Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Without minimizing challenges, Council reaffirms commitment

    On 24 October 2007, the ITER Organization was officially established following the ratification by the seven ITER Members of the project's constitutive document [...]

    Read more

  • Heat waves

    Plasma is like a tenuous mist of particles—light atoms that have been dissociated into ions (the atom nucleus) and free-roaming electrons. In order to study pla [...]

    Read more

  • What a difference ten days make

    There was a time when progress in Tokamak Complex construction was easy to follow.Excavation in 2010; the creation of the ground support structure and seismic f [...]

    Read more

  • What's in the box?

    At ITER, even the opening of a box takes on a spectacular dimension. The operation requires a powerful crane, a full team of specialists and, as everything ITER [...]

    Read more

  • EU Commission has "positive appreciation" of ITER progress

    On 14 June, the European Commission issued a Communication presenting the revised schedule and budget estimates for European participation in ITER. Its object? [...]

    Read more

Of Interest

See archived articles

Preparing for a Wow! moment

In a few weeks, a spectacular operation will unfold in the Assembly Hall: the four girders and corresponding trolleys that form the double overhead crane will be lifted into position, some 43 metres above the basemat.

In the Poloidal Field Coils Winding Facility workers are busy installing the accessories and electrical equipement of the four 155-tonne girders that will form the Assembly Hall's double overhead travelling crane. (Click to view larger version...)
In the Poloidal Field Coils Winding Facility workers are busy installing the accessories and electrical equipement of the four 155-tonne girders that will form the Assembly Hall's double overhead travelling crane.
Most of the elements that will form this exceptionally powerful lifting tool have been delivered to ITER─the four girders, each weighing 155 tonnes, arrived in March and April, and the four trolley structures in mid-May. As for the drums, they will be in this week.

In order to prepare for the installation, similar operations are underway at both ends of the ITER site.

At the north end of the Poloidal Field Coils Winding Facility where the girders have been stored since their delivery, workers are busy installing bogies (also called "trucks"), gear-motors, braces and the electrical equipment that will power both cranes and trolleys.

In the storage area at the entrance of the site, work began today to install equipment on two of the four trolleys—this work will gain momentum when the drums are delivered in mid-week.

Once all the equipment and accessories are installed, girders and trolleys will be moved to the Assembly Hall. A powerful crawler crane, operating from outside the building, will pass its hook through an opening in the roof and lift the components according to a carefully planned sequence of events.

Considering the height of the Assembly Hall structure, the weight and size of the components to install, and the required precision, the operation promises to be one of the Wow! moments of ITER construction.


return to the latest published articles