Read more

  • Assembly Hall | One giant standing

    Two identical handling tools in the Assembly Hall will play a critical role in preparing ITER's nine vacuum vessel sectors for their final journey: transport by [...]

    Read more

Of Interest

See archived entries

10th ITER Council held in Washington DC

Michel Claessens, Head of ITER Communication

The participants to the tenth ITER Council stand together in the Ronald Reagan Building in Washington D.C. on Thursday 21 June. (Click to view larger version...)
The participants to the tenth ITER Council stand together in the Ronald Reagan Building in Washington D.C. on Thursday 21 June.
During its tenth meeting held on 20-21 June in Washington DC, the ITER Council acknowledged a number of positive advancements for the project, noting, in particular, the progress of ITER construction and licensing.
 
The Council stressed that respecting the project schedule within cost remains a critical issue and that reported slippages need rapid correction; it also noted that the ITER Organization and the seven Domestic Agencies are working together on these corrections. Relative to schedule issues, decisions were taken regarding the manufacturing of some major ITER Tokamak components.
 
''The US is committed in the project,'' stated Steven Chu, United States Secretary of Energy (right) as the tenth ITER Council began on 20 June in Washington, DC. Next to Chu: Council Chair Hideyuki Takatsu, speaking; ITER Director-General Osamu Motojima; and, right to left, deputies Rem Haange, Rich Hawryluk and Carlos Alejaldre. (Click to view larger version...)
''The US is committed in the project,'' stated Steven Chu, United States Secretary of Energy (right) as the tenth ITER Council began on 20 June in Washington, DC. Next to Chu: Council Chair Hideyuki Takatsu, speaking; ITER Director-General Osamu Motojima; and, right to left, deputies Rem Haange, Rich Hawryluk and Carlos Alejaldre.
This meeting took place in the Ronald Reagan building, which is fitting given the fact that ITER was born out of the shared vision of Secretary General Gorbachev and President Reagan at the Geneva Summit in 1985. This ITER Council was the first chaired by Dr. Hideyuki Takatsu of Japan, who began his term as ITER Council Chair on 1 January 2012.
 
The Director-General Osamu Motojima thanked all ITER Members for their proactive and forward looking contributions and their much appreciated encouragement. The ITER Organization will keep continuing to promote the ITER Project together with its seven Domestic Agencies," Motojima stressed.

Read the ITER Council Press Release in English and in French.