Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Heating | A pinch of moondust in the ITER plasma

    One day in the distant future, fusion plants might be fuelled by helium 3—an isotope that is extremely scarce on Earth but reputed to be abundant on the Moon. B [...]

    Read more

  • Delivery | 2,000 km through canals, locks and tunnels

    When the thruway is closed, one takes the back roads. And when it's low-water season on the Rhine-Rhône canal, a barge leaving Switzerland for the Mediterranean [...]

    Read more

  • Monaco Fellows | A hand in shaping ITER

    For the sixth time, ITER is welcoming a group of five young researchers as part of the Monaco-ITER postdoctoral fellowship scheme. Working alongside experienced [...]

    Read more

  • On site | Drone survey on a perfect day

    There are days in winter when the skies over Provence are perfectly transparent. Snowy peaks 200 kilometres away appear close enough to be touched and farms, co [...]

    Read more

  • AAAS conference | ITER on the world science stage

    With more than 120,000 members globally, the American Association for the Advancement of Science (AAAS) is billed as the world's largest scientific society. The [...]

    Read more

Of Interest

See archived entries

Warm concrete in the chilly dawn

Some 800 cubic metres of warm (14-17 °C) concrete were poured in the course of the 10-hour long operation. (Click to view larger version...)
Some 800 cubic metres of warm (14-17 °C) concrete were poured in the course of the 10-hour long operation.
Concrete pouring operations resumed early on Wednesday 22 January in the southern corner of the Tokamak Pit.

Two large concrete pumps, one equipped with a 58-metre extensible arm (the largest available in France), were mobilized to fill a 500 square-metre area with specially formulated concrete produced in the nearby batching plant.

Operations began at 4:00 a.m. and continued for 10 hours. This was the second segment (out of 15) poured for the Tokamak Complex basemat, and one of three that will support the future ITER Diagnostics Building.

Special measures were set into place to counter the early morning cold, such as producing warm concrete in the batching plant (by heating the water and gravel) and using plastic sheeting as the work progressed to avoid too rapid cooling.

The thick fog blanket that covered the ITER site added to the eerie atmosphere of the early dawn operations. (Click to view larger version...)
The thick fog blanket that covered the ITER site added to the eerie atmosphere of the early dawn operations.
Hot air blowers were also activated once the pour was complete to regulate the drying process.

The complete Tokamak Complex basemat (1.5-metre-thick) is scheduled to be in place in July. Work will resume next week on the rebar installation in the central area of the Tokamak Pit.



return to the latest published articles