Busy August on platform

Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Augmented reality | Assessing the future work environment

    As part of their collaboration within the Site Support Agreement*, ITER and its neighbour CEA are developing a novel approach to explore, analyze and assess the [...]

    Read more

  • Diagnostics and instrumentation | First welding on the vacuum vessel

    Beginning in 2035, ITER will open a window into "burning plasmas"—a state of matter that exists in the core of stars only. Observing, assessing and mo [...]

    Read more

  • Assembly | Machining workshop opens on site

    Construction of an on-site machining workshop began in December 2019 and was completed on schedule in September 2020.The new workshop will be operated by the D [...]

    Read more

  • Neutral Beam Test Facility | Power is ready for the prototype injector

    The European Domestic Agency has carried out successful site acceptance tests at the ITER Neutral Beam Test Facility on power supply equipment installed ov [...]

    Read more

  • In-vessel coils | First components arrive on site

    ITER has received the first shipments of mineral-insulated conductor for ITER's in-vessel coils. The first lengths are destined for winding and bending trials a [...]

    Read more

Of Interest

See archived entries

Busy August on platform

As blinding concrete is poured in the background, an excavator is at work on an 8 x 7-metre gallery. (Click to view larger version...)
As blinding concrete is poured in the background, an excavator is at work on an 8 x 7-metre gallery.
Work kept progressing on the ITER platform during the summer recess.

Blinding concrete was poured over the rock surface of the future Assembly Hall adjacent to the Tokamak Seismic Pit. The resulting clean and flat 6,000 m² surface will be used as a working platform to install the reinforcement steel of the building's structural foundation.

In parallel, workers finalized rock excavation for the galleries that will run in the foundations. In the picture, an excavator is at work on an 8 x 7 metre gallery that will serve as an entry point for most of the electrical cables providing energy to the tools and devices to be used for assembly operations.

Work began on the networks of Contractor Area #2 and continued throughout the platform as manholes connecting the large 1.6-kilometre-long concrete piping of the underground drainage network were installed.

Foundation work on the Assembly Hall worksite will extend into March 2013, and drainage network installation should be completed by November of this year.


return to the latest published articles