Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Upending tool | How to raise a sleeping giant

    How will the teams on site raise components weighing up to 450 tonnes from their horizontal delivery configurations to the upright orientation needed for assemb [...]

    Read more

  • SOFT 2018 | Conference opens in antique setting

    The ancient theatre of Taormina, in northeast Sicily, was built by the Romans on the foundations of an earlier Greek theatre. Still used to this day, the round [...]

    Read more

  • Former Council Chair Iotti | "Everyone should be congratulated!"

    For those who dreamed ITER in the 1990s, a visit to the construction site today is like stepping into a miracle. For Bob Iotti, who has been associated with the [...]

    Read more

  • In-vessel coils | Conductor qualified for manufacturing

    For magnet coils operating inside of the vacuum vessel, conventional insulation schemes are not an option. ITER will rely on mineral-insulated conductor technol [...]

    Read more

  • ITER Research Plan | The 400-page scenario

    The ITER Organization has just made publically available the most recent version of the ITER Research Plan, a 400-page document that describes the present visio [...]

    Read more

Of Interest

See archived entries

Bracing for a busy September

ITER Communications

Transporting an 800-ton load along the ITER Itinerary requires some heavy logistics. (Click to view larger version...)
Transporting an 800-ton load along the ITER Itinerary requires some heavy logistics.
The summer recess at ITER (the site will be closed the week of 12-18 August) will be followed by a flurry of activity.

On 6 September, on the initiative of Günther Oettinger, European Commissioner in charge of Energy, representatives at ministerial level of the seven ITER Members will convene at the ITER Headquarters to review the main progress accomplished. This will be the second time in the project's history that the highest-level government representatives of the seven ITER Members meet; the last time was 21 November 2006, on the day after the signature of the ITER Agreement.

Ten days later, the first technical tests will be performed on the ITER Itinerary. Organized jointly by Agence Iter France (AIF) and the DAHER Group, the operation will consist in verifying that the engineers' calculations agree with the reality of travelling the whole length of the Itinerary (104 km) with a convoy that mimicks the most exceptional ITER loads—800 tonnes, 40 metres in length, 9 metres in width, and 11 metres in height.

The "measurement campaign," as it is officially called by AIF, will be performed at night negociating the 16 roundabouts and crossing the 30 bridges that punctuate the Itinerary. The vehicle—an 88-axle self-propelled platform—will remain stationary during the day in order not to interfere with the heavy summer traffic. The public will be able to share in the spectacular event from two specifically designed viewing areas, one in Berre l'Etang where the platform will be stationed on 16 September and one in Peyrolles where it will arrive two days later.

In order to confirm that the organization among all involved entities is appropriate, a complete dress rehearsal, with all the logistics of an actual Highly Exceptional Convoy, will be organized in the following months. The first supersized ITER components (the US-manufactured drain tanks) should be delivered on site in June 2014.

As it has for the past six and a half years, Newsline will continue to report on all the events, large and small, that make the daily life and history of ITER.

We'll be back with more news on 26 August!