  • Open Doors Day | An intense and unforgettable experience

    Saturday was Jacques's birthday. At age 90, the long-retired engineer from Aix-en-Provence had only one item on his wish list: to visit ITER for a third time an [...]

    Read more

  • Power conversion | A potent illustration of the "One ITER" spirit

    Europe made the buildings; the piping came from India; China and Korea provided the transformers; Russia manufactured the massive 'busbar' network. The ITER Org [...]

    Read more

  • Fusion world | Upgrade completed on DIII-D tokamak

    The DIII-D National Fusion Program (US) has completed a series of important enhancements to its fusion facility, providing researchers with several first-of-a-k [...]

    Read more

  • Vacuum lab | Ensuring leak test sensitivity

    A helium leak test is one of several factory acceptance tests planned for the sectors of the ITER vacuum vessel before they are shipped to ITER. In a vacuum lab [...]

    Read more

  • Bookmark | The Future of Fusion Energy

    To write about fusion is to walk a fine line between the temptation of lyricism and the arid demands of scientific accuracy. Whereas the general media tends to [...]

    Read more

Of Interest

See archived entries

ITER Council endorses updated project schedule

ITER Communication

During the Nineteenth Meeting of the ITER Council held last week from 16 to 17 November, representatives of the ITER Members reviewed the complete updated project schedule as proposed by the ITER Organization. The schedule, which covers the period up to First Plasma in 2025 and on to Deuterium-Tritium Operation in 2035, was approved by all Members.

During the Council meeting on 16-17 November, representatives of China, Europe, India, Japan, Korea, Russia and the United States discussed the detailed updated baseline (scope, schedule, cost and risks) for ITER through the start of Deuterium-Tritium Operation in 2035. (Click to view larger version...)
During the Council meeting on 16-17 November, representatives of China, Europe, India, Japan, Korea, Russia and the United States discussed the detailed updated baseline (scope, schedule, cost and risks) for ITER through the start of Deuterium-Tritium Operation in 2035.
Building on renewed confidence achieved through the past 18 months of sustained strong performance in construction and manufacturing, the updated 2016-2035 schedule reflects the consensus and integrated efforts of the ITER Organization and the seven Domestic Agencies.

The overall project schedule was approved by all ITER Members, and the overall project cost was approved ad referendum, meaning that it will now fall to each Member to seek approval of project costs through respective governmental budget processes.

The Council stressed that the successful completion of all 19 project milestones for 2016, on time and on budget, provides tangible evidence of full adherence to commitments by all Members. These milestones had been approved by the ITER Council one year ago as a way to track project momentum while discussions were underway on the long-term schedule.

The updated schedule through Deuterium-Tritium Operation (2035) selects a "staged approach" after First Plasma as a way to increase confidence and minimize risk. In the staged approach to assembling ITER, assembly phases will alternate with periods of operation.

Read the full press release in English or French.
View the photo gallery from the Nineteenth ITER Council (IC-19) below.