Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • On site | ITER celebrates important milestones

    On 16 June 2022, the ITER amphitheatre was packed with life again after two years of silence, part of a new project culture initiative called "Commit to De [...]

    Read more

  • Port cell maintenance | A full-scale mockup for dress rehearsals

    Every port in the ITER vacuum vessel has a corresponding port cell in the Tokamak Building. These corridor-like spaces allow heating and fuelling pipes, electri [...]

    Read more

  • Magnets | Have the last pancake!

    After close to five years of intense activity, the winding table at the south end of the European poloidal field coil factory on site is now empty. Last week, t [...]

    Read more

  • 30th ITER Council: Progress in a time of challenge and transition

    The Council chamber on the fifth floor of the ITER Headquarters building resonated once again with the sound of voices as Member representatives gathered for th [...]

    Read more

  • Open Doors Day | Back together again

    After more than two years, ITER has resumed a tradition that dates back to 2007—Open Doors Day. On Saturday 18 June, more than 50 "volunteers," staff [...]

    Read more

Of Interest

See archived entries

"Topping out" RES cooling towers

Work on the Nuclear Propulsion Test Reactor (RES) began in the mid 1990s and should be complete by 2012. © CEA / Le Senechal (Click to view larger version...)
Work on the Nuclear Propulsion Test Reactor (RES) began in the mid 1990s and should be complete by 2012. © CEA / Le Senechal
The development of nuclear propulsion reactors for the French Navy was one of the main reasons why CEA-Cadarache was established in 1959. Half a century later, it's the fourth generation of nuclear boilers that is being developed there.

Work on the Nuclear Propulsion Test Reactor (RES) began in the mid-1990s and should be complete by 2012. A research installation more than an actual prototype, RES will act as support for the French nuclear fleet and contribute to the training of their officers. It will also test new fuels and new core architectures, validate computational models and simulations, and qualify new concepts.

In July 2005, the reactor's 820-tonne containment system was assembled on site and moved into the reactor building, using 36-wheel transport platform similar to the ones that will deliver the largest ITER components to the ITER site. Less than two years later, the reactor vessel was inserted into the containment system.

Following construction tradition, a small tree was placed last week on the roof of the concrete structure that will host the RES atmospheric cooling system. © CEA / Le Senechal (Click to view larger version...)
Following construction tradition, a small tree was placed last week on the roof of the concrete structure that will host the RES atmospheric cooling system. © CEA / Le Senechal
Next to the main building, work is ongoing for the concrete structure that will host the atmospheric cooling system. These "cooling towers" will dissipate the residual energy from the reactor. Last week, as work on the tallest part of the structure was completed, a small tree was placed on the roof and hung with garlands—a construction tradition that originates in Eastern Europe and is called "topping out."



return to the latest published articles