Subscribe options

Select your newsletters:

Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Monaco-ITER Fellows | New campaign announced

    The seventh recruitment campaign for the Monaco-ITER postdoctoral fellowship program opens on 13 January. Since 2008, thirty postdocs have carried out origin [...]

    Read more

  • Electrical network | The waking of the beast

    The beast had sat immobile for more than three years—no blood running in its veins, no electrical impulse shaking its nerves alive. With three long horns sticki [...]

    Read more

  • ITER staff | Nearing the 1,000 mark

    Given the breadth of assignments, schedules, and responsibilities it is impossible to capture a complete snapshot of ITER Organization staff at any given point [...]

    Read more

  • Image of the week | How cable became a coil

    We saw it being born, in the form of spooled lengths of jacketed conductor; we saw it being wrapped in white fiberglass tape and slowly transformed into a " [...]

    Read more

  • 25th ITER Council: All efforts converging toward the start of machine assembly

    The governing board of the ITER Organization, the ITER Council, concluded its Twenty-Fifth Meeting on Thursday 21 November. This was the last ITER Council meeti [...]

    Read more

Of Interest

See archived entries

Busy August on platform

As blinding concrete is poured in the background, an excavator is at work on an 8 x 7-metre gallery. (Click to view larger version...)
As blinding concrete is poured in the background, an excavator is at work on an 8 x 7-metre gallery.
Work kept progressing on the ITER platform during the summer recess.

Blinding concrete was poured over the rock surface of the future Assembly Hall adjacent to the Tokamak Seismic Pit. The resulting clean and flat 6,000 m² surface will be used as a working platform to install the reinforcement steel of the building's structural foundation.

In parallel, workers finalized rock excavation for the galleries that will run in the foundations. In the picture, an excavator is at work on an 8 x 7 metre gallery that will serve as an entry point for most of the electrical cables providing energy to the tools and devices to be used for assembly operations.

Work began on the networks of Contractor Area #2 and continued throughout the platform as manholes connecting the large 1.6-kilometre-long concrete piping of the underground drainage network were installed.

Foundation work on the Assembly Hall worksite will extend into March 2013, and drainage network installation should be completed by November of this year.


return to the latest published articles