Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Challenges | Managing risk in a first-of-a-kind project

    The classic approach to project management is to group risks into three separate categories. The first consists of known risks, the second of unknown risks, and [...]

    Read more

  • Steve Cowley | Projecting into the coming decades

    Steven Cowley, who now heads the Princeton Plasma Physics Laboratory (PPPL), gave a seminar last week at CEA-Cadarache and he had some good news regarding the s [...]

    Read more

  • Outreach | What vacuum does to marshmallows

    Every year in France, science is "à la fête" for two consecutive weekends in October. Free events and demonstrations—tailored particularly to school-a [...]

    Read more

  • Physics | 11th ITER International School announced

    The 11th ITER International School will be held from 20 to 24 July 2020, hosted by Aix-Marseille University in Aix-en-Provence, France. The subject of this year [...]

    Read more

  • Image of the week | An anniversary in blue, white and red

    ITER neighbour and close partner in fusion research, the CEA-Cadarache nuclear research centre, was established in October 1959. This week, it celebrated the 60 [...]

    Read more

Of Interest

See archived entries

Busy August on platform

As blinding concrete is poured in the background, an excavator is at work on an 8 x 7-metre gallery. (Click to view larger version...)
As blinding concrete is poured in the background, an excavator is at work on an 8 x 7-metre gallery.
Work kept progressing on the ITER platform during the summer recess.

Blinding concrete was poured over the rock surface of the future Assembly Hall adjacent to the Tokamak Seismic Pit. The resulting clean and flat 6,000 m² surface will be used as a working platform to install the reinforcement steel of the building's structural foundation.

In parallel, workers finalized rock excavation for the galleries that will run in the foundations. In the picture, an excavator is at work on an 8 x 7 metre gallery that will serve as an entry point for most of the electrical cables providing energy to the tools and devices to be used for assembly operations.

Work began on the networks of Contractor Area #2 and continued throughout the platform as manholes connecting the large 1.6-kilometre-long concrete piping of the underground drainage network were installed.

Foundation work on the Assembly Hall worksite will extend into March 2013, and drainage network installation should be completed by November of this year.


return to the latest published articles