Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • The crown's jewels

    They are the jewels of the concrete crown that will support the combined mass of the Tokamak and its surrounding cryostat: 18 perfectly polished, chrome-plated [...]

    Read more

  • "Making the best of fusion installations in Europe"

    With the recent addition of the Ukraine's Kharkov Institute for Physics and Technology (KIPT), the EUROfusion consortium now encompasses 30 European fusion labo [...]

    Read more

  • New cryostat manufacturing milestone

    They all gathered—members of the ITER-India team and contractor Larsen & Toubro—to mark a portentous moment: the start of manufacturing on the upper cylinde [...]

    Read more

  • Key power supply elements pass tests in Russia

    Since the signature of a Procurement Arrangement in 2011 with Russia for switching networks, fast discharge units, DC busbars and instrumentation—all key elemen [...]

    Read more

  • First vessel subassembly achieved in Europe

    Nine massive steel sectors deliveredby the Domestic Agencies of Europe (five sectors) and Korea (four sectors) will be welded together on site during the assemb [...]

    Read more

Of Interest

See archived articles

Preparing for a Wow! moment

In a few weeks, a spectacular operation will unfold in the Assembly Hall: the four girders and corresponding trolleys that form the double overhead crane will be lifted into position, some 43 metres above the basemat.

In the Poloidal Field Coils Winding Facility workers are busy installing the accessories and electrical equipement of the four 155-tonne girders that will form the Assembly Hall's double overhead travelling crane. (Click to view larger version...)
In the Poloidal Field Coils Winding Facility workers are busy installing the accessories and electrical equipement of the four 155-tonne girders that will form the Assembly Hall's double overhead travelling crane.
Most of the elements that will form this exceptionally powerful lifting tool have been delivered to ITER─the four girders, each weighing 155 tonnes, arrived in March and April, and the four trolley structures in mid-May. As for the drums, they will be in this week.

In order to prepare for the installation, similar operations are underway at both ends of the ITER site.

At the north end of the Poloidal Field Coils Winding Facility where the girders have been stored since their delivery, workers are busy installing bogies (also called "trucks"), gear-motors, braces and the electrical equipment that will power both cranes and trolleys.

In the storage area at the entrance of the site, work began today to install equipment on two of the four trolleys—this work will gain momentum when the drums are delivered in mid-week.

Once all the equipment and accessories are installed, girders and trolleys will be moved to the Assembly Hall. A powerful crawler crane, operating from outside the building, will pass its hook through an opening in the roof and lift the components according to a carefully planned sequence of events.

Considering the height of the Assembly Hall structure, the weight and size of the components to install, and the required precision, the operation promises to be one of the Wow! moments of ITER construction.


return to the latest published articles