Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Cryoplant | Filled from floor to ceiling

    The ITER cryoplant used to be a vast echoey chamber with 5,400 m² of interior space divided into two areas; now, it is filled from floor to ceiling with industr [...]

    Read more

  • Cryostat | Adjusting, welding, testing ...

    The assembly of the ITER cryostat—the stainless steel "thermos" that insulates the ultra-cold superconducting magnets from the environment—is progress [...]

    Read more

  • Tokamak Building | Full steam ahead

    In this central arena of the construction site, construction teams are active three shifts a day—two full work shifts and a third, at night, dedicated to moving [...]

    Read more

  • Poloidal field coils | Turning tables and hot resin

    One of only two manufacturing facilities located on the ITER site, the Poloidal Field Coils Winding Facility was constructed by Europe to house the winding, imp [...]

    Read more

  • Assembly Hall | One giant standing

    Two identical handling tools in the Assembly Hall will play a critical role in preparing ITER's nine vacuum vessel sectors for their final journey: transport by [...]

    Read more

Of Interest

See archived entries

It's now official: First Plasma in December 2025

ITER Communication

A two-year effort by the ITER Organization and the seven Domestic Agencies came to fruition on 16 June, as the ITER Council officially announced its endorsement of the Resource-Loaded Integrated Schedule for the ITER Project, which identifies the date of First Plasma as December 2025.

On Thursday 16 June, the ITER Council officially announced its endorsement of the Resource-Loaded Integrated Schedule for the ITER Project, which identifies the date of First Plasma as December 2025.<br /><br /> (Click to view larger version...)
On Thursday 16 June, the ITER Council officially announced its endorsement of the Resource-Loaded Integrated Schedule for the ITER Project, which identifies the date of First Plasma as December 2025.

While the ITER Council acknowledges that the endorsed schedule to First Plasma is "challenging but technically achievable," it considers that by meeting all project milestones* to date, on or ahead of schedule, the ITER Organization and Domestic Agencies have already demonstrated their "collective capacity" to deliver on the updated schedule.

The updated Integrated Schedule represents "the best technically achievable path forward to First Plasma."

The Council highlighted the renewed confidence that results from evidence of increased effectiveness of decision-making, improved understanding of risks, and rigour in adhering to commitments.

First Plasma, however, is just the beginning of the road. The Council has asked the ITER Organization to lead the effort to extend the updated schedule through nuclear (deuterium-tritium) operation. Council expects a proposal "with sufficient detail" to enable the adoption of an updated project baseline at its next meeting in November.

"Although all of the Members have certain constraints due to their respective political and administrative processes at home," said Council Chair Won Namkung in his opening remarks, "I have no doubt about the commitment of all of us here today for the success of the project, and in providing utmost support to Domestic Agencies and the Director-General of the ITER Organization."

* During its Seventeenth Meeting in November 2015, the ITER Council approved a number of high-level project milestones for 2016-2017, against which the performance of the project could be monitored.
 
Click to read the Press Release in English or French.
See the photo gallery below.

 