Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Cryoplant | Filled from floor to ceiling

    The ITER cryoplant used to be a vast echoey chamber with 5,400 m² of interior space divided into two areas; now, it is filled from floor to ceiling with industr [...]

    Read more

  • Cryostat | Adjusting, welding, testing ...

    The assembly of the ITER cryostat—the stainless steel "thermos" that insulates the ultra-cold superconducting magnets from the environment—is progress [...]

    Read more

  • Tokamak Building | Full steam ahead

    In this central arena of the construction site, construction teams are active three shifts a day—two full work shifts and a third, at night, dedicated to moving [...]

    Read more

  • Poloidal field coils | Turning tables and hot resin

    One of only two manufacturing facilities located on the ITER site, the Poloidal Field Coils Winding Facility was constructed by Europe to house the winding, imp [...]

    Read more

  • Assembly Hall | One giant standing

    Two identical handling tools in the Assembly Hall will play a critical role in preparing ITER's nine vacuum vessel sectors for their final journey: transport by [...]

    Read more

Of Interest

See archived entries

Warm concrete in the chilly dawn

Some 800 cubic metres of warm (14-17 °C) concrete were poured in the course of the 10-hour long operation. (Click to view larger version...)
Some 800 cubic metres of warm (14-17 °C) concrete were poured in the course of the 10-hour long operation.
Concrete pouring operations resumed early on Wednesday 22 January in the southern corner of the Tokamak Pit.

Two large concrete pumps, one equipped with a 58-metre extensible arm (the largest available in France), were mobilized to fill a 500 square-metre area with specially formulated concrete produced in the nearby batching plant.

Operations began at 4:00 a.m. and continued for 10 hours. This was the second segment (out of 15) poured for the Tokamak Complex basemat, and one of three that will support the future ITER Diagnostics Building.

Special measures were set into place to counter the early morning cold, such as producing warm concrete in the batching plant (by heating the water and gravel) and using plastic sheeting as the work progressed to avoid too rapid cooling.

The thick fog blanket that covered the ITER site added to the eerie atmosphere of the early dawn operations. (Click to view larger version...)
The thick fog blanket that covered the ITER site added to the eerie atmosphere of the early dawn operations.
Hot air blowers were also activated once the pour was complete to regulate the drying process.

The complete Tokamak Complex basemat (1.5-metre-thick) is scheduled to be in place in July. Work will resume next week on the rebar installation in the central area of the Tokamak Pit.



return to the latest published articles