Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Image of the week | Tokamak-sur-mer

    At the height of the heat wave, in late June, surface temperature on the ITER worksite climbed to the 50 °C range. To continue work—and protect workers—a series [...]

    Read more

  • Space propulsion | Have fusion, will travel

    The idea of propelling rockets and spaceships using the power of the atom is nothing new: the Manhattan Project in the mid-1940s as well as countless endeavours [...]

    Read more

  • Cold fusion | End of story?

    Thirty years ago, two electrochemists at the University of Utah, Martin Fleischmann and Stanley Pons, created a sensation when they claimed they had achieved fu [...]

    Read more

  • Magnet feeders | Wave of deliveries ahead

    Several batches of magnet feeder components will arrive from China in September containing elements that need to be received, inspected and readied for installa [...]

    Read more

  • Tokamak cooling system procurement | Global team for better efficiency

    A unique work-sharing arrangement is expediting the design and fabrication of ITER's tokamak cooling water system and building the knowledge base that will be c [...]

    Read more

Of Interest

See archived entries

ITER Council endorses updated project schedule

ITER Communication

During the Nineteenth Meeting of the ITER Council held last week from 16 to 17 November, representatives of the ITER Members reviewed the complete updated project schedule as proposed by the ITER Organization. The schedule, which covers the period up to First Plasma in 2025 and on to Deuterium-Tritium Operation in 2035, was approved by all Members.

During the Council meeting on 16-17 November, representatives of China, Europe, India, Japan, Korea, Russia and the United States discussed the detailed updated baseline (scope, schedule, cost and risks) for ITER through the start of Deuterium-Tritium Operation in 2035. (Click to view larger version...)
During the Council meeting on 16-17 November, representatives of China, Europe, India, Japan, Korea, Russia and the United States discussed the detailed updated baseline (scope, schedule, cost and risks) for ITER through the start of Deuterium-Tritium Operation in 2035.
Building on renewed confidence achieved through the past 18 months of sustained strong performance in construction and manufacturing, the updated 2016-2035 schedule reflects the consensus and integrated efforts of the ITER Organization and the seven Domestic Agencies.

The overall project schedule was approved by all ITER Members, and the overall project cost was approved ad referendum, meaning that it will now fall to each Member to seek approval of project costs through respective governmental budget processes.

The Council stressed that the successful completion of all 19 project milestones for 2016, on time and on budget, provides tangible evidence of full adherence to commitments by all Members. These milestones had been approved by the ITER Council one year ago as a way to track project momentum while discussions were underway on the long-term schedule.

The updated schedule through Deuterium-Tritium Operation (2035) selects a "staged approach" after First Plasma as a way to increase confidence and minimize risk. In the staged approach to assembling ITER, assembly phases will alternate with periods of operation.

Read the full press release in English or French.