Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Magnets | CEA delivers ITER cryogenic instrumentation

    The ITER Organization has relied on the French CEA institute and its expertise in cryogenics and large superconducting magnets for the specialized instrumentati [...]

    Read more

  • Sector sub-assembly | Twin meets twin

    Although they were born one full year apart, they are identical twins: when the second vacuum vessel sector sub-assembly tool (SSAT-2) is complete, nothing will [...]

    Read more

  • R&D in Europe | Working with industry on digital hydraulics

    A contract signed with the European Domestic Agency is helping Finnish industry innovate in the domain of digital hydraulic valves. The result could interest IT [...]

    Read more

  • Diagnostics | What is the plasma shape? Ask the flux loop

    Inside the machine, the flux loop diagnostic will provide important information to operators on the boundary shape, energy and stability of the plasma. In ITE [...]

    Read more

  • Image of the week | Communicators of all countries, unite!

    ITER is a fascinating story to tell—how it began and how it developed, the challenges it has never ceased to face, the awe its infrastructure and components ins [...]

    Read more

Of Interest

See archived entries

Three giants take position on the platform

Giants... Three of the five cranes planned for Tokamak Complex construction activities will rise over 75 metres (76 m, 80 m and 82 m) and have lifting capacities of 6-8 tonnes at the tip of their 55- to 65-metre-long booms.

Three of the five cranes planned for Tokamak Complex construction activities will rise over 75 metres (76 m, 80 m and 82 m) and have lifting capacities of 6-8 tonnes at the tip of their 55- to 65-metre-long booms. (Click to view larger version...)
Three of the five cranes planned for Tokamak Complex construction activities will rise over 75 metres (76 m, 80 m and 82 m) and have lifting capacities of 6-8 tonnes at the tip of their 55- to 65-metre-long booms.
The giants will not be alone. As wall erection is due to begin before the end of this month, two other cranes ranging in height from 55 to 63 metres "under the hook," are in various stages of assembly. One, the central crane (52 metres high), will be anchored right in the middle of the Tokamak Complex basemat slab. Equipped with a shorter boom (35 metres), it will handle loads of up to 9 tonnes.

Whereas laying rebar for the construction of the basemat slab required a lifting capacity of 1.5 to 2 tonnes, the construction activities planned in the Tokamak Pit will require stronger "workhorses," as heavy prefabricated elements and five-metre pieces of formwork will be handled.

As assembly work was progressing on the two large cranes closest to ITER Headquarters, anchorage for the the central crane (52 metres high) was visible on this picture of the Tokamak Complex basemat slab. Equipped with a 35-metre boom, the central crane will handle loads of up to 9 tonnes. (Click to view larger version...)
As assembly work was progressing on the two large cranes closest to ITER Headquarters, anchorage for the the central crane (52 metres high) was visible on this picture of the Tokamak Complex basemat slab. Equipped with a 35-metre boom, the central crane will handle loads of up to 9 tonnes.
Operating in a relatively restricted area, the Tokamak Complex cranes will be guided by sophisticated interference software that will coordinate their movements and ensure the safety of the handling operations.

The two large cranes closest to ITER Headquarters have now reached their final height. Where it takes one week to assemble a standard 45-metre crane, it will have taken four to raise these monsters to their full stature.


return to the latest published articles