  • Upending tool | How to raise a sleeping giant

    How will the teams on site raise components weighing up to 450 tonnes from their horizontal delivery configurations to the upright orientation needed for assemb [...]

    Read more

  • SOFT 2018 | Conference opens in antique setting

    The ancient theatre of Taormina, in northeast Sicily, was built by the Romans on the foundations of an earlier Greek theatre. Still used to this day, the round [...]

    Read more

  • Former Council Chair Iotti | "Everyone should be congratulated!"

    For those who dreamed ITER in the 1990s, a visit to the construction site today is like stepping into a miracle. For Bob Iotti, who has been associated with the [...]

    Read more

  • In-vessel coils | Conductor qualified for manufacturing

    For magnet coils operating inside of the vacuum vessel, conventional insulation schemes are not an option. ITER will rely on mineral-insulated conductor technol [...]

    Read more

  • ITER Research Plan | The 400-page scenario

    The ITER Organization has just made publically available the most recent version of the ITER Research Plan, a 400-page document that describes the present visio [...]

    Read more

Of Interest

See archived entries

Big yellow crane, right on time

R.A.

With a lifting capacity of 200 tonnes (plus an auxiliary 50-tonne hook) the crane will be used to lift and handle the 54 cryostat segments that will arrive from India. (Click to view larger version...)
With a lifting capacity of 200 tonnes (plus an auxiliary 50-tonne hook) the crane will be used to lift and handle the 54 cryostat segments that will arrive from India.
Right on time! On Wednesday 12 February, nine months after construction began on ITER's on-site Cryostat Workshop, the first elements of the workshop's gantry crane were delivered to the ITER site.

Manufactured in Italy by Danieli Centro Cranes, the gantry crane will be assembled on site from six 12-metre-long beams bolted together to make a twin beam assembly that carries a motor trolley lifting device.

Once installed, it will stand 18 metres high and be able to travel by rail the entire length of the huge workshop (~100 metres).

With a lifting capacity of 200 tonnes (plus an auxiliary 50-tonne hook) the crane will be used to lift and handle the 54 cryostat segments that will arrive from India. After welding, these segments will form the four cryostat sections that will enclose the ITER Tokamak.

The temporary Cryostat Workshop is the only building on the ITER platform that is not under European construction responsibility. The large steel-framed building stands on a small football-field-sized parcel (50 x 120 m) that has been made available to the Indian Domestic Agency.

As part of the cryostat manufacturing contract awarded in 2012 by ITER India to Larsen & Toubro, the Indian manufacturer is also responsible for on-site assembly. Larsen & Toubro awarded a contract to SPIE Batignolles for the construction of the Cryostat Workshop.