Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Worksite postcards | Under fog and autumn light

    Due to its proximity to the Durance River and to the narrow gully spanned by the Bridge of Mirabeau, the area around ITER often experiences a peculiar meteorolo [...]

    Read more

  • Assembly Hall | Another massive paint job

    By the end of December, the massive painting job in the Assembly Hall will be complete and the building's floor will be as white and pristine as the landscape i [...]

    Read more

  • ITER India | Testing a neutral beam for diagnostics

    Every 23 seconds during fusion operation, a probe beam will penetrate deep into the core of the ITER plasma to aid in the detection of helium ash—one of fusion' [...]

    Read more

  • Welded attachments | Follow the laser projections

    How do you position 150,000 welded attachments on to a vacuum vessel the size of a house, each one needing to be accurately placed to less than a 4 mm target? [...]

    Read more

  • Visit | Our neighbour the Nobel

    In 2018, the Nobel Prize in Physics was awarded to Gérard Mourou for his work on ultra-short, extremely high-intensity laser pulses—the so-called 'chirped pulse [...]

    Read more

Of Interest

See archived entries

First steps towards "energizing"

It takes more than the flipping of a switch to connect the ITER site to the French national grid. The operation, called a "first energizing," is a complex, step-by-step procedure that requires close coordination with the French transmission system operator RTE (Réseau de transport d'électricité).

ITER head of Plant Engineering Sergio Orlandi (centre) and the ITER ''electricians''—head of division Ivone Benfatto and section leader Joël Hourtoule, along with Jeremy Sanna and Marco Olivier—stand at the edge of the switchyard as operations unfold. Also present is head of Communications Laban Coblentz. (Click to view larger version...)
ITER head of Plant Engineering Sergio Orlandi (centre) and the ITER ''electricians''—head of division Ivone Benfatto and section leader Joël Hourtoule, along with Jeremy Sanna and Marco Olivier—stand at the edge of the switchyard as operations unfold. Also present is head of Communications Laban Coblentz.
For the moment, the electrical needs of the ITER worksite and buildings are covered by a 15 kV line extended from the neighbouring CEA research centre. But as activity increases the installation will feed directly from the grid through the switchyard that sprawls over four hectares at the southeast end of the platform.

Preparation for this moment—an ITER Council milestone to be achieved during the first quarter of 2017—began on Friday 20 January at the first of the seven switchyard's "bays." Busbars, switches, pantographs, breakers ... all of the complex equipment and systems that link the grid to the ITER transformers were activated and tested in close coordination with RTE control room in Marseille.

Tests will continue for the other bays individually and will conclude with the energization of the entire switchyard. The steady state electrical network (SSEN), which occupies four bays out of seven, is set to be operational in June, whereas the pulsed power electrical network (PPEN), which is only needed for Tokamak operation, will be energized at a later date.

Performed under "real" conditions, Friday's operations provided a precious opportunity to test and demonstrate the integration of the ITER installation (with all its specificities) into the environment of France's national grid. Beyond the technical dimension, they represented a full-fledged exercise in coordination, methodology, and safety procedures that will be applicable to other plant systems.


return to the latest published articles