Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Image of the week | Tokamak-sur-mer

    At the height of the heat wave, in late June, surface temperature on the ITER worksite climbed to the 50 °C range. To continue work—and protect workers—a series [...]

    Read more

  • Space propulsion | Have fusion, will travel

    The idea of propelling rockets and spaceships using the power of the atom is nothing new: the Manhattan Project in the mid-1940s as well as countless endeavours [...]

    Read more

  • Cold fusion | End of story?

    Thirty years ago, two electrochemists at the University of Utah, Martin Fleischmann and Stanley Pons, created a sensation when they claimed they had achieved fu [...]

    Read more

  • Magnet feeders | Wave of deliveries ahead

    Several batches of magnet feeder components will arrive from China in September containing elements that need to be received, inspected and readied for installa [...]

    Read more

  • Tokamak cooling system procurement | Global team for better efficiency

    A unique work-sharing arrangement is expediting the design and fabrication of ITER's tokamak cooling water system and building the knowledge base that will be c [...]

    Read more

Of Interest

See archived entries

Busy August on platform

As blinding concrete is poured in the background, an excavator is at work on an 8 x 7-metre gallery. (Click to view larger version...)
As blinding concrete is poured in the background, an excavator is at work on an 8 x 7-metre gallery.
Work kept progressing on the ITER platform during the summer recess.

Blinding concrete was poured over the rock surface of the future Assembly Hall adjacent to the Tokamak Seismic Pit. The resulting clean and flat 6,000 m² surface will be used as a working platform to install the reinforcement steel of the building's structural foundation.

In parallel, workers finalized rock excavation for the galleries that will run in the foundations. In the picture, an excavator is at work on an 8 x 7 metre gallery that will serve as an entry point for most of the electrical cables providing energy to the tools and devices to be used for assembly operations.

Work began on the networks of Contractor Area #2 and continued throughout the platform as manholes connecting the large 1.6-kilometre-long concrete piping of the underground drainage network were installed.

Foundation work on the Assembly Hall worksite will extend into March 2013, and drainage network installation should be completed by November of this year.


return to the latest published articles