Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • On site | ITER celebrates important milestones

    On 16 June 2022, the ITER amphitheatre was packed with life again after two years of silence, part of a new project culture initiative called "Commit to De [...]

    Read more

  • Port cell maintenance | A full-scale mockup for dress rehearsals

    Every port in the ITER vacuum vessel has a corresponding port cell in the Tokamak Building. These corridor-like spaces allow heating and fuelling pipes, electri [...]

    Read more

  • Magnets | Have the last pancake!

    After close to five years of intense activity, the winding table at the south end of the European poloidal field coil factory on site is now empty. Last week, t [...]

    Read more

  • 30th ITER Council: Progress in a time of challenge and transition

    The Council chamber on the fifth floor of the ITER Headquarters building resonated once again with the sound of voices as Member representatives gathered for th [...]

    Read more

  • Open Doors Day | Back together again

    After more than two years, ITER has resumed a tradition that dates back to 2007—Open Doors Day. On Saturday 18 June, more than 50 "volunteers," staff [...]

    Read more

Of Interest

See archived entries

First plant components delivered to ITER

The trailer truck that pulled to a stop alongside the Poloidal Field Coils Winding Facility last Wednesday was nothing out of the ordinary—just a regular truck that didn't even qualify as a convoi exceptionnel.

The load it carried, however, was of highly symbolic value for ITER.

ITER personnel check the contents of the four crates delivered to the ITER site on Thursday 4 September 2014. From left to right: Ken Blackler, head of Assembly & Operations; Sergio Orlandi, director for Plant System Engineering (representing ITER Director-General Osamu Motojima); Piotr Pajak, electrical engineer; Joël Hourtoule, Electrical Power Distribution section leader; Gilles Consolo, electrical technician. (Click to view larger version...)
ITER personnel check the contents of the four crates delivered to the ITER site on Thursday 4 September 2014. From left to right: Ken Blackler, head of Assembly & Operations; Sergio Orlandi, director for Plant System Engineering (representing ITER Director-General Osamu Motojima); Piotr Pajak, electrical engineer; Joël Hourtoule, Electrical Power Distribution section leader; Gilles Consolo, electrical technician.
The four wooden crates solidly attached to its flatbed contained the very first plant components delivered to the ITER worksite: 12 high voltage surge arrestors supplied by the US Domestic Agency as part of the US contribution to the installation's steady state electrical system.

"This is a historic and meaningful moment," said Ken Blackler, head of the Assembly & Operations Division, as the crates were being unloaded into the building for temporary storage. "These are the first of many thousands of components to be delivered to ITER by the project's Members."

Key actors in the shipping and delivery of these first plant components included ITER's Yanchun Qiao, Transport & Logistics Responsible Officer, and DAHER's operations manager Laurence Prudhomme. (Click to view larger version...)
Key actors in the shipping and delivery of these first plant components included ITER's Yanchun Qiao, Transport & Logistics Responsible Officer, and DAHER's operations manager Laurence Prudhomme.
Surge arresters have the same function as a home surge protection device that prevents excess voltage from flowing straight from the grid to appliances or equipment in the case of a voltage surge.

With one big difference, however: whereas a circuit breaker or a fuse "interrupts" the current flow by creating a gap in the circuit, a surge arrester diverts the considerable amount of energy generated by a surge to the ground.

As their name suggests, surge arresters are designed to protect the transformers from a major voltage surge of the kind that lightning can cause. Four metres in height, they are calibrated to divert the considerable amount of energy generated by a surge to the ground. (Click to view larger version...)
As their name suggests, surge arresters are designed to protect the transformers from a major voltage surge of the kind that lightning can cause. Four metres in height, they are calibrated to divert the considerable amount of energy generated by a surge to the ground.
"The ITER surge arrestors are calibrated to short circuit whenever they detect a voltage higher than nominal (of the order of 400 kV), which would be the case if a bolt of lightning hits the switchyard," explains Joël Hourtoule, ITER Electrical Power Distribution section leader.

The 12 surge arresters delivered on 4 September are part of a large system that will be installed between the RTE switchyard and the transformers that feed power to the installation.

Twelve each of the following components—line disconnectors that physically separate the 400 kV RTE switchyard from the ITER installation, circuit breakers to protect the transformers, and potential and current transducers—will be shipped to ITER to equip four transformers fed by three-phase electric power.

The full set of components is expected at the ITER site before the end of the month for assembly and installation in early 2015.

For all the parties involved—ITER Organization, US ITER, the manufacturer ABB, and the logistics service provider DAHER who handled the shipment all the way from New York—this first delivery provided a concrete opportunity to test the administrative, technical, industrial and regulatory procedures that will accompany the procurement of plant and machine components by the ITER Members.

"The proper planning and timely delivery of these first plant components—in conformity with the schedule proposed in 2010—is an example to be followed," said Directorate head Sergio Orlandi (Plant System Engineering) who represented ITER Director-General Osamu Motojima at the short ceremony that followed the unpacking of the crates.

Click to read the press release in English or in French.


return to the latest published articles