Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Crane operator | A cabin in the sky

    There are times, at dusk, when the ITER construction platform resembles an airport, with roads and buildings illuminated by yellow and white lights. From their [...]

    Read more

  • Assembly | A colossal task made manageable

    For the execution of work during the next project phase—machine and plant assembly up to First Plasma—the ITER Organization has chosen a contractual approach th [...]

    Read more

  • Neutral Beam Test Facility | A new agreement for a new era

    The ITER Organization and the Italian consortium Consorzio RFX* have signed a new agreement governing the construction and operation of the ITER Neutral Beam Te [...]

    Read more

Of Interest

See archived entries

Warm concrete in the chilly dawn

Some 800 cubic metres of warm (14-17 °C) concrete were poured in the course of the 10-hour long operation. (Click to view larger version...)
Some 800 cubic metres of warm (14-17 °C) concrete were poured in the course of the 10-hour long operation.
Concrete pouring operations resumed early on Wednesday 22 January in the southern corner of the Tokamak Pit.

Two large concrete pumps, one equipped with a 58-metre extensible arm (the largest available in France), were mobilized to fill a 500 square-metre area with specially formulated concrete produced in the nearby batching plant.

Operations began at 4:00 a.m. and continued for 10 hours. This was the second segment (out of 15) poured for the Tokamak Complex basemat, and one of three that will support the future ITER Diagnostics Building.

Special measures were set into place to counter the early morning cold, such as producing warm concrete in the batching plant (by heating the water and gravel) and using plastic sheeting as the work progressed to avoid too rapid cooling.

The thick fog blanket that covered the ITER site added to the eerie atmosphere of the early dawn operations. (Click to view larger version...)
The thick fog blanket that covered the ITER site added to the eerie atmosphere of the early dawn operations.
Hot air blowers were also activated once the pour was complete to regulate the drying process.

The complete Tokamak Complex basemat (1.5-metre-thick) is scheduled to be in place in July. Work will resume next week on the rebar installation in the central area of the Tokamak Pit.



return to the latest published articles