Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Open Doors Day | An intense and unforgettable experience

    Saturday was Jacques's birthday. At age 90, the long-retired engineer from Aix-en-Provence had only one item on his wish list: to visit ITER for a third time an [...]

    Read more

  • Power conversion | A potent illustration of the "One ITER" spirit

    Europe made the buildings; the piping came from India; China and Korea provided the transformers; Russia manufactured the massive 'busbar' network. The ITER Org [...]

    Read more

  • Fusion world | Upgrade completed on DIII-D tokamak

    The DIII-D National Fusion Program (US) has completed a series of important enhancements to its fusion facility, providing researchers with several first-of-a-k [...]

    Read more

  • Vacuum lab | Ensuring leak test sensitivity

    A helium leak test is one of several factory acceptance tests planned for the sectors of the ITER vacuum vessel before they are shipped to ITER. In a vacuum lab [...]

    Read more

  • Bookmark | The Future of Fusion Energy

    To write about fusion is to walk a fine line between the temptation of lyricism and the arid demands of scientific accuracy. Whereas the general media tends to [...]

    Read more

Of Interest

See archived entries

Warm concrete in the chilly dawn

Some 800 cubic metres of warm (14-17 °C) concrete were poured in the course of the 10-hour long operation. (Click to view larger version...)
Some 800 cubic metres of warm (14-17 °C) concrete were poured in the course of the 10-hour long operation.
Concrete pouring operations resumed early on Wednesday 22 January in the southern corner of the Tokamak Pit.

Two large concrete pumps, one equipped with a 58-metre extensible arm (the largest available in France), were mobilized to fill a 500 square-metre area with specially formulated concrete produced in the nearby batching plant.

Operations began at 4:00 a.m. and continued for 10 hours. This was the second segment (out of 15) poured for the Tokamak Complex basemat, and one of three that will support the future ITER Diagnostics Building.

Special measures were set into place to counter the early morning cold, such as producing warm concrete in the batching plant (by heating the water and gravel) and using plastic sheeting as the work progressed to avoid too rapid cooling.

The thick fog blanket that covered the ITER site added to the eerie atmosphere of the early dawn operations. (Click to view larger version...)
The thick fog blanket that covered the ITER site added to the eerie atmosphere of the early dawn operations.
Hot air blowers were also activated once the pour was complete to regulate the drying process.

The complete Tokamak Complex basemat (1.5-metre-thick) is scheduled to be in place in July. Work will resume next week on the rebar installation in the central area of the Tokamak Pit.



return to the latest published articles