Subscribe options

Select your newsletters:


Please enter your email address:

@

News & Media

Latest ITER Newsline

  • Rendezvous | D and T to meet at JET in 2020

    In 2020, for the first time in more than 20 years, a reaction that only occurs in the core of the stars will be produced on Earth in a man-made machine. In the [...]

    Read more

  • On site | MOMENTUM believes in recent graduates

    It is rare for students to leave university and immediately begin work on a globally significant project. But thanks to the graduate program run by the project' [...]

    Read more

  • Tokamak Pit | Big steel elbow in place

    A cryostat feedthrough delivered by the Chinese Domestic Agency has become the first metal component of the machine to be installed in the Tokamak Pit, in an op [...]

    Read more

  • Neutral beam source | Europe awards EUR 20 million contract

    The contract, awarded to ALSYOM-SEIV (ALCEN group, France), launches the manufacturing phase for the beam source that will come on line in 2022 as part of the f [...]

    Read more

  • Image of the week | US Under Secretary of Science tours site

    Five months, almost to the day, after the US Secretary of Energy Rick Perry visited ITER, his deputy, Under Secretary for Science Paul Dabbar, stood by the same [...]

    Read more

Of Interest

See archived entries

The wave factory

A year ago, work was just beginning on the steel reinforcement for the building's foundation slab. The Radio Frequency Heating Building is now nearing the last stages of completion.The space inside the 26-metre-tall building will be shared by two radio-wave-generating systems designed to feed energy, in the form of electromagnetic radiation, into the plasma.
 
Originally planned for installation inside the Assembly Hall, equipment for the electron and ion cyclotron external heating systems (power supplies and generators) now has a three-storey building of its own. Located adjacent to the emblematic 60-metre-tall Assembly Hall, the structure is in the last stages of completion, as insulation and cladding is installed on the facades and finishing works are underway inside. As a red delivery truck passes in front of the building, the elements for the first large sector sub-assembly tool wait under their green wrapping for installation in the Assembly Building. (Click to view larger version...)
Originally planned for installation inside the Assembly Hall, equipment for the electron and ion cyclotron external heating systems (power supplies and generators) now has a three-storey building of its own. Located adjacent to the emblematic 60-metre-tall Assembly Hall, the structure is in the last stages of completion, as insulation and cladding is installed on the facades and finishing works are underway inside. As a red delivery truck passes in front of the building, the elements for the first large sector sub-assembly tool wait under their green wrapping for installation in the Assembly Building.

Power supplies for both resonance heating systems (a total input of 100 MW) will occupy the better part of the first two floors, while the top floor will be reserved for the wave generators—gyrotrons for electron cyclotron resonance heating (ECRH) and ion for the ion cyclotron resonance heating (ICRH). The construction of the Radio Frequency Building is nearing completion, with small regions of the second and third floor to be poured and removable internal hatches to be installed. The final task for the structural part of the building will consist in inserting two overhead cranes. (Click to view larger version...)
Power supplies for both resonance heating systems (a total input of 100 MW) will occupy the better part of the first two floors, while the top floor will be reserved for the wave generators—gyrotrons for electron cyclotron resonance heating (ECRH) and ion for the ion cyclotron resonance heating (ICRH). The construction of the Radio Frequency Building is nearing completion, with small regions of the second and third floor to be poured and removable internal hatches to be installed. The final task for the structural part of the building will consist in inserting two overhead cranes.


return to the latest published articles