Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Top management | Tim Luce, Head of Science & Operation

    What does a seven-year-old growing up in a small community in Arkansas know about what it means to be an 'atomic scientist'? Probably not much. Except, remember [...]

    Read more

  • Blanket shield blocks | Series production milestone in Korea

    It takes many months for a single forged block of stainless steel to be transformed into the complex shape of an ITER blanket shield block, full of gullies, cha [...]

    Read more

  • Image of the week | 5 top lid segments expected

    A little less than five years ago, in December 2015, the first segments of the ITER cryostat (out of a total of 54) were delivered to the construction site from [...]

    Read more

  • On site | As ITER begins assembly, HVAC becomes mission critical

    Not only will heating, ventilation and air conditioning (HVAC) help protect people and equipment during the assembly phase at ITER, but they will also help ensu [...]

    Read more

  • Vacuum vessel | Sector #6 is leak tight

    The first ITER vacuum vessel sector has passed a helium leak test on site with flying colours. Back in March 2020, as experts from the Korean Domestic Agency [...]

    Read more

Of Interest

See archived entries

Procurement Arrangements now total 90.53% of ITER in-kind value

Sabina Griffith

On 15 December 2014, ITER Director-General Osamu Motojima signed three Procurement Arrangements: the Electron Cyclotron Plant Controller and the Subsystem Control Unit Procurement Arrangement; the In-Vessel Viewing System Procurement Arrangement (pictured); and the Blanket Module Connector Procurement Arrangement (see next picture). (Click to view larger version...)
On 15 December 2014, ITER Director-General Osamu Motojima signed three Procurement Arrangements: the Electron Cyclotron Plant Controller and the Subsystem Control Unit Procurement Arrangement; the In-Vessel Viewing System Procurement Arrangement (pictured); and the Blanket Module Connector Procurement Arrangement (see next picture).
With the recent conclusion of three new Procurement Arrangements, the number of Procurement Arrangements signed with the ITER Domestic Agencies since 2007 has reached 104, representing 90.53 percent of the in-kind value of the project. 
 
On 15 December 2014, ITER Director-General Osamu Motojima signed the Electron Cyclotron Plant Controller and the Subsystem Control Unit Procurement Arrangement. The plant controller is the master control system that will oversee the configuration and operation of the entire electron cyclotron plant, protecting the system against potentially damaging events such as loss of vacuum or arcs in the transmission lines or in the diamond windows. The plant controller is also in charge of managing the stop requests sent by ITER's central interlock system. The subsystem control unit oversees the operation and monitoring of the electron cyclotron upper launchers, implements local protection functions and interfaces with the electron cyclotron plant control system. This system will be procured by the European Domestic Agency.

The In-Vessel Viewing System Procurement Arrangement, also concluded with Europe, covers the system that will be deployed between plasma pulses (or during the shutdown of the machine) to perform visual examination and metrology of the plasma-facing components. It will be able to visualize, on demand, the whole interior surface of the vacuum vessel with a lateral resolution in the range of 1 to 3 mm and create a 3D map with a depth resolution of 0.1 to 0.5 mm. The in-vessel viewing system will allow operators to assess the effect of transient events such as disruptions or vertical displacement events; in the latter case, the system will perform the long-term assessment of the overall erosion of the blanket first wall. The in-vessel viewing system is based on the principle of laser-scanning.

The Blanket Module Connector Procurement Arrangement, signed at ITER and countersigned in Russia, covers the set of connections between the blanket modules and the vacuum vessel that will accommodate for the large electromagnetic loads and keep blanket modules from moving. (Click to view larger version...)
The Blanket Module Connector Procurement Arrangement, signed at ITER and countersigned in Russia, covers the set of connections between the blanket modules and the vacuum vessel that will accommodate for the large electromagnetic loads and keep blanket modules from moving.
The final Procurement Arrangement, signed with Russia, covers a set of connections between the blanket modules and the vacuum vessel (Blanket Module Connectors) that will accommodate for the large electromagnetic loads expected during off-normal plasma events and keep blanket modules from moving in radial, poloidal and toroidal directions. The 1,760 connectors will be produced in Russia out of extra high tensile steel.

A complementary diagnostic arrangement (CDP) was also signed with Russia for the Vertical Neutron Camera, a diagnostic system that will enable—through the direct measurement of neutrons during operation—to demonstrate the achievement of fusion on a reactor scale.

All Procurement Arrangements have been countersigned by the respective Domestic Agencies.