Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Tokamak Complex | Interior design

    Fresh from the offices of the Design& Construction Integration Division, this cutaway drawing peels back the walls to reveal theinterior layout of the Tokam [...]

    Read more

  • Fusion world | A visit to Kyoto's heliotron

    At the Institute of Advanced Energy, Kyoto University, researchers have been exploring the heliotron concept of magnetic fusion device for more than half a cent [...]

    Read more

  • Construction site | The lights of autumn

    Summer is over in Provence and the beautiful autumn light is back, revealing every detail of the landscape... and of the ongoing works on the ITER construction [...]

    Read more

  • Cryostat | A true sense of size

    Just like a thermos provides the insulation to keep your coffee warm—or your water cold—the ITER cryostat raises a barrier around the superconducting magnets th [...]

    Read more

  • Image of the week | ITER at 10

    The ITER Organization was established ten years ago, on 24 October 2007. A week ahead of the official celebration, part of the ITER staff, now numbering 800, ga [...]

    Read more

Of Interest

See archived articles

Busy August on platform

As blinding concrete is poured in the background, an excavator is at work on an 8 x 7-metre gallery. (Click to view larger version...)
As blinding concrete is poured in the background, an excavator is at work on an 8 x 7-metre gallery.
Work kept progressing on the ITER platform during the summer recess.

Blinding concrete was poured over the rock surface of the future Assembly Hall adjacent to the Tokamak Seismic Pit. The resulting clean and flat 6,000 m² surface will be used as a working platform to install the reinforcement steel of the building's structural foundation.

In parallel, workers finalized rock excavation for the galleries that will run in the foundations. In the picture, an excavator is at work on an 8 x 7 metre gallery that will serve as an entry point for most of the electrical cables providing energy to the tools and devices to be used for assembly operations.

Work began on the networks of Contractor Area #2 and continued throughout the platform as manholes connecting the large 1.6-kilometre-long concrete piping of the underground drainage network were installed.

Foundation work on the Assembly Hall worksite will extend into March 2013, and drainage network installation should be completed by November of this year.


return to the latest published articles