Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • The making of a ring coil—a photo story

    From one end to the other of the on-site manufacturing facility for poloidal field coils, the different production stations are now clearly delimited, with tool [...]

    Read more

  • An unexpected fusion spinoff: aircraft carrier catapult

    The US company General Atomics is fabricating the 'beating heart of ITER,' an electromagnet called the central solenoid that is so large and powerful, that its [...]

    Read more

  • First steps towards "energizing"

    It takes more than the flipping of a switch to connect the ITER site to the French national grid. The operation, called a 'first energizing,' is a complex, step [...]

    Read more

  • The bioshield rises

    The bioshield structure is rising at the heart of the Tokamak Building. The last plot of the B1 level was poured last week; about half of the first ground level [...]

    Read more

  • Barcelona Supercomputer Center and ITER strengthen ties

    In a Memorandum of Understanding signed on 12 January 2017, the ITER Organization and the Barcelona Supercomputing Center (BSC) in Spain have agreed 'to promote [...]

    Read more

Of Interest

See archived articles

Collaboration is in the pipes

Representatives of the different parties travelled together to India in early June, in a visit initiated by Sergio Orlandi, ITER head of Plant Engineering; Laurent Schmieder, site project manager and BIPS (Buildings Infrastructure and Power Supplies) leader; and Ajith Kumar, India project leader for the cooling water system. (Click to view larger version...)
Representatives of the different parties travelled together to India in early June, in a visit initiated by Sergio Orlandi, ITER head of Plant Engineering; Laurent Schmieder, site project manager and BIPS (Buildings Infrastructure and Power Supplies) leader; and Ajith Kumar, India project leader for the cooling water system.
The installation of buried pipes for ITER's cooling water system is a first-phase assembly activity that must be carried out before other site infrastructure works for the cooling water system can be initiated.

While the design and procurement of the Component Cooling Water System (CCWS), the Chilled Water System (CHWS) and the Heat Rejection System (HRS)—including piping—is part of India's procurement responsibilities for ITER, the European Domestic Agency is responsible for the installation of the buried piping for these systems on the platform.

The work will fall under a general infrastructure contract signed between Europe and the consortium Spie Batignolles Group (Spie Batignolles TPCI /Valérian/ADF) for on-site electricity and hydraulic networks.

As the start date of on-site infrastructure works approaches, close collaboration among the different parties is essential in order to ensure the best possible coordination between the arrival of the material and the work schedule for buried installation on site. The first deliveries from India have already reached ITER, closely monitored by representatives of the Indian and European Domestic Agencies, the ITER logistics team, and European contractors.

Standing in front of cooling water pipes CCWS1 in the Indian factory. The installation of buried piping will begin this summer. (Click to view larger version...)
Standing in front of cooling water pipes CCWS1 in the Indian factory. The installation of buried piping will begin this summer.
In the same collaborative spirit, representatives of the European Domestic Agency, architect engineer ENGAGE and implementation contractor ADF were invited to visit India together in early June, welcomed by the Indian Domestic Agency and contractor Larsen & Toubro. The aim was to review the coherence of manufacturing, delivery and installation schedules; discuss the site work procedures and quality processes to be respected; and see fabrication first hand at the factory.

The visit was productive for all and all deliveries corresponding to the first phase of site works are confirmed. The European contractors plan to start excavation works early this summer.


return to the latest published articles