Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Tokamak assembly | The "module" has landed

    This 'module' was not designed to land on the Moon. But it was as complex a piece of technology, requiring as much precision in its handling as the famed 'lunar [...]

    Read more

  • Remembering Bernard Bigot, ITER Director-General 2015-2022

    On the ITER site, the machinery of construction was humming just like on any weekday. Workers were concentrating on their tasks, laying rebar for new buildings [...]

    Read more

  • Tokamak assembly | Preparing for the Big Lift

    The distance was short but the challenge daunting: on Thursday last week, the first section of the plasma chamber was lifted 50 centimetres above its suppor [...]

    Read more

  • Image of the week | 13th toroidal field coil arrives from Europe

    The toroidal field coil procurement effort has been one of the longest of the ITER program, initiated by Procurement Arrangements signed in 2007 and 2008. Manuf [...]

    Read more

  • Diagnostics | Final Procurement Arrangement signed

    ITER Diagnostics reached an important milestone in December 2021 when it concluded the last Procurement Arrangement of the diagnostics program. After signing a [...]

    Read more

Of Interest

See archived entries

US deliveries continue for ITER electrical network

The United States is providing 75 percent of the steady state electrical network components, like this large high-voltage transformer. All of these components have to be installer by October 2015, when the site power demand will exceed the capacity of the temporary 15 kV supply line now in use. (Click to view larger version...)
The United States is providing 75 percent of the steady state electrical network components, like this large high-voltage transformer. All of these components have to be installer by October 2015, when the site power demand will exceed the capacity of the temporary 15 kV supply line now in use.
Since September, the US Domestic Agency has been shipping components for ITER's steady state electrical network. High voltage surge arrestors, circuit breakers, switches, current and voltage transformers, substation hardware, control and protection components, and earthing resistors have all reached site successfully and in mid-November, US-procured high voltage substation transformers left Korea for the ITER site after fabrication by vendor Hyundai Heavy Industries.

All of these components are necessary to power up the steady state electrical network by October 2015, when the site power demand will exceed the capacity of the temporary 15 kV supply line now in use.

Because of a well-coordinated team effort involving Princeton Plasma Physics Laboratory (PPPL), the US ITER Project Office at Oak Ridge National Laboratory, URS Corporation and the ITER Organization, the first eight deliveries were completed on schedule.

"This achievement is especially notable because many of the processes and procedures associated with the logistics service provider's delivery of components to the ITER site were exercised for the first time," said Charles Neumeyer, the PPPL-based US ITER team lead for the steady state electrical network.

The United States is providing 75 percent of the steady state electrical network components. The electrical network is essential for supplying conventional power needs at the ITER site, including the pumps and heat exchangers of the tokamak cooling water system and the cryogenic plant that supplies liquid helium to the superconducting magnets. The European Union will provide the remainder of the electrical network hardware and will also handle installation.

During 2015, the United States will also deliver drain tanks for the tokamak cooling water system and toroidal field coil conductors for the magnet systems.


return to the latest published articles