Subscribe options

Select your newsletters:

Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Cryolines | Another day, another spool

    Having wedged his body and equipment into the cramped space between the ceiling and the massive pipe, a worker is busy welding two cryolines spools. A few metre [...]

    Read more

  • Image of the week | Bearings unveiled

    The construction teams are in the last stages of preparing the Tokamak pit for the first major operation of ITER machine assembly: the lowering of the cryostat [...]

    Read more

  • Technology | Perfecting tritium breeding for DEMO and beyond

    While ITER will never breed tritium for its own consumption, it will test breeding blanket concepts—the tools and techniques that designers of future DEMO react [...]

    Read more

  • Fusion world | Japan and Europe complete the assembly of JT-60SA

    The JT-60SA fusion experiment in Naka, Japan, is designed to explore advanced plasma physics in support of the operation of ITER and next-phase devices. After s [...]

    Read more

  • Manufacturing | Thermal shield milestone in Korea

    Six years after the start of fabrication, Korean contractor SFA has completed the last 40° sector of vacuum vessel thermal shield. The stainless steel panels, c [...]

    Read more

Of Interest

See archived entries

US deliveries continue for ITER electrical network

The United States is providing 75 percent of the steady state electrical network components, like this large high-voltage transformer. All of these components have to be installer by October 2015, when the site power demand will exceed the capacity of the temporary 15 kV supply line now in use. (Click to view larger version...)
The United States is providing 75 percent of the steady state electrical network components, like this large high-voltage transformer. All of these components have to be installer by October 2015, when the site power demand will exceed the capacity of the temporary 15 kV supply line now in use.
Since September, the US Domestic Agency has been shipping components for ITER's steady state electrical network. High voltage surge arrestors, circuit breakers, switches, current and voltage transformers, substation hardware, control and protection components, and earthing resistors have all reached site successfully and in mid-November, US-procured high voltage substation transformers left Korea for the ITER site after fabrication by vendor Hyundai Heavy Industries.

All of these components are necessary to power up the steady state electrical network by October 2015, when the site power demand will exceed the capacity of the temporary 15 kV supply line now in use.

Because of a well-coordinated team effort involving Princeton Plasma Physics Laboratory (PPPL), the US ITER Project Office at Oak Ridge National Laboratory, URS Corporation and the ITER Organization, the first eight deliveries were completed on schedule.

"This achievement is especially notable because many of the processes and procedures associated with the logistics service provider's delivery of components to the ITER site were exercised for the first time," said Charles Neumeyer, the PPPL-based US ITER team lead for the steady state electrical network.

The United States is providing 75 percent of the steady state electrical network components. The electrical network is essential for supplying conventional power needs at the ITER site, including the pumps and heat exchangers of the tokamak cooling water system and the cryogenic plant that supplies liquid helium to the superconducting magnets. The European Union will provide the remainder of the electrical network hardware and will also handle installation.

During 2015, the United States will also deliver drain tanks for the tokamak cooling water system and toroidal field coil conductors for the magnet systems.


return to the latest published articles