Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • The magnet lab next door

    Two and a half years ago ITER and the French Alternative Energies and Atomic Energy Commission (CEA) entered a collaborationto prepare for the challenging task [...]

    Read more

  • Activity on every floor

    At every floor of the Tokamak Complex—from the lowest underground level (B2) all the way to the second regular level of the bioshield (L2)—there is intense acti [...]

    Read more

  • Bringing the Research Plan up to date

    The ITER Research Plan is an ITER baseline document which outlines the main lines of science and technology research derived from the project's mission goals. [...]

    Read more

  • Further validation for ring magnet fabrication

    Once a component mockup has been produced—and before fabrication can begin on the actual component or system—a manufacturing readiness review is required to ens [...]

    Read more

  • First central solenoid module ready for heat treatment

    In a major milestone, the US contractor responsible for the fabrication of the ITER central solenoid has successfully joined seven individual coil sections, or [...]

    Read more

Of Interest

See archived articles

Busy August on platform

As blinding concrete is poured in the background, an excavator is at work on an 8 x 7-metre gallery. (Click to view larger version...)
As blinding concrete is poured in the background, an excavator is at work on an 8 x 7-metre gallery.
Work kept progressing on the ITER platform during the summer recess.

Blinding concrete was poured over the rock surface of the future Assembly Hall adjacent to the Tokamak Seismic Pit. The resulting clean and flat 6,000 m2 surface will be used as a working platform to install the reinforcement steel of the building's structural foundation.

In parallel, workers finalized rock excavation for the galleries that will run in the foundations. In the picture, an excavator is at work on an 8 x 7 metre gallery that will serve as an entry point for most of the electrical cables providing energy to the tools and devices to be used for assembly operations.

Work began on the networks of Contractor Area #2 and continued throughout the platform as manholes connecting the large 1.6-kilometre-long concrete piping of the underground drainage network were installed.

Foundation work on the Assembly Hall worksite will extend into March 2013, and drainage network installation should be completed by November of this year.


return to the latest published articles