Subscribe options

Select your newsletters:

Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Divertor | Far more than a fancy ashtray

    It has been likened to the filter of a swimming pool or an oversized ashtray. It has been called alien in shape and hellish in its affinity for heat. But whatev [...]

    Read more

  • Council milestone #50 | The way to assembly is open

    Passing an ITER Council milestone is always an achievement. Passing this milestone at this moment is much more than that: it is a demonstration that, despite th [...]

    Read more

  • Deliveries | A third magnet ready for transport to ITER

    Three ITER magnets are now in transit to ITER from different points on the globe—two toroidal field magnets and one poloidal field coil. In terms of component w [...]

    Read more

  • Heaviest load yet | Europe's coil soon to hit the road

    It's big, it's heavy, it's precious and it's highly symbolic: the toroidal field coil that was unloaded at Marseille industrial harbour on 17 March is the most [...]

    Read more

  • Russia's ring coil | Entering the final sequence

    The smallest of ITER's poloidal field coils is entering the final sequence in a long series of activities that transform cable-in-conduit superconductor into a [...]

    Read more

Of Interest

See archived entries

Three giants take position on the platform

Giants... Three of the five cranes planned for Tokamak Complex construction activities will rise over 75 metres (76 m, 80 m and 82 m) and have lifting capacities of 6-8 tonnes at the tip of their 55- to 65-metre-long booms.

Three of the five cranes planned for Tokamak Complex construction activities will rise over 75 metres (76 m, 80 m and 82 m) and have lifting capacities of 6-8 tonnes at the tip of their 55- to 65-metre-long booms. (Click to view larger version...)
Three of the five cranes planned for Tokamak Complex construction activities will rise over 75 metres (76 m, 80 m and 82 m) and have lifting capacities of 6-8 tonnes at the tip of their 55- to 65-metre-long booms.
The giants will not be alone. As wall erection is due to begin before the end of this month, two other cranes ranging in height from 55 to 63 metres "under the hook," are in various stages of assembly. One, the central crane (52 metres high), will be anchored right in the middle of the Tokamak Complex basemat slab. Equipped with a shorter boom (35 metres), it will handle loads of up to 9 tonnes.

Whereas laying rebar for the construction of the basemat slab required a lifting capacity of 1.5 to 2 tonnes, the construction activities planned in the Tokamak Pit will require stronger "workhorses," as heavy prefabricated elements and five-metre pieces of formwork will be handled.

As assembly work was progressing on the two large cranes closest to ITER Headquarters, anchorage for the the central crane (52 metres high) was visible on this picture of the Tokamak Complex basemat slab. Equipped with a 35-metre boom, the central crane will handle loads of up to 9 tonnes. (Click to view larger version...)
As assembly work was progressing on the two large cranes closest to ITER Headquarters, anchorage for the the central crane (52 metres high) was visible on this picture of the Tokamak Complex basemat slab. Equipped with a 35-metre boom, the central crane will handle loads of up to 9 tonnes.
Operating in a relatively restricted area, the Tokamak Complex cranes will be guided by sophisticated interference software that will coordinate their movements and ensure the safety of the handling operations.

The two large cranes closest to ITER Headquarters have now reached their final height. Where it takes one week to assemble a standard 45-metre crane, it will have taken four to raise these monsters to their full stature.


return to the latest published articles