Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Building ITER | Halfway to First Plasma

    It's been a long road and we haven't reached our destination yet. But on its way to operation, ITER has just passed a significant milestone: according to the st [...]

    Read more

  • Director-General | Visits and an award in Washington

    Keeping the governments and policy makers of the ITER Members informed on the project's progress and challenges is an essential part of the Director-General's m [...]

    Read more

  • On-site coil winding | Big, round and red

    It's big, round and red and represents the latest addition to the collection of cranes operating on the ITER construction site. On Friday 8 November, two power [...]

    Read more

  • Milestones | Japan completes central solenoid conductor

    The Japanese Domestic Agency has successfully completed the procurement of 43 kilometres (700 tonnes) of niobium-tin cable-in-conduit superconductor for ITER's [...]

    Read more

  • Neutral beam test facility | Powerful ion source delivered

    OnSPIDER, one of twotestbeds at the ITER Neutral Beam Test Facility, the negative ion source for ITER's heating neutral beam system will be demonstrated at full [...]

    Read more

Of Interest

See archived articles

ITER Council endorses updated project schedule

ITER Communication

During the Nineteenth Meeting of the ITER Council held last week from 16 to 17 November, representatives of the ITER Members reviewed the complete updated project schedule as proposed by the ITER Organization. The schedule, which covers the period up to First Plasma in 2025 and on to Deuterium-Tritium Operation in 2035, was approved by all Members.

During the Council meeting on 16-17 November, representatives of China, Europe, India, Japan, Korea, Russia and the United States discussed the detailed updated baseline (scope, schedule, cost and risks) for ITER through the start of Deuterium-Tritium Operation in 2035. (Click to view larger version...)
During the Council meeting on 16-17 November, representatives of China, Europe, India, Japan, Korea, Russia and the United States discussed the detailed updated baseline (scope, schedule, cost and risks) for ITER through the start of Deuterium-Tritium Operation in 2035.
Building on renewed confidence achieved through the past 18 months of sustained strong performance in construction and manufacturing, the updated 2016-2035 schedule reflects the consensus and integrated efforts of the ITER Organization and the seven Domestic Agencies.

The overall project schedule was approved by all ITER Members, and the overall project cost was approved ad referendum, meaning that it will now fall to each Member to seek approval of project costs through respective governmental budget processes.

The Council stressed that the successful completion of all 19 project milestones for 2016, on time and on budget, provides tangible evidence of full adherence to commitments by all Members. These milestones had been approved by the ITER Council one year ago as a way to track project momentum while discussions were underway on the long-term schedule.

The updated schedule through Deuterium-Tritium Operation (2035) selects a "staged approach" after First Plasma as a way to increase confidence and minimize risk. In the staged approach to assembling ITER, assembly phases will alternate with periods of operation.

Read the full press release in English or French.