  • Summer postcards from the ITER worksite

    The latest harvest of ITER construction photos may be taken from the same point—the tallest crane on site—but there is always an abundance of new detail to be g [...]

    Read more

  • The ring fortress

    ITER'ssteel-and-concretebioshield has become the definingfeature of Tokamak Complex construction. Twolevels only remain to be poured (out of six). It is a 'rin [...]

    Read more

  • The wave factory

    A year ago, work was just beginning on the steel reinforcement for the building's foundation slab. The Radio Frequency Heating Building is now nearing the last [...]

    Read more

  • It's all happening inside

    Since the giant poster was added to the Assembly Hall's completed exterior in June 2016 the building has lookedfrom afar like a finished project. Butinside, tea [...]

    Read more

  • Along skid row

    They look like perfectly aligned emergency housing units. But of course they're not: the 18 concrete structures in the ITER cryoplant are massive pads that will [...]

    Read more

Of Interest

See archived articles

Expert panel reviews cryopump systems design

The preliminary design review aimed to confirm the technical maturity of the design and prepare the manufacturing of a torus pre-production cryopump. (Click to view larger version...)
The preliminary design review aimed to confirm the technical maturity of the design and prepare the manufacturing of a torus pre-production cryopump.
The designs of the ITER cryopumps and cryogenic supply systems are now accelerating towards completion. Last week a three-day preliminary design review (PDR) was held at ITER Headquarters to confirm the technical maturity of the design, prepare the manufacturing of a torus pre-production cryopump and pursue developments towards the Procurement Arrangement.

"We have to make absolutely sure that everything is going in the right direction," explains Robert Pearce, ITER Vacuum Pumping Section Leader and the organizer of the review. "It is very important, at this stage, to present the design status to a panel of distinguished independent experts that will see if there's a problem we haven't identified and come up with pertinent suggestions ..."

This PDR for the ITER cryopumps and front end cryodistribution system was one of the largest ever held at ITER. (Click to view larger version...)
This PDR for the ITER cryopumps and front end cryodistribution system was one of the largest ever held at ITER.
Wolfgang Obert, Cryogenic Group Leader at JET, who was responsible for the cutting edge design and operation of JET cryogenics system, was the review Chair. He was supported by: Hans Falter, who led the development of neutral beams at JET and IPP, Garching; Laurent Tavian, responsible for CERN's cryogenic systems; and Larry Baylor, a world expert in pellet injection development.

All together, the meeting was attended by more than 60 people from ITER, the European Domestic Agency F4E and European Associates either at Headquarters or through video conference. This PDR for the ITER cryopumps and front end cryodistribution system was one of the largest ever held at ITER.

The next big step is scheduled for the end of the year, with the call for tender for a full size pre-production torus cryopump.



return to the latest published articles