Enable Recite

Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Cryoplant | First steps toward commissioning

    Every week since the beginning of November, a tube trailer filled with approximately 4,600 cubic metres (750 kg) of compressed gaseous helium delivers its load [...]

    Read more

  • Training | Seeking the next group of Monaco-ITER Fellows

    Recruitment opens for the next Monaco-ITER Postdoctoral Fellowship campaign on 17 January 2022. If your PhD was awarded after 1 January 2019—or you are about to [...]

    Read more

  • Contemporary art | Venet's "arcs" are as heavy as ITER coils

    A 'conceptual artist' among the most prominent on the art scene today, Bernar Venet is not impressed by massive towering steel structures like those in the ITER [...]

    Read more

  • Image of the week | Final activities on Europe's first sector

    The first vacuum vessel sector produced in Europe will arrive at ITER next year. Five of ITER's nine vacuum vessel sectors are the responsibility of Europe's AM [...]

    Read more

  • Vacuum vessel sector preparation | Lessons learned reduce work time by half

    In life as in the assembly of the ITER machine, 'lessons learned' are what makes progress possible. Gains in wisdom, time, skill, investment can be incremental; [...]

    Read more

Of Interest

See archived entries

An anchor for the backbone

While concrete pouring was underway last Wednesday on the last segment of the Tokamak Complex basemat, laser measurements were still being performed on a large steel ring, deeply anchored at the very centre of the plot.

Laser measurements on the circular steel ring were still being performed while concrete pouring was underway last Wednesday. (Click to view larger version...)
Laser measurements on the circular steel ring were still being performed while concrete pouring was underway last Wednesday.
Topped by a temporary, blue steel structure designed to prevent deformation, the steel ring is part of the support system for the huge inner support column—the steel backbone that, along will seven radial beams, will stabilize the vacuum vessel sectors during the first stages of machine assembly.

Because it was vitally important that the circular ring and its four associated inserted plates remain perfectly positioned, the temporary steel structure guaranteed the ring's rigidity during the pour and regular laser surveys ensured that no deviation had occurred from the original position.

The inner support column will form the axis and backbone of the Tokamak during the first phase of machine assembly. (Click to view larger version...)
The inner support column will form the axis and backbone of the Tokamak during the first phase of machine assembly.
During first-phase Tokamak assembly operations, the inner support column will form the axis of the Tokamak. Once the nine sectors of the vacuum vessel are assembled and welded, the column will be removed from the machine and the central solenoid will take its place.

Last Wednesday, as ITER celebrated the "Final Pour" of the Tokamak Complex basemat, the first element of an assembly tool was in place, ready for an operation that should begin in 2017.


return to the latest published articles