Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • IAEA and ITER | Even closer cooperation

    Under Practical Arrangements signed in June, the International Atomic Energy Agency and the ITER Organization will be expanding and deepening a long history of [...]

    Read more

  • Neutral Beam Test Facility | High voltage component for MITICA

    Creating reliable high-energy neutral beams at ITER parameters, from a negative ion source, requires such a large technological leap that the components of the [...]

    Read more

  • 24th ITER Council | En route to First Plasma, 63% of the work is done

    The ITER Council has met for the twenty-fourth time since the signature of the ITER Agreement. Representatives from China, the European Union, India, Japan, Kor [...]

    Read more

  • Upper ports | A very international effort

    The 18 upper ports of the ITER vacuum vessel are procured by Russia, manufactured in Germany, and mounted (in part) on the vessel sectors by contractors in Ital [...]

    Read more

  • Paint job | One level done, five to go

    The job is done and the effect is spectacular. At the deepest basement level (B2) of the Tokamak Building, the floors, walls, and ceilings are now perfectly whi [...]

    Read more

Of Interest

See archived entries

An anchor for the backbone

R.A.

While concrete pouring was underway last Wednesday on the last segment of the Tokamak Complex basemat, laser measurements were still being performed on a large steel ring, deeply anchored at the very centre of the plot.

Laser measurements on the circular steel ring were still being performed while concrete pouring was underway last Wednesday. (Click to view larger version...)
Laser measurements on the circular steel ring were still being performed while concrete pouring was underway last Wednesday.
Topped by a temporary, blue steel structure designed to prevent deformation, the steel ring is part of the support system for the huge inner support column—the steel backbone that, along will seven radial beams, will stabilize the vacuum vessel sectors during the first stages of machine assembly.

Because it was vitally important that the circular ring and its four associated inserted plates remain perfectly positioned, the temporary steel structure guaranteed the ring's rigidity during the pour and regular laser surveys ensured that no deviation had occurred from the original position.

The inner support column will form the axis and backbone of the Tokamak during the first phase of machine assembly. (Click to view larger version...)
The inner support column will form the axis and backbone of the Tokamak during the first phase of machine assembly.
During first-phase Tokamak assembly operations, the inner support column will form the axis of the Tokamak. Once the nine sectors of the vacuum vessel are assembled and welded, the column will be removed from the machine and the central solenoid will take its place.

Last Wednesday, as ITER celebrated the "Final Pour" of the Tokamak Complex basemat, the first element of an assembly tool was in place, ready for an operation that should begin in 2017.


return to the latest published articles