Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Video | How does the ITER cryoplant work?

    Cold is essential to ITER—10,000 tonnes of superconducting magnets, the thermal shield that surrounds the machine, the cryopumps that achieve the high vacuum in [...]

    Read more

  • Component logistics | Consistency "from the cradle to the grave"

    There's a fun and easy way to demonstrate the importance of having all ITER parts properly tagged and identified in storage—organize a workshop and ask four com [...]

    Read more

  • Image of the week | Brewing storm

    In Provence, one gets tired of blue skies... so when the opportunity arises to capture the ITER site plunged in the darkness of an approaching storm, we rush to [...]

    Read more

  • Toroidal field coils | First cold test in Europe

    The first ITER toroidal field coil winding pack has spent nearly 20 days in a specially conceived cryostat at minus 193 °C (80 K), in a cold testing operation t [...]

    Read more

  • Central solenoid | All conductor received

    Officials from the US and Japanese fusion energy programs were at General Atomics' Magnet Technologies Center in California in early May to celebrate the delive [...]

    Read more

Of Interest

See archived articles

Warm concrete in the chilly dawn

Some 800 cubic metres of warm (14-17 °C) concrete were poured in the course of the 10-hour long operation. (Click to view larger version...)
Some 800 cubic metres of warm (14-17 °C) concrete were poured in the course of the 10-hour long operation.
Concrete pouring operations resumed early on Wednesday 22 January in the southern corner of the Tokamak Pit.

Two large concrete pumps, one equipped with a 58-metre extensible arm (the largest available in France), were mobilized to fill a 500 square-metre area with specially formulated concrete produced in the nearby batching plant.

Operations began at 4:00 a.m. and continued for 10 hours. This was the second segment (out of 15) poured for the Tokamak Complex basemat, and one of three that will support the future ITER Diagnostics Building.

Special measures were set into place to counter the early morning cold, such as producing warm concrete in the batching plant (by heating the water and gravel) and using plastic sheeting as the work progressed to avoid too rapid cooling.

The thick fog blanket that covered the ITER site added to the eerie atmosphere of the early dawn operations. (Click to view larger version...)
The thick fog blanket that covered the ITER site added to the eerie atmosphere of the early dawn operations.
Hot air blowers were also activated once the pour was complete to regulate the drying process.

The complete Tokamak Complex basemat (1.5-metre-thick) is scheduled to be in place in July. Work will resume next week on the rebar installation in the central area of the Tokamak Pit.



return to the latest published articles