Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Cryopumps | First unit reaches ITER

    The ITER vacuum team, the European Domestic Agency Fusion for Energy, Research Instruments (RI), and the ITER Director-General were all excited to welcome the d [...]

    Read more

  • Tritium Plant Summit | A shared vision to prepare for delivery

    A summit organized at ITER Headquarters from 3 to 6 June brought together the international teams that will deliver the sub-systems of the ITER Tritium Plant. I [...]

    Read more

  • Image of the week | ITER Robots goes international

    Thinking outside the box, teamwork and ingenuity are the ingredients that make for a successful robotics engineer—all qualities that are cultivated by participa [...]

    Read more

  • In memoriam | Physicist Michael Lehnen

    The ITER Organization mourns the passing of an outstanding physicist and beloved colleague. It is with the deepest sadness and a profound sense of loss that we [...]

    Read more

  • 34th ITER Council | Updated baseline presented

    Nearly 100 people met for two days this week for the 34th Meeting of the ITER Council. The meeting was an important one, as the ITER Organization and the D [...]

    Read more

Of Interest

See archived entries

Managing ITER assembly: a clear framework for the future

The Construction Project Management Plan details the required actions during the phase leading up to assembly, during construction execution and, finally, when the testing is complete and the facility is turned over for operations. (Click to view larger version...)
The Construction Project Management Plan details the required actions during the phase leading up to assembly, during construction execution and, finally, when the testing is complete and the facility is turned over for operations.
The Assembly & Operations Division achieved an important milestone at the end of 2014, as it completed the last volume in a suite of management plans for the assembly of the ITER Tokamak and the installation of plant systems.

These plans define how the works will be organized and managed on the site in the next phase of the project—once the buildings are completed and handed over by the European Domestic Agency. The ITER Organization then has full responsibility for the integration, assembly and testing of components delivered to the ITER site by the seven ITER Members.

The plans describe the Organization's overarching vision of how it will prepare, manage, control and complete the construction of millions of pieces that make up the ITER Tokamak and plant systems (electrical, cooling, fuelling, heating and diagnostic systems).

"These documents form the basis of Assembly & Operations work today and for the next 18 to 24 months," says Steve Gilligan, the Assembly & Planning Responsible Officer in charge of elaborating the 450 pages of the Construction Project Management Plan. "They allow the Division to implement an assembly baseline, prepare contracts, and get industry on board to start the work."

The 17 volumes of the plan form the basis of Assembly & Operations work today and for the next 18 to 24 months, allowing the Division to implement an assembly baseline, prepare contracts, and get industry on board to start the work. (Click to view larger version...)
The 17 volumes of the plan form the basis of Assembly & Operations work today and for the next 18 to 24 months, allowing the Division to implement an assembly baseline, prepare contracts, and get industry on board to start the work.
The 17 volumes of the plan were reviewed one by one through ITER's Management and Quality Program—a key process for a licenced basic nuclear facility.

"Our management plan reflects lessons learned in other huge construction and assembly projects," says Steve. "We have collected 'return on experience' data and consulted the best experts from industry and projects around the world to learn lessons. These have then been tailored to meet the special complexities of ITER, to ensure that what we'll go forward with is correct for a project like ITER."

Whether describing the management of human resources, safety, requirements, cost or change control, each volume of the management plan is functionally written, detailing the required actions during the phase leading up to assembly (front-end planning), working alongside industry during execution, and finally when the testing is complete and the facility is turned over for operations.

The plan will now be further developed through ITER's continuous improvement strategy, and underpinned through detailed working instructions, templates and guidelines.

"These plans define an effective and consistent management approach and processes for the ITER Organization, Domestic Agencies and their contractors during assembly, installation and testing," says Rem Haange, head of the ITER Project Department. "My experience shows that when it comes to assembling something as hugely complex as the ITER machine, very detailed, accurate planning is essential for smoother assembly operations and to reach our ultimate goal—to demonstrate the feasibility of fusion energy—more quickly."