Enable Recite

Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the ITER Organization publication(s) that you have requested. ITER Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from ITER Organization.

For more information, see our Privacy policy.

News & Media

Latest ITER Newsline

  • Vacuum vessel | Second "jewel" to leave Korea

    A second 40-degree sector of the ITER vacuum vessel is about to leave the Hyundai Heavy Industries manufacturing facility in Ulsan, Korea, for shipment to ITER. [...]

    Read more

  • ITER Robots | The experts of tomorrow

    Robotics is at the heart of every major industrial project. In ITER, the operation of mobile automated systems will play a key role in assembling machine compon [...]

    Read more

  • Cryoline network | Now the vertical spools

    At the L3 level of the Tokamak Building, ceiling height in some galleries exceeds 10 metres. But when it comes to lifting a cryoline spool, tilting it 90 degree [...]

    Read more

  • In memoriam | Dhiraj Bora, leading contributor to fusion and ITER

    The ITER community was greatly saddened to learn of the passing of Dhiraj Bora, a well-known expert in plasma physics and tireless proponent of the ITER Project [...]

    Read more

  • Thermal shield portfolio | All shine and precision

    A cluster of polished metal and silver catches the eye at the far end of the Assembly Hall, as thermal shield panels join vacuum vessel #6 inside the arms of a [...]

    Read more

Of Interest

See archived entries

Ring magnets

Heaviest and first to go

The heaviest of ITER's ring magnets, poloidal field coil #6 (PF6), is taking shape at the Chinese Institute of Plasma Physics ASIPP under the terms of an agreement signed with the procuring party, Europe. Three of the nine spiralled coils of conductor ("double pancakes") required for the final assembly have been wound and one is in the final stages of vacuum impregnation. Nearly 80 people are involved with fabrication.

This double pancake is on its way to the next process station: impregnation. During vacuum pressure impregnation, epoxy resin is carefully injected and then cured to solidify. (Click to view larger version...)
This double pancake is on its way to the next process station: impregnation. During vacuum pressure impregnation, epoxy resin is carefully injected and then cured to solidify.
PF6, built from nine stacked double pancakes and finished off with clamps and a protective cover, will weigh 396 tonnes—11 tonnes more than the second-heaviest coil in the poloidal field series (#3). It is the only one made from nine double pancakes stacked; (the others require from six to eight).

Situated at the very bottom of the machine, PF6 is also the first poloidal field coil required in the ITER in-pit assembly sequence.

Fabrication activities are proceeding strongly at the ASIPP facility in Hefei, where niobium titanium superconductor produced in Europe is precisely wound into a double-layer "pancake" and insulated; "terminations" are created for the input of helium and for electrical current; and impregnation with epoxy resin is carried out.

An ASIPP technician is working to create a ''termination''—an opening through which the coil coolant (liquid helium) can be injected into the coil. The termination joints have been completed on two double pancakes for helium and current. (Click to view larger version...)
An ASIPP technician is working to create a ''termination''—an opening through which the coil coolant (liquid helium) can be injected into the coil. The termination joints have been completed on two double pancakes for helium and current.
At the end of the multi-stage fabrication process, the hardened double pancakes—nine in all—will be stacked to form the final PF#6 assembly and impregnated once again as a whole.

This final impregnation stage will be practised on a qualification mockup before the actual component is handled, a process that allows the tooling and methodologies to be tested.

By carrying out all the steps in the process on mockups first, tooling and techniques are confirmed before the work is carried out on actual components. Pictured: the vacuum impregnation of a ''dummy'' double pancake winding at ASIPP. (Click to view larger version...)
By carrying out all the steps in the process on mockups first, tooling and techniques are confirmed before the work is carried out on actual components. Pictured: the vacuum impregnation of a ''dummy'' double pancake winding at ASIPP.

The European Domestic Agency is responsible for procuring five of ITER's six poloidal field magnets. Work on poloidal field coils #2-5 is underway now in a European facility on the ITER site.

See the report published last week on the European Domestic Agency's website.


return to the latest published articles