Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Neighbours | In goes the antenna

    Just a short distance from the ITER site, the Institute for Magnetic Fusion Research (IRFM) is modifying the Tore Supra plasma facility which, once transformed, [...]

    Read more

  • Remote handling | Off-site test facility for design evaluation

    Through a technical collaboration established between the ITER Organization and the UK Atomic Energy Authority (UKAEA) in 2017, the UKAEA's centre for Remote Ap [...]

    Read more

  • Poloidal field coils | A tailor-made ring

    They work like tailors, carefully taking measurements and cutting immaculate fabric with large pairs of scissors. But they're not making a white three-piece sui [...]

    Read more

  • Fusion world | Record results at KSTAR

    Experiments in the Korean tokamakKSTAR in 2017 achieved record-length periods of ELM suppression by the application of three-dimensional magnetic fields with in [...]

    Read more

  • JT-60 SA| Cryostat ready for Europe-Japan tokamak

    The cryostat vessel body of the JT-60SA tokamakhas been successfully manufactured and pre-assembled at a factory in Spain, and will soon be transferred to the J [...]

    Read more

Of Interest

See archived articles

Six years later and still delivering

K.D.

Nine strand suppliers around the world are contributing to the ITER magnet systems, including three suppliers that are new to the world market. (Click to view larger version...)
Nine strand suppliers around the world are contributing to the ITER magnet systems, including three suppliers that are new to the world market.
It's the longest running ITER Organization-Domestic Agency meeting at a technical level.

For the last six years, the Domestic Agencies responsible for delivering ITER's high-tech superconductors have met twice a year to share experience, talk over challenges and mutualize technological expertise.

Despite a multiplicity of ITER conductor types (poloidal field, toroidal field, central solenoid, correction coils, feeders), strand production sites (nine), conductor jacketing lines (five), and participating Members (China, Europe, Korea, Japan, Russia, US), the semi-annual Conductor Meeting has been able to promote synergies and enable constructive dialogue.

And the results are tangible. At the Conductor Meeting organized on 18-20 March, Arnaud Devred, head of Superconductor Systems & Auxiliaries at ITER, reviewed the latest accomplishments.

After five years of ramping up, strand production for the toroidal field conductors is almost completed. Nearly 480 tonnes of niobium-tin (Nb3Sn) strands (>100,000 km) have been registered in the Conductor Database and one producing Domestic Agency, Korea, has entirely completed its share. The cabling and jacketing of conductor unit lengths (ULs) is underway in the six Domestic Agencies involved. Sixty-three 760-metre ULs and twenty-six 415-metre ULs have been registered and are now stored for coil winding, an amount corresponding to approximately 12 toroidal field coils.

The meeting held on 18-20 March at ITER Headquarters was the eleventh in a long line of Conductor Meetings. The semi-annual meetings have been an important forum for collaboration and exchange for the six producing Domestic Agencies and the ITER Organization. (Click to view larger version...)
The meeting held on 18-20 March at ITER Headquarters was the eleventh in a long line of Conductor Meetings. The semi-annual meetings have been an important forum for collaboration and exchange for the six producing Domestic Agencies and the ITER Organization.
Suppliers have also registered 185 tonnes of niobium-titanium (Nb-Ti) poloidal field strand, 20 tonnes of Nb-Ti strand for the correction coil and feeder conductors, and 25 tonnes of Nb3Sn strand for the central solenoid in the Conductor Database.

China reports that it has completed half of the correction coil conductor ULs and two correction coil busbar conductors; Japan has completed one 613-metre UL and one 918-metre UL for central solenoid module CS3L.

Over the years, the ITER Organization has validated 8,475 control points, relying on 29,550 strand critical current measurements. "Thanks to the Conductor Database and close relationships between the ITER Organization and the Domestic Agencies, these control points were cleared in a timely manner, allowing industrial production to proceed worldwide," says Arnaud.

The next Conductor Meeting is planned for October 2014.



return to the latest published articles