Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Upper ports | A very international effort

    The 18 upper ports of the ITER vacuum vessel are procured by Russia, manufactured in Germany, and mounted (in part) on the vessel sectors by contractors in Ital [...]

    Read more

  • Paint job | One level done, five to go

    The job is done and the effect is spectacular. At the deepest basement level (B2) of the Tokamak Building, the floors, walls, and ceilings are now perfectly whi [...]

    Read more

  • On site | Through the eyes of a crane operator

    Sitting in his cabin 80 metres above the ground, Alex Dumonteil enjoys a most spectacular view. To the north, on a clear day, he can see as far as the Alpine ri [...]

    Read more

  • Poloidal field coil #6 | The home stretch

    In Hefei, China, a 400-tonne ring magnet procured by the European Domestic Agency is entering the final phase of production—resin impregnation. In just over one [...]

    Read more

  • Neutral Beam Test Facility | SPIDER gets a beam for its first birthday

    Just one year ago, on 11 June 2018, the world's largest negative ion source was inaugurated at the ITER Neutral Beam Test Facility with the ignition of a brief [...]

    Read more

Of Interest

See archived entries

It's now official: First Plasma in December 2025

ITER Communication

A two-year effort by the ITER Organization and the seven Domestic Agencies came to fruition on 16 June, as the ITER Council officially announced its endorsement of the Resource-Loaded Integrated Schedule for the ITER Project, which identifies the date of First Plasma as December 2025.

On Thursday 16 June, the ITER Council officially announced its endorsement of the Resource-Loaded Integrated Schedule for the ITER Project, which identifies the date of First Plasma as December 2025.<br /><br /> (Click to view larger version...)
On Thursday 16 June, the ITER Council officially announced its endorsement of the Resource-Loaded Integrated Schedule for the ITER Project, which identifies the date of First Plasma as December 2025.

While the ITER Council acknowledges that the endorsed schedule to First Plasma is "challenging but technically achievable," it considers that by meeting all project milestones* to date, on or ahead of schedule, the ITER Organization and Domestic Agencies have already demonstrated their "collective capacity" to deliver on the updated schedule.

The updated Integrated Schedule represents "the best technically achievable path forward to First Plasma."

The Council highlighted the renewed confidence that results from evidence of increased effectiveness of decision-making, improved understanding of risks, and rigour in adhering to commitments.

First Plasma, however, is just the beginning of the road. The Council has asked the ITER Organization to lead the effort to extend the updated schedule through nuclear (deuterium-tritium) operation. Council expects a proposal "with sufficient detail" to enable the adoption of an updated project baseline at its next meeting in November.

"Although all of the Members have certain constraints due to their respective political and administrative processes at home," said Council Chair Won Namkung in his opening remarks, "I have no doubt about the commitment of all of us here today for the success of the project, and in providing utmost support to Domestic Agencies and the Director-General of the ITER Organization."

* During its Seventeenth Meeting in November 2015, the ITER Council approved a number of high-level project milestones for 2016-2017, against which the performance of the project could be monitored.
 
Click to read the Press Release in English or French.