Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Fusion world | Public/private consortium is building the DTT tokamak

    The Divertor Test Tokamak in Italy is creating a new model for engagement with industry in fusion research. ITER helped to pave the way. The Divertor Test Tokam [...]

    Read more

  • Image of the week | An architectural paradox

    There is something deliberately paradoxical in the architectural treatment of the ITER buildings. On the one hand, the alternation between the mirror-like stai [...]

    Read more

  • Former French Prime Minister | A fan then and now

    For Jean-Pierre Raffarin, former Prime Minister of France (2002-2005) who visited ITER on Friday 15 March, touring the ITER installation with ITER Director-Gene [...]

    Read more

  • CARE at ITER | New project values launched

    Collaboration, Accountability, Respect and Excellence drive the future of fusion for a diverse staff. When Pietro Barabaschi joined as ITER Director-General to [...]

    Read more

  • Blanket | Midway through shield block procurement

    It all begins with a forged stainless-steel block weighing nine tonnes. As machining and deep-drilling operations commence, the rectangular block progressively [...]

    Read more

Of Interest

See archived entries

It's now official: First Plasma in December 2025

A two-year effort by the ITER Organization and the seven Domestic Agencies came to fruition on 16 June, as the ITER Council officially announced its endorsement of the Resource-Loaded Integrated Schedule for the ITER Project, which identifies the date of First Plasma as December 2025.

On Thursday 16 June, the ITER Council officially announced its endorsement of the Resource-Loaded Integrated Schedule for the ITER Project, which identifies the date of First Plasma as December 2025.<br /><br /> (Click to view larger version...)
On Thursday 16 June, the ITER Council officially announced its endorsement of the Resource-Loaded Integrated Schedule for the ITER Project, which identifies the date of First Plasma as December 2025.

While the ITER Council acknowledges that the endorsed schedule to First Plasma is "challenging but technically achievable," it considers that by meeting all project milestones* to date, on or ahead of schedule, the ITER Organization and Domestic Agencies have already demonstrated their "collective capacity" to deliver on the updated schedule.

The updated Integrated Schedule represents "the best technically achievable path forward to First Plasma."

The Council highlighted the renewed confidence that results from evidence of increased effectiveness of decision-making, improved understanding of risks, and rigour in adhering to commitments.

First Plasma, however, is just the beginning of the road. The Council has asked the ITER Organization to lead the effort to extend the updated schedule through nuclear (deuterium-tritium) operation. Council expects a proposal "with sufficient detail" to enable the adoption of an updated project baseline at its next meeting in November.

"Although all of the Members have certain constraints due to their respective political and administrative processes at home," said Council Chair Won Namkung in his opening remarks, "I have no doubt about the commitment of all of us here today for the success of the project, and in providing utmost support to Domestic Agencies and the Director-General of the ITER Organization."

* During its Seventeenth Meeting in November 2015, the ITER Council approved a number of high-level project milestones for 2016-2017, against which the performance of the project could be monitored.
 
Click to read the Press Release in English or French.