Subscribe options

Select your newsletters:

Please enter your email address:

@

News & Media

Latest ITER Newsline

  • WEST | Revamped tokamak completes 1st phase of operation

    One day, in the latter half of this decade, it will be routine at ITER: dozens of operators, with eyes riveted to their individual monitors as numbers, graphs a [...]

    Read more

  • Roof modules | Patience, precision and a crane's long arm

    In the spring of 2020 a new and strategic phase of ITER construction will begin: the assembly of the ITER Tokamak. In order to deliver machine components to the [...]

    Read more

  • Image of the week | "Bringing light and hope"

    Most international organizations are headquartered in large cities—the UN in New York, UNESCO and the International Energy Agency in Paris, the IAEA in Vienna, [...]

    Read more

  • Outreach in China | A week devoted to fusion

    A new biennial event in China seeks to create a comprehensive exchange platform for the scientists, engineers and industries that are driving the country's stro [...]

    Read more

  • Monaco-ITER Fellows | New campaign announced

    The seventh recruitment campaign for the Monaco-ITER postdoctoral fellowship program opens on 13 January. Since 2008, thirty postdocs have carried out origin [...]

    Read more

Of Interest

See archived entries

Laying tracks for the elevated railway

R.A.

They're as thick and strong as railroad tracks and could easily carry the equivalent of four TGVs, two Eurostars or 15 steam locomotives. The steel rails that are being installed 43 metres above the basemat of the Assembly Hall are an essential part of the lifting system that will handle components weighing up to 1,500 tonnes.

43 metres above the basemat of the Assembly Hall, workers are laying the rails for the lifting system that will handle components weighing up to 1,500 tonnes. (Click to view larger version...)
43 metres above the basemat of the Assembly Hall, workers are laying the rails for the lifting system that will handle components weighing up to 1,500 tonnes.
When rails are laid on the ground, they rest on a bed of crushed stone (the track ballast) that distributes the load of the passing trains. In the ITER Assembly Hall, the ballast role is played by massive steel elements (9.3 metres long, 20 tonnes) called railway beams.

Resting on the vertical pillars of the Assembly Hall and running the entire length of the building, the railway beams form a perfectly smooth steel track upon which the rails can be affixed.

It will take a few weeks to install the rails and fine tune their alignment. (Click to view larger version...)
It will take a few weeks to install the rails and fine tune their alignment.
On Thursday 12 May, on the north side of the Assembly Hall, the first 18-metre length of rail was lifted, carefully deposited and fastened with heavy clips to the ledge formed by the railway beams. It will take a few weeks to install the rails and fine tune their alignment in time for the installation, beginning next month, of the girders and trolleys of the travelling crane.