Enable Recite

Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Seismic analysis | Collaboration helps to keep ITER on solid ground

    At ITER, system designers have to ensure that their equipment will withstand earthquakes, large and small. Equipment required for the safety of ITER has to be d [...]

    Read more

  • Assembly preparation | Busy month ahead

    This year at ITER, the month of March will not only mark the coming of spring. It will also set into motion a series of spectacular operations in the assembly t [...]

    Read more

  • Vacuum vessel | Last phase for Europe's sector #5

    The first European vacuum vessel sector is entering an important and critical phase: the assembly and welding of four segments into the D-shaped sector. Und [...]

    Read more

  • Magnet system | Second coil comes out of the cold

    A second ring-shaped poloidal field coil has successfully passed all thermal testing. Following in the footsteps of poloidal field coil #6 (PF6), which complet [...]

    Read more

  • Thermal shield | Practising the embrace

    In the ITER Assembly Hall, fitting tests are underway on two outboard thermal shield panels. Once paired, the 11-metre-tall, silver-plated components will [...]

    Read more

Of Interest

See archived entries

Busy August on platform

As blinding concrete is poured in the background, an excavator is at work on an 8 x 7-metre gallery. (Click to view larger version...)
As blinding concrete is poured in the background, an excavator is at work on an 8 x 7-metre gallery.
Work kept progressing on the ITER platform during the summer recess.

Blinding concrete was poured over the rock surface of the future Assembly Hall adjacent to the Tokamak Seismic Pit. The resulting clean and flat 6,000 m² surface will be used as a working platform to install the reinforcement steel of the building's structural foundation.

In parallel, workers finalized rock excavation for the galleries that will run in the foundations. In the picture, an excavator is at work on an 8 x 7 metre gallery that will serve as an entry point for most of the electrical cables providing energy to the tools and devices to be used for assembly operations.

Work began on the networks of Contractor Area #2 and continued throughout the platform as manholes connecting the large 1.6-kilometre-long concrete piping of the underground drainage network were installed.

Foundation work on the Assembly Hall worksite will extend into March 2013, and drainage network installation should be completed by November of this year.


return to the latest published articles